Thomas Steel, Inc. v. Wilson Bennett, Inc.

711 N.E.2d 1029, 127 Ohio App. 3d 96
CourtOhio Court of Appeals
DecidedMarch 30, 1998
DocketNo. 72071.
StatusPublished
Cited by8 cases

This text of 711 N.E.2d 1029 (Thomas Steel, Inc. v. Wilson Bennett, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thomas Steel, Inc. v. Wilson Bennett, Inc., 711 N.E.2d 1029, 127 Ohio App. 3d 96 (Ohio Ct. App. 1998).

Opinion

James M. Porter, Presiding Judge.

Plaintiff-appellant Thomas Steel, Inc. appeals from summary judgment entered in favor of defendants-appellees Wilson Bennett, Inc. and Safeco Insurance Company of America on their payment bond arising out of certain subcontract work performed by plaintiff at Cleveland Hopkins Airport. Plaintiff Thomas Steel claims that the trial court erred in barring its action by applying the incorrect statute of limitations and in not recognizing plaintiffs unjust enrichment claims. We find no error and affirm.

On June 9, 1992, Wilson Bennett, as general contractor, entered into a contract with the city of Cleveland to install certain improvements at Cleveland Hopkins International Airport. The project included construction of an Aircraft Rescue and Fire Fighters Station (“ARFF”) and Relocation of Electric Vault (“EV-9”) for the lump sum contract price of $6,841,000.

The contract obliged Wilson Bennett to obtain a payment and performance bond in the form set forth in C.C.O. (“Cleveland Codified Ordinance”) 185.14. *99 Wilson Bennett obtained the required bond from Safeco. The bond provided that Wilson Bennett as principal and Safeco as surety would jointly and severally indemnify and save harmless the city of Cleveland from all liens, charges, claims, demands, loss, costs, and damages, and “shall pay all lawful claims of subcontractors, materialmen and laborers for labor performed, and materials furnished” in performing the contract on the project.

On September 17, 1992, Wilson Bennett entered into a purchase order subcontract with Simms Steel Service Company to provide the structural steel and labor to erect the ARFF building and EV-9 building for the contract price of $385,000, subject to a ten-percent retainage.

Simms Steel’s subcontract with Wilson Bennett was based on a purchase order agreement, dated May 12, 1992, with plaintiff Thomas Steel to supply the structural steel and other accessories needed to frame the ARFF building and EV-9 for the contract price of $207,000. Thomas Steel supplied the steel on the job and submitted periodic invoices to Simms Steel, totaling $208,450. Simms Steel withheld ten percent of the total contract price or $20,845 as retainage. Thomas Steel completed its work and sent its final invoice to Simms Steel, dated April 12, 1993.

Despite Thomas Steel’s repeated demands upon completion of the project, Simms Steel and Wilson Bennett failed and refused to pay Thomas Steel the outstanding retainage of $20,845. Correspondence in the record suggests that Simms Steel was in bankruptcy. By letter dated April 3, 1995, Thomas Steel’s counsel sent Wilson Bennett formal written notice that Thomas Steel had not been paid in full by Simms Steel. Thomas Steel advised Wilson Bennett that when the city issued final payment to Wilson Bennett, Thomas Steel claimed any money due Simms Steel.

On June 30, 1995, Wilson Bennett submitted its final request for payment to the city and stated under oath that all laborers, materialmen and/or subcontractors had been paid in full despite the notice of nonpayment from Thomas Steel.

On October 18, 1995, prior to the city’s final payment to Wilson Bennett, counsel for Thomas Steel gave formal written notice to Safeco of its $20,845 bond claim. On December 15, 1995, the city determined that the project was completed and made a final payment of $40,300 to Wilson Bennett.

On January 5,1996, Wilson Bennett’s counsel sent Thomas Steel formal written notice that Wilson Bennett and Safeco denied Thomas Steel’s bond claim under the statute of limitations set forth in R.C. 153.56, since the project was accepted on December 14, 1993 and Thomas Steel had not complied with the time limitations in the statute.

*100 On April 4, 1996, Thomas Steel commenced this action on the bond against Wilson Bennett and Safeco for $20,850. After discovery, all parties filed motions for summary judgment. The trial court granted summary judgment for defendants on statute-of-limitations grounds and denied Thomas Steel’s motion for summary judgment. This timely appeal ensued.

We will address plaintiffs assignments of error in the order presented and together where the subject matter is appropriate.

“I. The trial court erred when it granted defendants-appellees’ motion for summary judgment and dismissed plaintiff-appellant’s complaint as time barred because the general bond statute, Ohio Revised Code § 153.56, is inapplicable to a bond furnished pursuant to § 185.14 of the Codified Ordinances of the city of Cleveland.

“II. The trial court erred when it granted defendants-appellees’ motion for summary judgment and dismissed plaintiff-appellant’s complaint as time-barred because plaintiff-appellant filed suit within one year from the date of acceptance of the public improvement project by the city of Cleveland even if R.C. § 153.56 applies to defendants-appellees’ bond claim, which it does not.”

Under Civ.R. 56, summary judgment is proper when “(1) no- genuine issue as to any material fact remains to be litigated; (2) the moving party is entitled to judgment as a matter of law; and (3) it appears from the evidence that reasonable minds can come to but one conclusion, and viewing such evidence most strongly in favor of the nonmoving party, that conclusion is adverse to the party against whom the motion for summary judgment is made.” State ex rel. Parsons v. Fleming (1994), 68 Ohio St.3d 509, 511, 628 N.E.2d 1377, 1379; Temple v. Wean United, Inc. (1977), 50 Ohio St.2d 317, 327, 4 O.O.3d 466, 471-472, 364 N.E.2d 267, 273-274.

It is well settled that the party seeking summary judgment bears the burden of showing that no genuine issue of material fact exists for trial. Celotex Corp. v. Catrett (1986), 477 U.S. 317, 330, 106 S.Ct. 2548, 2556, 91 L.Ed.2d 265, 278; Mitseff v. Wheeler (1988), 38 Ohio St.3d 112, 115, 526 N.E.2d 798, 801-802. Doubts must be resolved in favor of the nonmoving party. Murphy v. Reynoldsburg (1992), 65 Ohio St.3d 356, 358-359, 604 N.E.2d 138, 139-141.

However, the nonmoving party must produce evidence on any issue for which that party bears the burden of production at trial. Wing v. Anchor Media, Ltd. of Texas (1991), 59 Ohio St.3d 108, 111, 570 N.E.2d 1095, 1099; Celotex, supra, at 322-323, 106 S.Ct. at 2552-2553, 91 L.Ed.2d at 273-274. In accordance with Civ.R. 56(E), “a nonmovant may not rest upon the mere allegations or denials of his pleadings, but must set forth specific facts showing there is a *101 genuine issue for trial.” Chaney v. Clark Cty. Agricultural Soc. (1993), 90 Ohio App.3d 421, 424, 629 N.E.2d 513, 515.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
711 N.E.2d 1029, 127 Ohio App. 3d 96, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thomas-steel-inc-v-wilson-bennett-inc-ohioctapp-1998.