21st Century Concrete Constr., Inc. v. Reginella Constr. Co., Ltd.

2013 Ohio 3006
Ohio Court of Appeals·Decided July 11, 2013·No. 99366·Published·Cited by 1 cases

Opinion

[Cite as 21st Century Concrete Constr., Inc. v. Reginella Constr. Co., Ltd., 2013-Ohio-3006.]

Court of Appeals of Ohio

EIGHTH APPELLATE DISTRICT COUNTY OF CUYAHOGA

JOURNAL ENTRY AND OPINION No. 99366

21ST CENTURY CONCRETE

CONSTRUCTION, INC.

PLAINTIFF-APPELLEE

vs.

REGINELLA CONSTRUCTION

COMPANY, LTD., ET AL.

DEFENDANTS-APPELLANTS

JUDGMENT:

AFFIRMED

Civil Appeal from the

Cuyahoga County Court of Common Pleas Case No. CV-779703

BEFORE: Stewart, A.J., S. Gallagher, J., and E.A. Gallagher, J.

RELEASED AND JOURNALIZED: July 11, 2013

ATTORNEYS FOR DEFENDANT-APPELLANT REGINELLA CONSTRUCTION COMPANY, LTD.

Steven R. Hobson, II Leiby Hanna Rasnick Towne Evanchan Palmisano & Hobson, L.L.C. 388 S. Main Street, Suite 402 Akron, OH 44311

ATTORNEYS FOR DEFENDANT-APPELLEE TRAVELERS CASUALTY & SURETY COMPANY OF AMERICA

Audrey E. Varwig Dickie, McCamey & Chilcote, P.C. 2109 Stella Court Columbus, OH 43215

W. Alan Torrance Dickie, McCamey & Chilcote, P.C. 2 PPG Place, Suite 400 Pittsburgh, PA 15222

ATTORNEYS FOR PLAINTIFF-APPELLEE

R. Russell O’Rourke Scott R. Sylkatis O’Rourke & Associates Co., L.P.A. 2 Summit Park Drive, Suite 650 Independence, OH 44131

ATTORNEYS FOR OHIO TURNPIKE COMMISSION

Peter J. Comodeca Ronald M. McMillan Calfee, Halter & Griswold, L.L.P. The Calfee Building 1405 East 6th Street Cleveland, OH 44114

MELODY J. STEWART, A.J.:

{¶1} Plaintiff-subcontractor 21st Century Concrete Construction, Inc., brought this breach of contract action against defendant-general contractor Reginella Construction Co., Ltd., alleging that Reginella breached a subcontract by making oral changes to a work order but refusing to pay for those changes. 21st Century also named surety Travelers Casualty & Surety Co. of America as a defendant, alleging that Travelers refused to pay 21st Century on a performance and payment bond that it issued to Reginella. The court, recognizing that arbitration proceedings had been initiated between 21st Century and Reginella, stayed the action. It also ordered that Travelers participate in the arbitration because Travelers, as surety, was in privity with Reginella and might be bound by any decision issued by the arbitrator. Reginella appeals, arguing that the court erred by ordering Travelers to participate in the arbitration because Travelers is not a party to the arbitration agreement, it is not in privity with Reginella, and that the addition of Travelers to the pending arbitration would delay the proceedings between 21st Century and Reginella.

I

{¶2} We first consider Travelers’ argument that Reginella lacks standing to argue that the court improperly ordered Travelers to arbitrate 21st Century’s claim on the bond. That claim, argues Travelers, is separate from 21st Century’s breach of contract claim against Reginella, so Reginella has no standing to complain about an order that does not affect it. Reginella maintains that including Travelers in the arbitration will affect it by forcing it to incur additional time and expense during that proceeding.

A

{¶3} Regardless of whether Reginella has standing to argue that the court erred by ordering Travelers to participate in the arbitration, Reginella cannot be heard to complain about that order because it invited the error by specifically requesting that Travelers be included in any order compelling arbitration.

