Storts v. Martin K. Eby Construction Co.

535 P.2d 908, 217 Kan. 34, 1975 Kan. LEXIS 402
CourtSupreme Court of Kansas
DecidedMay 10, 1975
Docket47,553
StatusPublished
Cited by11 cases

This text of 535 P.2d 908 (Storts v. Martin K. Eby Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Storts v. Martin K. Eby Construction Co., 535 P.2d 908, 217 Kan. 34, 1975 Kan. LEXIS 402 (kan 1975).

Opinion

The opinion of the court was delivered by

Harman, C.:

This is an appeal from summary judgment denying an employee of a subcontractor the right to maintain a tort action against the general contractor for personal injury on the basis the employee’s exclusive remedy was under the workmen’s compensation act pursuant to K. S. A. 44-503 (a). The primary issue is whether a contract existed between the general contractor and the subcontractor at the time of the plaintiff’s injury.

*35 Plaintiff Jay C. Storts, an employee of Kendall, Inc., was severely injured on June 12, 1970, when the wall of a storm sewer excavation collapsed on him. Plaintiff was provided workmen’s compensation and medical aid by Kendall and its insurance carrier. He instituted this action to recover damages allegedly caused by the negligence of the general contractor, Martin K. Eby Construction Company.

Garvey Center, Inc. was the developer of an area in downtown Wichita known as the Kiva project, which included a high rise motel, a theater, a parking garage and three office buildings. Eby had previously been the general contractor for Garvey in constructing the garage. On January 16, 1970, after conferences between the two, Garvey notified Eby it had been selected as the general contractor to work with the architects further to develop the project and a construction contract. The agreement was to be a negotiated contract project wherein the construction company worked with the architect during design phases prior to a formal written contract between Garvey and Eby. The arrangement was to be a cost plus contract with a maximum guaranteed cost (not to exceed a certain amount).

On February 18, 1970, Eby sent a letter to Kendall inviting a proposal for mechanical work (air-conditioning, heating, ventilating and plumbing) to be done on the Kiva project. The letter stated the work would be done on a maximum guaranteed price basis with Kendall to compute the maximum cost for the complete job when the mechanical drawings were available; Kendall was requested to propose the percentage above cost for which it would do the work; upon completion of the job if the cost plus percentage figure was less than the maximum guaranteed price the lesser amount would be paid.

Kendall replied by letter February 23, 1970, in which it proposed to do the work on phase one of the project for cost plus 12% and on phase two for cost plus 15%. Kendall pointed out it had been the mechanical contractor on two of the Garvey buildings in the project.

By letter dated March 3, 1970, Eby accepted Kendall’s proposal to do the mechanical work. The letter further stated: “The award was made based on your proposal dated February 23, 1970, with one exception. The job will be awarded on a maximum guaranteed cost basis, and not a true cost plus job.”

On March 12, 1970, Kendall sent a letter to Eby which detailed how Kendall would compute its cost. The letter concluded with *36 this: “Thank you for the opportunity of working with you on this project.”

Meanwhile, there had been oral discussions between Eby and Kendall officials as to excavation work necessary in connection with Kendall’s part of the project — Eby was to do this with its own backhoe and operator.

On April 23, 1970, Garvey authorized Eby to commence construction on May 1, 1970; however, the formal written contract between them was not signed until late in December, 1970. In the middle part of May, 1970, Kendall entered the site and commenced its work on the project.

On June 15, 1970, after Kendall received its copy of the plans and specifications, it submitted a maximum cost figure on the project of $419,016. Although excavation was not specifically mentioned this figure included the cost of excavation necessary in connection with Kendall’s portion of the work.

The formal written subcontract between Eby and Kendall, prepared by the former, was dated June 10, 1970. On that date Eby, in accord with its custom, mailed two unsigned copies of the contract to Kendall. This contract specifically provided Eby was to furnish the labor and equipment for machine excavation and backfill. The contract price, by reason of this work by Eby, was stated as $5,576.00 less than the afore-mentioned figure, or $413,440. Kendall signed the two copies of the subcontract and returned them to Eby by letter of transmittal dated June 15, 1970. The contracts were then signed by Eby.

Meanwhile plaintiff’s injury occurred on June 12, 1970. The ditch in question had been dug June 9th by Eby’s backhoe operator using Eby’s backhoe. The next day pipe was run into it and inspected and backfilling had been commenced. The ditch had not been shored. On June 12th while the workers were waiting for another load of sand for backfill plaintiff asked his foreman if he should repair a gasket that looked out of place on the pipe in the ditch. The foreman said it was okay the way it was but plaintiff could suit himself. Plaintiff entered the ditch and it collapsed upon him. Plaintiff had been in the same ditch earlier that day.

This action was instituted by the filing of plaintiff s petition alleging that at a time when no contract existed between Eby and his employer Kendall he was injured by Eby’s negligence in failing to shore the ditch and in failing to warn him of the dangerous condi *37 tions. In the alternative he alleged that if a contract existed between the two contractors then Eby was Kendall’s subcontractor as to the excavation work.

Eby’s answer, among other things, denied the nonexistence of a contract and asserted exclusivity of the workmen’s compensation act. After the taking of depositions to which were attached the writings already referred to and entry of a pretrial conference order which included certain stipulations Eby filed a motion for summary judgment upon three grounds: The exclusivity of the remedy of workmen’s compensation, that there was no evidence of Eby’s negligence and plaintiff was guilty of contributory negligence as a matter of law. This motion was twice argued to the trial court. The court sustained the motion upon the first ground but made no ruling as to either of the negligence questions. The court found that on the date of the accident a contract existed between Garvey and Eby and a subcontract existed between Eby and Kendall; that Eby was not a subcontractor of Kendall. It ruled that the provisions of the workmen’s compensation act barred plaintiffs tort action. Plaintiff has appealed from the summary judgment.

Appellant Storts contends that prior to the accident on June 12, 1970, appellee Eby and his employer Kendall had not entered into a binding contract and did not do so until appellee formally signed the written contract on June 15, 1970. He concedes now, and did so also at trial level, that K. S. A. 44-503 (a) bars tort actions by employees of subcontractors against the prime contractor and, where this is the case, the employee’s exclusive remedy is a claim for workmen’s compensation, citing Watson v. Dickey Clay Mfg. Co., 202 Kan. 366, 450 P. 2d 10. He also concedes now as he did at trial that if a contract existed between the two his primary theory for recovery herein has no merit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
535 P.2d 908, 217 Kan. 34, 1975 Kan. LEXIS 402, Counsel Stack Legal Research, https://law.counselstack.com/opinion/storts-v-martin-k-eby-construction-co-kan-1975.