Burson Trucking, Inc v. Kirk Bros. Co., 2006ca0002 (10-19-2007)

2007 Ohio 5639
CourtOhio Court of Appeals
DecidedOctober 19, 2007
DocketNo. 2006CA0002.
StatusPublished

This text of 2007 Ohio 5639 (Burson Trucking, Inc v. Kirk Bros. Co., 2006ca0002 (10-19-2007)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Burson Trucking, Inc v. Kirk Bros. Co., 2006ca0002 (10-19-2007), 2007 Ohio 5639 (Ohio Ct. App. 2007).

Opinions

OPINION *Page 2
{¶ 1} In 1992, appellant, Kirk Bros. Co., Inc., was awarded the job of constructing a new water treatment plant for the Village of Mt. Gilead (Contract No. 92-1). Appellant subcontracted with appellees, Burson Trucking, Inc., Jim Burson dba Burson Excavating, and Jim Burson dba Burson Trucking, to deliver the necessary dirt and soil materials for the job.

{¶ 2} On July 7, 1998, appellees filed a complaint against the Village of Mt. Gilead and appellant for amounts due and owing and unjust enrichment. On November 23, 1998, appellant filed an answer and counterclaim, claiming appellees performed faulty work.

{¶ 3} On September 3, 1998, appellant filed a motion to dismiss the complaint because appellees had failed to comply with R.C. 153.56 which sets forth the exclusive statutory scheme for recovery of monies due and owing on a public improvement project. A hearing was held on September 30, 1998. By judgment entry filed October 19, 1998, the trial court denied the motion.

{¶ 4} A bench trial commenced on June 6, 2005 without participation from the Village of Mt. Gilead. Appellant renewed its motion to dismiss the complaint based on R.C. 153.56. By decision and judgment entry filed December 20, 2005, the trial court noted the counterclaim and the Village of Mt. Gilead were dismissed, found the October 19, 1998 judgment entry was law of the case and the remedies under R.C. 153.56 are not exclusive, and granted judgment in favor of appellees as against appellant in the amount of $8,780.51. *Page 3

{¶ 5} Appellant filed an appeal and this matter is now before this court for consideration. Assignments of error are as follows:

I
{¶ 6} "THE TRIAL COURT ERRED AS A MATTER OF LAW IN ITS DETERMINATION THAT THE PROCEDURES AND REMEDIES IN SECTION 153.56 OF THE OHIO REVISED CODE ARE NOT THE EXCLUSIVE REMEDY AVAILABLE TO PLAINTIFF."

II
{¶ 7} "THE TRIAL COURT ERRED AS A MATTER OF LAW THROUGH IMPOSITION OF A BURDEN OF PROOF ON KIRK BROS. TO DISPROVE PLAINTIFF'S CASE WHERE THE PLAINTIFF FAILED TO PRESENT EVIDENCE OF CONTRACT PERFORMANCE."

III
{¶ 8} "THE TRIAL COURT ERRED AS A MATTER OF LAW IN ITS DETERMINATION THAT MONIES WERE DUE THE PLAINTIFF; NOTWITHSTANDING KIRK BROS. CO., INC. OVERPAYMENT ON THE CONTRACT BALANCE OF THE PLAINTIFF."

I
{¶ 9} Appellant claims the trial court erred in finding the remedies under R.C. 153.56 are not exclusive. We disagree.

{¶ 10} R.C. 153.56 governs "[creditor shall furnish statement of amount due; limitation of actions" and states the following in pertinent part: *Page 4

{¶ 11} "(A) Any person to whom any money is due for labor or work performed or materials furnished in a public improvement as provided in section 153.54 of the Revised Code, at any time after performing the labor or work or furnishing the materials, but not later than ninety days after the completion of the contract by the principal contractor and the acceptance of the public improvement for which the bond was provided by the duly authorized board or officer, shall furnish the sureties on the bond, a statement of the amount due to the person.

{¶ 12} "(C) To exercise rights under this section, a subcontractor or materials supplier supplying labor or materials that cost more than thirty thousand dollars, who is not in direct privity of contract with the principal contractor for the public improvement, shall serve a notice of furnishing upon the principal contractor in the form provided in section 1311.261 of the Revised Code.

{¶ 13} "(D) A subcontractor or materials supplier who serves a notice of furnishing under division (C) of this section as required to exercise rights under this section has the right of recovery only as to amounts owed for labor and work performed and materials furnished during and after the twenty-one days immediately preceding service of the notice of furnishing."

{¶ 14} As case law indicates, this statutorily created shortened statute of limitations applies only when an action is commenced against the lending company and/or the political subdivision. Thomas Steel, Inc.vs. Wilson Bennett, Inc. (1998), 127 Ohio App.3d 96. *Page 5

{¶ 15} Appellees chose not to initiate an action under R.C. 153.56 and sue for breach of contract against the general contractor only. If appellees had chosen to pursue its claims against appellant only, the late filing would have been time barred.

{¶ 16} This analysis is similar to a materialman who abandons a claim under the Mechanic's Lien Law (R.C. 1311.02) and pursues only a contract/unjust enrichment action.

{¶ 17} Upon review, we find the trial court did not err in finding the remedies under R.C. 153.56 are not exclusive.

{¶ 18} Assignment of Error I is denied.

II
{¶ 19} Appellant claims the trial court shifted the burden of proof to it instead of requiring appellees to prove their case. We disagree.

{¶ 20} The genesis of this assignment is the following statements by the trial court in its December 20, 2005 decision and judgment entry:

{¶ 21} "The evidence presented at trial was confusing and contradictory. Plaintiff kept very poor records of the work he did, and defendant kept very poor records of what was paid. The burden of proof is on the Plaintiff to show performance on the contract, and the burden is on the Defendant to show payment. In order to reach a decision on the evidence presented at trial the court will consider each claim in the complaint and the documentary and testimonial evidence relevant to that claim. The court will then render a decision on that claim."

{¶ 22} We fail to find that such an innocuous comment in a judgment entry would warrant a reversal. We find the statement to be a shorthand approach to the burden of *Page 6 proof and when the burden shifts. However, in reading the trial court's judgment entry as a whole, we find a thorough and thoughtful analysis of all the evidence was given with respect to appellees' burden of proof and appellant's defense of payment in full. Vol. I T. at 76.

{¶ 23} Upon review, we find the trial court did not shift the burden of proof to appellant.

{¶ 24} Assignment of Error II is denied.

III
{¶ 25}

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thomas Steel, Inc. v. Wilson Bennett, Inc.
711 N.E.2d 1029 (Ohio Court of Appeals, 1998)
C. E. Morris Co. v. Foley Construction Co.
376 N.E.2d 578 (Ohio Supreme Court, 1978)
State v. Jamison
552 N.E.2d 180 (Ohio Supreme Court, 1990)
Myers v. Garson
614 N.E.2d 742 (Ohio Supreme Court, 1993)
Miller v. First International Fidelity & Trust Building, Ltd.
113 Ohio St. 3d 474 (Ohio Supreme Court, 2007)
Myers v. Garson
1993 Ohio 9 (Ohio Supreme Court, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
2007 Ohio 5639, Counsel Stack Legal Research, https://law.counselstack.com/opinion/burson-trucking-inc-v-kirk-bros-co-2006ca0002-10-19-2007-ohioctapp-2007.