Tokio Marine & Fire Insurance v. Western Pacific Roofing Corp.

89 Cal. Rptr. 2d 1, 75 Cal. App. 4th 110, 99 Cal. Daily Op. Serv. 7890, 99 Daily Journal DAR 10013, 1999 Cal. App. LEXIS 859
CourtCalifornia Court of Appeal
DecidedSeptember 22, 1999
DocketB125178
StatusPublished
Cited by27 cases

This text of 89 Cal. Rptr. 2d 1 (Tokio Marine & Fire Insurance v. Western Pacific Roofing Corp.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tokio Marine & Fire Insurance v. Western Pacific Roofing Corp., 89 Cal. Rptr. 2d 1, 75 Cal. App. 4th 110, 99 Cal. Daily Op. Serv. 7890, 99 Daily Journal DAR 10013, 1999 Cal. App. LEXIS 859 (Cal. Ct. App. 1999).

Opinion

*113 Opinion

ZEBROWSKI, J.

The trial court summarily named an insurer as an additional judgment debtor on the judgment in this case. Although the insurer insured a party to this action, the insurer itself was not a party and no basis appears on which it could be summarily named as a judgment debtor. We therefore reverse.

I. Factual and Procedural Background

In 1988, the Department of Water Resources contracted to have its Pearblossom Pumping Plant expanded. In 1991, as the expansion work progressed, a fire occurred, causing extensive damage. Prior to any litigation, an “Interim Funding Agreement” (IFA) was concluded among the general contractor (Torno America, Inc.), its insurer (Certain Underwriters at Lloyd’s, 1 appellants here), the roofing contractor (Western Pacific Roofing Corporation, respondent here) and its insurer (United States Fidelity & Guaranty Co.). Pursuant to the IFA, the insurers contributed funds in order to effect prompt repairs and mitigate damages. The IFA provided that the financial contributions were subject to reallocation by binding arbitration at a later date.

A different insurer (which had insured the supplier of pumping equipment damaged in the fire) later commenced subrogation litigation. Various cross-claims were then filed by a variety of parties, and a number of claims were settled. The remaining parties were then realigned so that the general contractor became the plaintiff and the roofing contractor became the defendant. In 1997, the case went to jury trial. Near the time of commencement of trial, a stipulation was executed. 2 The stipulation formed the basis of the judgment against the Underwriters which is the subject of this appeal.

On one side of the stipulation were the general contractor and its insurer (the Underwriters), defined in the stipulation as the “Torno parties.” On the other side were the roofing contractor and its insurer, defined in the stipulation as the “Western parties.” The stipulation recited that each side had contributed substantial sums pursuant to the IFA, that the IFA had provided that “the amounts contributed would be reallocated based upon the eventual resolution of this matter,” and that the IFA “contains provisions for alternative dispute resolution [binding arbitration] for this reallocation which the *114 parties now wish to modify.” The “parties to this Stipulation” then agreed that “the money funded under the interim agreement will be reallocated amongst and between the parties according to the factual rulings by the jury and legal findings by the judge.”

Directly pertinent to this appeal, the stipulation also provided that “if the court finds that defendant Western Pacific Roofing Corporation is not liable or if plaintiff [the general contractor] is unable to establish Western’s liability, then the defendant Western parties will be reimbursed by the Torno parties [previously defined as the general contractor plus its insurer, the Underwriters] all sums contributed by the Western parties to the interim agreement. . .” The stipulation further provided that “the amount subject to this Stipulation will be incorporated by the court into the final judgment in the underlying case,” and that the existence of the IFA and the amounts advanced would not be disclosed to the jury, but instead “the judge shall apply the jury and judge findings to incorporate these findings into the judgment in this case.”

Significantly, the stipulation did not provide that the Underwriters submitted to jurisdiction, that the Underwriters would be added as a party to the litigation, that the Underwriters agreed to be named as judgment debtors in this litigation, or that the Underwriters waived their policy limits or policy defenses.

According to the Underwriters, the purpose of the stipulation was simply to avoid the time and cost of the reallocation arbitration called for by the IFA, which was expected to duplicate findings which could be made at trial. Hence, again according to the Underwriters, the stipulation simply eliminated the need for the binding reallocation arbitration called for in the IFA by specifying findings to be made at trial, by providing for incorporation of those findings into the judgment, and by providing for reallocation to be made in light of those findings.

