Kansas Power & Light Co. v. Burlington Northern Railroad

544 F. Supp. 1336, 1982 U.S. Dist. LEXIS 17479
CourtDistrict Court, D. Kansas
DecidedAugust 19, 1982
DocketCiv. A. 82-4018
StatusPublished
Cited by9 cases

This text of 544 F. Supp. 1336 (Kansas Power & Light Co. v. Burlington Northern Railroad) is published on Counsel Stack Legal Research, covering District Court, D. Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kansas Power & Light Co. v. Burlington Northern Railroad, 544 F. Supp. 1336, 1982 U.S. Dist. LEXIS 17479 (D. Kan. 1982).

Opinion

MEMORANDUM AND ORDER

SAFFELS, District Judge.

This is an action for declaratory judgment and for a permanent injunction to prevent defendant Burlington Northern Railroad Company [hereinafter BN] from *1339 breaching an agreement or violating a promise to Kansas Power and Light Company [hereinafter KPL] by putting into effect rates and charges for the transportation of coal from Belle Ayr, Wyoming, to KPL’s generating station at Jeffrey, Kansas, which rates would be higher than the rates and charges to which defendant agreed and promised to keep in effect.

In sum and substance, plaintiff seeks an order from this court finding that a contract existed between the parties for transportation of coal in unit trains from Wyoming to Kansas, and that defendant’s recently-approved seventy-five cents (75$) per ton rate increase is a breach of that contract.

Plaintiff contends that a rate of Eight and 28/100 Dollars ($8.28) per ton was the rate jointly agreed to by the parties for the movement of coal from Belle Ayr, Wyoming, to Kansas. Plaintiff contends that the agreement between the parties provided for an increase in this rate according to an escalation formula. BN, however, has made known its intention to raise the rate substantially higher than that called for in the purported agreement between the parties, and substantially higher than allowed for by the escalation formula.

On February 5, 1982, this court issued a temporary restraining order restraining BN from increasing the rate above that contained in the purported agreement between the parties, as escalated. On February 12, 1982, this court issued a similar preliminary injunction on the basis of a finding that there was a substantial likelihood that plaintiff would prevail on the merits, that irreparable harm would occur if the order were not entered, that the balance of hardship was in plaintiff’s favor, and that the public interest favored the granting of such an injunction. On March 12,1982, the court allowed the Kansas Corporation Commission to intervene in this lawsuit, they appeared by counsel at the trial on the merits, and have briefed the issues before the court. The trial of this case was held from May 17 through May 21, 1982, and concluded on June 1, 1982. The court has taken the matter under advisement and is now prepared to rule. Pursuant to Rule 52(a), Federal Rules of Civil Procedure, the court makes the following findings of fact and conclusions of law.

FINDINGS OF FACT

1. Plaintiff KPL is incorporated under the laws of Kansas, and has its principal place of business in Topeka, Kansas.

2. Defendant BN is incorporated under the laws of Delaware, and has its principal place of business in St. Paul, Minnesota.

3. KPL is a privately-owned electric company. By the late 1960s, KPL had decided to establish new electricity generating facilities within its service area.

4. KPL decided on coal as the fuel for its new generating plants, after ruling out other types of fuel such as natural gas and nuclear energy.

5. By the early 1970s, KPL undertook to find a location for its new generating facility, to plan for a new coal supply, to arrange for the transportation of the coal required, and to arrange for the construction of boilers for the new generating plant whose specifications had to be finally determined by the particular type of coal selected.

6. In mid-1971, it became apparent that some of the possible sites for the new plant and its coal supply would be served by BN, and others by the Union Pacific Railroad and other carriers.

7. During the latter half of 1971, both the Union Pacific Railroad and BN supplied KPL with tentative estimates of unit train rates from a number of possible coal producing areas in the west to several possible plant locations in Kansas.

8. Several meetings were held by KPL with these railroads.

9. Daric Miller was the KPL employee who was primarily responsible for the initial planning of the new power plant. At a meeting in Topeka at KPL headquarters on September 20, 1971, Mr. Miller asked BN to provide estimates for unit train rates for the transportation of coal from Powder River Basin, Wyoming, to several prospective power plant sites.

*1340 BN responded to Mr. Miller’s request by letter dated October 7, 1971, in which rates were quoted from Gillette, Wyoming, to four prospective locations in Kansas, and additional rates for other possible locations along the Kansas river.

10. On November 11,1971, BN and KPL representatives met to discuss several possible plant locations, preliminary rate estimates and a proposed escalation formula. Specifically, Mr. Miller asked BN to quote rates for three locations and to contact the Union Pacific Railroad regarding a joint movement of coal from Wyoming to Topeka, Kansas.

11. In response, on January 19,1972, BN sent a letter to KPL setting forth rates from Gillette, Wyoming, and Decker, Montana, to three sites in Kansas. BN indicated that the rate quotations would be subject to a rate escalation. The formula was set out in detail and was declared to be subject to the concurrence of a connecting line carrier for a joint movement. The letter also included a “formula intent” clause, which stated that the escalation formula would compensate the railroad for increases in the cost of transporting coal above a stated base-cost level, except for “gross inequities,” which had to be resolved by the mutual agreement of the parties.

12. The letter of January 19, 1972, stated:

“The rates quoted above are tendered with a time limit of six months from the date of this letter.”

KPL took no action in reliance on, and BN received no response to, the letter of January 19th within the six-month period.

13. The letter of January 19, 1972, also stated:

“This proposal is contingent upon the utility entering into a long-term contract of twenty or more years with coal producers on BN for the indicated coal requirements.”

14. KPL, however, was seeking a fifty-year initial commitment from a coal supplier. KPL has not made any claim, nor has it offered any evidence, that in obtaining its forty-year coal supply contract, it acted as a result of the twenty-year language contained in the January 19, 1972, letter.

15. By April 3,1972, KPL had tentatively rejected coal from the Hanna Basin because it was too costly and did not contain sufficient supplies of easily-mined coal.

16. By a memo to the file, dated July 5, 1972, Mr. Jeffrey, the Chief Executive Officer of KPL, had decided to proceed with negotiations with suppliers from the Powder River Basin. Further, in the same memo, Mr. Jeffrey indicated that he had decided that the site near Delia, Kansas, “had the best prospects” and that, in his opinion, KPL should proceed with planning the location of the new electric generating plant at that site.

17.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
544 F. Supp. 1336, 1982 U.S. Dist. LEXIS 17479, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kansas-power-light-co-v-burlington-northern-railroad-ksd-1982.