thyssenkrupp Materials, LLC v. Triumph Group, Inc.

CourtDistrict Court, E.D. Michigan
DecidedJanuary 26, 2022
Docket4:20-cv-11087
StatusUnknown

This text of thyssenkrupp Materials, LLC v. Triumph Group, Inc. (thyssenkrupp Materials, LLC v. Triumph Group, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
thyssenkrupp Materials, LLC v. Triumph Group, Inc., (E.D. Mich. 2022).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF MICHIGAN SOUTHERN DIVISION THYSSENKRUPP MATERIALS, LLC,

Plaintiff, Case No. 20-cv-11087 Hon. Matthew F. Leitman v. TRIUMPH GROUP, INC., et al.,

Defendant __________________________________________________________________/ ORDER (1) DENYING DEFENDANTS’ MOTION TO VACATE ARBITRATION AWARD (ECF No. 14); AND (2) GRANTING PLAINTIFF’S MOTION TO CONFIRM ARBITRATION AWARD (ECF No. 12) On May 4, 2020, Plaintiff thyssenkrupp Materials, LLC (“TK”) filed this civil action against Defendant Triumph Aerostructures, LLC (“TAS”) and its parent corporation, Triumph Group, Inc. (“TGI”). TK alleged that TGI and TAS were jointly and severally liable for breach of contract and breach of implied contract. The parties subsequently stipulated to submit TK’s claims to binding arbitration. They further agreed that the Arbitrator would issue an unreasoned award. The Arbitrator thereafter held a five-day evidentiary hearing during which the parties presented live testimony from several witnesses and introduced nearly 100 exhibits. After hearing final arguments from the parties, the Arbitrator ruled in favor of TK. In his unreasoned award, the Arbitrator determined that TGI and TAS were jointly and severally liable to TK for approximately $2.9 million in damages. He also directed TK to deliver to TGI and TAS certain aluminum that TK had acquired

on their behalf during the parties’ relationship, and he required TGI and TAS to accept delivery of that aluminum from TK. TK has now moved to confirm the arbitration award and for pre-judgment

interest (ECF No. 12), and TGI and TAS have moved to vacate the award (ECF No. 14). In the motion to vacate, TGI and TAS have raised a number of reasonable questions regarding whether the Arbitrator erred in holding them jointly and severally liable for damages. For instance, TGI and TAS have offered some

evidence that there was only one operative contract, that the contract was between TK and TAS only, and that there was therefore no basis for the Arbitrator to hold TGI jointly liable with TAS for breach of contract.

But raising reasonable questions about the correctness of an arbitration award is not enough to warrant its vacatur. On the contrary (and as TGI and TAS rightly acknowledge), TGI and TAS must show that the Arbitrator manifestly disregarded the law. To make that showing, the losing parties in an arbitration must ordinarily

establish that the arbitrator’s award flew in the face of clearly established precedent. And where, as here, an award is unreasoned, the losing parties must make an even higher showing to establish a manifest disregard for the law: They must show that

there was no conceivable rational basis for the award. TGI and TAS have failed to carry their heavy burden. As explained below, the Arbitrator could have concluded that TK, TGI, and TAS entered into a contract

through their conduct, that TGI and TAS breached that contract, and that TGI and TAS are therefore jointly and severally liable for that breach. TGI and TAS have not shown that these conclusions would have been precluded by clearly established

precedent or that they would have been irrational. For these reasons, the Court cannot vacate the award and must confirm it. Therefore, the Court GRANTS TK’s motion to confirm the award, DENIES TGI’s and TAS’s motion to vacate the award, and CONFIRMS the award. However, the Court DENIES TK’s request for pre-

judgment interest on the award. I A

TGI is a holding company whose subsidiaries manufacture aerospace products. (See Compl. at ¶¶ 15-16, ECF No. 1, PageID.5.) TAS is one TGI’s subsidiaries. (See id. at ¶ 10, PageID.3.) TAS and TGI’s other subsidiaries use aluminum in their production processes.

TK is a distributor of production materials, including aluminum. (See id. at ¶ 19, PageID.6.) B According to TK, it is a party to certain “agreements” with TGI and TAS

concerning the procurement and storage of aluminum. (Compl. at ¶ 20, ECF No. 1, PageID. 6.1) These agreements “include” terms found in a “Long Term Agreement Purchase Order 101-120099-AZ,” as amended from time to time (the “LTA”).2 (Id.

at ¶ 20, PageID.6.) TK alleges the parties’ relationship under these agreements was as follows: (1) TGI and TAS would order large quantities of aluminum products from an aluminum mill in anticipation of their production needs, leveraging their volume

purchasing to obtain favorable prices; and then (2) TK would “acquire[], warehouse[], and maintain[]” these aluminum products on behalf of TGI and TAS until they were needed by TGI and TAS (or their customers). (Id. at ¶ 27-28,