{¶4} “‘Invited error’ arises when a party tries to take advantage of an error that the party induced the trial court to make.” State ex rel. The V Cos. v. Marshall, 81 Ohio St.3d 467, 471, 692 N.E.2d 198 (1998). The invited error doctrine is applied when counsel is “actively responsible” for the trial court’s error. State v. Campbell, 90 Ohio St.3d 320, 324, 738 N.E.2d 1178 (2000).

{¶5} In its motion to stay the proceedings and compel arbitration, Reginella noted that the terms of the contract between it and 21st Century required arbitration of “[a]ny controversy or claim arising out of or relating to this contract, or breach thereof, including claims against third parties whom [Reginella Construction] is obligated to defend * * *.” Reginella told the court that the “third party” claims provision “clearly applies” to Travelers and that any order to compel arbitration should also apply to 21st Century’s claims against Travelers. See motion to stay and compel arbitration, at 2, fn. 1.

{¶6} Travelers agreed that it should participate in the arbitration. It cited a decision from this court, Midwest Curtainwalls, Inc. v. Pinnacle 701, LLC, 8th Dist. No.

92269, 2009-Ohio-3740, for the proposition that a surety in privity with a general contractor may be bound by a decision reached in an arbitration between the general contractor and a subcontractor, even if the surety did not participate in the arbitration.

{¶7} After the court stayed the proceedings and ordered all three parties to arbitration, 21st Century and Reginella filed a joint motion for partial reconsideration of that part of the court order requiring Travelers to participate in the arbitration. They argued that (1) Travelers is not a party to the arbitration agreement so the American Arbitration Association would have no jurisdiction to decide any claims involving Travelers; (2) Travelers waived its claim that it should be a part of the arbitration by filing “an adversary lawsuit against Reginella in another court of law”; and (3) arbitration between Reginella and 21st Century had been ongoing for “several months” and that Travelers “can bring nothing to the arbitration by way of witnesses or any factual evidence” so its presence would create an unnecessary delay. Reginella filed its notice of appeal before the court could rule on the motion for partial reconsideration.

{¶8} Given Reginella’s initial position that Travelers should be made a part of the arbitration, its claimed errors are barred by the invited error doctrine. Reginella filed its demand for arbitration on May 11, 2012, nearly one month before it filed its motion to stay proceedings and compel arbitration. And as noted, it specifically requested that any order staying the proceedings and ordering arbitration “should apply to Plaintiff’s claims against Defendant Travelers Casualty & Surety Co. of America in the present case as well.” With the court having ordered arbitration in terms consistent with those requested by Reginella, any error stemming from that order was invited by Reginella.

B

{¶9} Reginella now maintains that its interests are no longer aligned with Travelers because Travelers filed suit against it in Pennsylvania, making them adversaries. For its part, Travelers argues that its participation in the arbitration is required because it fears that Reginella would not adequately represent Travelers’ interests at the arbitration.

{¶10} According to Reginella, Travelers filed the Pennsylvania action on July 16, 2012. The court did not rule on the motion to stay proceedings and compel arbitration until December 6, 2012. At no point between asking the court to order Travelers to submit to arbitration and receiving the court order to that effect did Reginella raise an objection based on the Pennsylvania action. In fact, it was not until after the court ordered Travelers to participate in the arbitration that Reginella mentioned the Pennsylvania action and the potential that the parties would be adversaries in the arbitration. This was not a timely objection.

Free access — add to your briefcase to read the full text and ask questions with AI

21st Century Concrete Constr., Inc. v. Reginella Constr. Co., Ltd., 2013 Ohio 3006 (Ohio Ct. App. 2013).

2013 Ohio 3006 (21st Century Concrete Constr., Inc. v. Reginella Constr. Co., Ltd.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

JJ Connor Co., Inc. v. Reginella Constr. Co., Ltd.
2014 Ohio 3873 (Ohio Court of Appeals, 2014)