According to respondent roofing contractor, the effect of the stipulation was quite different. The roofing contractor’s different interpretation became an issue because of two events: the result at trial and the delay caused by an ensuing coverage dispute. First, the jury found that the roofing contractor’s actions had not contributed to the fire. The general contractor consequently took nothing by its complaint. Instead, the amounts contributed by the Western parties (the roofing contractor plus its insurer) were incorporated into the judgment pursuant to the stipulation. This resulted in a judgment in favor of the roofing contractor against the general contractor in an amount *115 exceeding (including interest) $1 million. Following the entry of this judgment, a coverage dispute arose among various carriers involving issues of primary versus excess layers, additional insured endorsements, etc. The coverage dispute caused a delay in payment to the roofing contractor.

After about a year’s delay, the roofing contractor made a motion to correct clerical error by adding the Underwriters to the judgment as additional judgment debtors. This motion was based on the roofing contractor’s interpretation of the stipulation’s definition of the “Torno parties” to include both the general contractor and its insurer. Since the stipulation stated that the roofing contractor would be reimbursed by the Torno parties, and since the Underwriters were included in that definition, the roofing contractor contended that it was entitled to be reimbursed by the Underwriters. The roofing contractor hence moved that the Underwriters be added as judgment debtors.

The Underwriters opposed for several reasons, apparently chief among them that their addition as judgment debtors would impose on them a liability far in excess of their policy limits. Before the time of the roofing contractor’s motion, the Underwriters had already contributed all but about $135,000 of their $1 million policy limits to the IFA. Hence only about $135,000 in policy limits remained, while the judgment was in excess of $1 million.

The trial court nevertheless granted the roofing contractor’s motion to correct clerical error, naming the Underwriters as judgment debtors on the judgment. This subjected the Underwriters to liability which exceeded the limits of the insurance they had issued by approximately $865,000.

Claiming that the stipulation was not intended to waive policy limits or defenses or to subject them to judgment, and that there is no authority for the summary procedure applied by the court, the Underwriters appeal.

II. Issues on Appeal

On appeal, respondent acknowledges that it does not claim that the Underwriters are the alter egos of their insured, the general contractor. (Cf. Triplett v. Farmers Ins. Exchange

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cattlemens v. Sanchez CA5
California Court of Appeal, 2025
Remington v. Wade CA6
California Court of Appeal, 2024
Northpoint Capital Fund v. McClenahan CA6
California Court of Appeal, 2023
WVJP 2018-3 LP v. SR Capital CA2/3
California Court of Appeal, 2023
Assn. for L.A. Deputy Sheriffs v. County of L.A.
California Court of Appeal, 2023
McPherson v. Southard CA4/3
California Court of Appeal, 2023
Valenzuela v. H-Mart Los Angeles CA2/1
California Court of Appeal, 2023
Leyva v. Ortiz CA3
California Court of Appeal, 2023
Marriage of Wallis CA4/3
California Court of Appeal, 2022
Mirzoyan v. West Coast Wound and Skin Care CA2/1
California Court of Appeal, 2022
Balakhane v. Sakhai CA2/4
California Court of Appeal, 2022
3123 SMB v. Horn CA2/7
California Court of Appeal, 2021
People v. Lexington National Ins. Corp. CA2/7
California Court of Appeal, 2020
Marriage of G.C. and R.W.
California Court of Appeal, 2018
Guan v. Hu
California Court of Appeal, 2017
Li Guan v. Yongmei Hu
218 Cal. Rptr. 3d 793 (California Court of Appeals, 5th District, 2017)
Hassell v. Bird
247 Cal. App. 4th 1336 (California Court of Appeal, 2016)
Hearn Pacific Corp. v. Second Generation Roofing, Inc.
247 Cal. App. 4th 117 (California Court of Appeal, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
89 Cal. Rptr. 2d 1, 75 Cal. App. 4th 110, 99 Cal. Daily Op. Serv. 7890, 99 Daily Journal DAR 10013, 1999 Cal. App. LEXIS 859, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tokio-marine-fire-insurance-v-western-pacific-roofing-corp-calctapp-1999.