PageID.8.) In other words, TGI and TAS would negotiate, with the aluminum mill, the prices and quantities of aluminum to be acquired by TK; TK would purchase the

1 In the paragraph of the Complaint cited above and elsewhere throughout the Complaint and TK’s submissions to this Court and to the Arbitrator, TK used the defined term “Triumph.” TK defined that term to include both TGI and TAS. (See Compl., ECF No. 1, PageID.1.) 2 The LTA is dated April 23, 2003. (See Compl. at ¶ 21, ECF No. 1, PageID.6.) The original parties to the LTA were Alcoa, Inc. and Vought Aircraft Industries, Inc. (See id.) TK alleges that it became the successor to Alcoa, Inc., and TGI and TAS became successors to Vought Aircraft Industries, Inc. (See id. at ¶¶ 22-23, PageID.6- 7.) TK further alleges that there were “a series of written amendments to the [LTA],” with the latest dated November 2017. (Id. at ¶ 24, PageID.7.) The LTA lapsed on December 31, 2020. (See Mot. to Vacate, ECF No. 14, PageID.518.) aluminum at the prices and quantities negotiated by TGI and TAS; and TK would store the aluminum until TGI and TAS needed it. TK would then deliver the

aluminum to TGI and TAS, and TGI and TAS would pay TK for the aluminum. Occasionally, TGI and TAS did not need all of the aluminum that TK had acquired for them on a particular project. (See id. at ¶ 29, PageID.8.) In some

instances, this excess aluminum could not be used on other projects due to its specialized nature, and it thus became obsolete as it sat in TK’s storage facilities (the “Obsolete Aluminum”). (See id.) TK says that the parties’ agreements required TGI and TAS to repurchase the Obsolete Aluminum from TK. (See id. at ¶ 30, PageID.8.)

TK further contends that in 2019, TGI and TAS breached their contractual obligations to repurchase from TK millions of dollars’ worth of Obsolete Aluminum. (See id. at ¶¶ 39-41, PageID.11.)

C On May 4, 2020, TK filed this civil action against TGI and TAS. (See Compl., ECF No. 1.) The action arises out of the refusal by TGI and TAS to repurchase the Obsolete Aluminum in 2019. (See id. at ¶¶ 39-41, PageID.11.) TK asserted three

claims in its Complaint. First, TK asserted a breach of contract claim against TGI and TAS. In that claim, TK alleged that both TGI and TAS were “parties to agreements” with TK and that those agreements required TGI and TAS to repurchase

Obsolete Aluminum. (See id. at ¶¶ 45-49, PageID.12.) TK contended that TGI and TAS breached those agreements by refusing to repurchase the Obsolete Aluminum in 2019. (See id. at ¶¶ 49-51.) And TK alleged that both TGI and TAS were “jointly

and severally” liable for the alleged breaches of contract. (See id., PageID.13.) TK sought damages in the amount of $3,623,612 from TGI and TAS. (See id.) “[I]n the alternative and/or in addition” to its claim for breach of contract, TK

also brought a claim for breach of implied contract against both TGI and TAS. (See id. at ¶ 52-55, PageID.13.) TK again alleged that both TGI and TAS were “jointly and severally” liable for at least $3,623,612 in damages. (See id., PageID.13-14.)3 D

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hall Street Associates, L. L. C. v. Mattel, Inc.
552 U.S. 576 (Supreme Court, 2008)
Apex Oil Company v. Vanguard Oil & Service Co. Inc.
760 F.2d 417 (Second Circuit, 1985)
General Aviation, Inc. v. The Cessna Aircraft Co.
915 F.2d 1038 (Sixth Circuit, 1990)
Patrick Murray v. Citigroup Global Markets, Inc.
511 F. App'x 453 (Sixth Circuit, 2013)
Hector, Inc. v. United Savings & Loan Ass'n
741 P.2d 542 (Utah Supreme Court, 1987)
Northwestern State Bank of Luverne v. Gangestad
289 N.W.2d 449 (Supreme Court of Minnesota, 1979)
A.P.S., Inc. v. Standard Motor Products, Inc.
295 B.R. 442 (D. Delaware, 2003)
Cherry River Music Co. v. Simitar Entertainment, Inc.
38 F. Supp. 2d 310 (S.D. New York, 1999)
Barcume v. City of Flint
132 F. Supp. 2d 549 (E.D. Michigan, 2001)
Coffee Beanery, Ltd. v. WW, L.L.C.
300 F. App'x 415 (Sixth Circuit, 2008)
Samaan v. General Dynamics Land Systems, Inc.
835 F.3d 593 (Sixth Circuit, 2016)
Hornell Brewing Co. v. Spry
174 Misc. 2d 451 (New York Supreme Court, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
thyssenkrupp Materials, LLC v. Triumph Group, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/thyssenkrupp-materials-llc-v-triumph-group-inc-mied-2022.