The Kansas Power & Light Company, State Corporation Commission of the State of Kansas, Intervening v. Burlington Northern Railroad Company

740 F.2d 780, 1984 U.S. App. LEXIS 20275
CourtCourt of Appeals for the Tenth Circuit
DecidedJuly 23, 1984
Docket82-2095, 82-2166 and 83-1277
StatusPublished
Cited by16 cases

This text of 740 F.2d 780 (The Kansas Power & Light Company, State Corporation Commission of the State of Kansas, Intervening v. Burlington Northern Railroad Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Kansas Power & Light Company, State Corporation Commission of the State of Kansas, Intervening v. Burlington Northern Railroad Company, 740 F.2d 780, 1984 U.S. App. LEXIS 20275 (10th Cir. 1984).

Opinion

WILLIAM E. DOYLE, Circuit Judge.

I. INTRODUCTION

This is an action which was instituted by The Kansas Power & Light Company (KPL). The allegation was that there was a breach of contract on the part of Burlington Northern Railroad Company. KPL sought a declaratory order that the parties had entered into an enforceable contract and a permanent injunction prohibiting BN from breaching the contract. The basic issue is whether a contract existed.

Burlington Northern (BN) denies that it entered into an enforceable contract with KPL, and thus, whether there was indeed a contract in effect is the basic issue here.

II. THE RELEVANT FACTS

The facts are somewhat complex. In the early 1970’s, KPL planned to build a new generating facility and commenced an arrangement for a supply of coal to power the new facility. Several sites were considered for both the facility and the supply of coal. However, in order to get the coal to the generating facility, KPL also began negotiating with carriers, including BN, for the transportation of the coal.

Following a meeting with representatives of BN, KPL sought from BN a schedule of rates that it would charge to transport coal from Wyoming to several sites in Kansas. BN responded by letter dated October 7, 1971. In that letter there were specified estimated rates. The parties continued discussions. On January 19, 1972, BN wrote to KPL once again regarding rates. This letter also outlined an escalation formula to increase the rate in the future. In addition, BN stated that “This proposal is contingent upon the utility entering into a long term contract of 20 or more years with coal producers on BN for the indicated coal requirements.” Finally, BN wrote that the “rates quoted above are tendered with a time limit of six months from the date of this letter.”

In November 1972, at the request of KPL, BN committed its position to writing. In a letter which is dated November 30, 1972, BN provided a letter to serve as “an outline of the intent and understanding that Burlington Northern, Inc. and Union Pacific Railroad Company have regarding movement of coal from Amax Coal Company Belle Ayr Mine * * * to Kansas Power & Light Company’s proposed plant site * * It was specified by BN that the proposed rates were attached and that it intended to file those rates with the ICC in anticipation of a 1978 start-up date. It also contained an escalation formula. The letter was signed by a representative of BN.

KPL had plans for a new generating plant facility and these plans were carried out. Also it should be noted that KPL entered into a long-term contract with Amax for the purpose of having a supply of coal. In early 1976, BN informed KPL that it wished to increase its rates. In *783 order to carry this out it filed with the ICC a tariff in 1977 for the transportation of coal from Wyoming to Kansas. There is a dispute between the parties on whether the rates filed differed from those specified in the November 30, 1972 letter. In early 1981, BN again informed KPL that it planned to raise its rates. In October BN then filed a tariff with the ICC to raise its rates. However, the ICC rejected this effort. BN filed again in December 1981 and this time the ICC allowed the rate increase. It was then that KPL filed the present lawsuit.

III. CONTENTIONS OF THE PARTIES

To clarify the issues we outline here the contentions of the parties.

KPL maintains that it had an enforceable contract with BN regarding the rates to be charged for the transportation of coal. KPL maintains that the November 30,1972 letter provides the basis of its contract with BN.

BN contends that it never entered into a binding agreement with KPL. According to BN, no contract exists and sets forth the following reasons for this:

(1) Due to the statutory framework in existence in 1972 a contract for rates between it and KPL would have been illegal per se.
(2) The letter of November 30, 1972 was not an offer.
(3) Even if the letter of November 30, 1972 was an offer, KPL never accepted.
(4) Any purported contract between the parties is too vague to be enforced.
(5) Any agreement between the parties is in violation of the Kansas Statute of Frauds (§ 33-106) because that statute requires a writing for any agreement not capable of performance within one year.
(6) The statutory framework now in existence, the Staggers Rail Act of 1980, 49 U.S.C. 10101, et seq. has no application.

The trial court, 544 F.Supp. 1336, ruled in favor of BN and against KPL concluding that there was no enforceable agreement existing between the parties for the following reasons. First, it held that any contract between a shipper and a carrier was illegal per se in 1972. Second, the trial court found that no contract existed. This second portion was based on a number of factors: (1) because any contract would have been illegal per se in 1972, the parties could not have intended to be bound at that time; (2) there was no offer; (3) there was no acceptance; and, (4) the writings did not evidence what duration the contract had. Third, the trial court found that any agreement between the parties violated the Kansas Statute of Frauds which requires a writing for any agreement incapable of performance within one year. The final conclusion of the trial court was that although § 208 of the Staggers Rail Act of 1980, (49 U.S.C. § 10713) permits rate contracts between carriers and shippers, it had no application to the issues here for the reason that no contract existed between KPL and BN. KPL maintains that the district court erred in each of those findings, and so each of them will be considered.

IV. ISSUES

A. DID THE TRIAL COURT ERR IN RULING THAT A RATE CONTRACT ENTERED INTO BY A CARRIER AND A SHIPPER WAS ILLEGAL PER SE IN 1972?

KPL argues that this ruling was in error. Our view is that KPL is right on this and that it was error for the trial court to finally conclude that any contract entered into between the parties would have been illegal per se, and unenforceable.

• To fully understand this issue and this problem, it is necessary to discuss the framework governing carriers in the 1970’s. It is well to examine the history of the present situation.

Prior to 1976, Congress had invested the ICC with the power to oversee the rates charged by railroads. The ICC required all *784 rates to be just and reasonable pursuant to its authority under the Interstate Commerce Act, 49 U.S.C. § 1(5), 15(1), (1970). Burlington Northern R. Co.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
740 F.2d 780, 1984 U.S. App. LEXIS 20275, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-kansas-power-light-company-state-corporation-commission-of-the-state-ca10-1984.