The City of Groton and Borough of Jewett City v. Federal Energy Regulatory Commission, Connecticut Light and Power Co., Intervenor

584 F.2d 1067, 190 U.S. App. D.C. 86, 1978 U.S. App. LEXIS 9642
CourtCourt of Appeals for the D.C. Circuit
DecidedAugust 10, 1978
Docket77-1361
StatusPublished
Cited by12 cases

This text of 584 F.2d 1067 (The City of Groton and Borough of Jewett City v. Federal Energy Regulatory Commission, Connecticut Light and Power Co., Intervenor) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The City of Groton and Borough of Jewett City v. Federal Energy Regulatory Commission, Connecticut Light and Power Co., Intervenor, 584 F.2d 1067, 190 U.S. App. D.C. 86, 1978 U.S. App. LEXIS 9642 (D.C. Cir. 1978).

Opinion

PER CURIAM:

Petitioners, six Connecticut municipal electric utility systems engaged in the retail distribution of electricity, contend that the Federal Power Commission should have rejected a wholesale electric service tariff filed on December 2, 1975 by intervenor Connecticut Light and Power Company. 1 Petitioners contend that the filing did not accurately estimate the impact of the new rate upon themselves, who are wholesale customers of the Company. The essential aggrievement alleged by petitioners, about which they provided no supporting materials either before the Commission or this court, is that the inaccurate estimate by the Company of revenues to be obtained under the new rate adversely affected their capacity to recoup their increased wholesale costs from their retail customers.

Petitioners’ initial motion to reject the tariff filing alleged inconsistencies and ambiguities as to the increase in payments they would be required to make under the new tariff. After the Commission denied this motion, 2 accepted the filing, and suspended its effectiveness for two months— until March 2,1976 — petitioners filed several additional motions calling upon the Commission to reject the tariff. The basis for these new requests, filed after the new rate *1069 had gone into effect, was that the actual increase in revenue being realized under the new schedule as compared with what would have been obtained had the superseded schedule remained in effect was more than double the increase estimated by the Company in an exhibit filed with the tariff. Petitioners contend that, even if the Commission did not err in initially refusing to reject the new tariff filing, it became obligated to do so when it became apparent that the revenue estimates contained in the filing were substantially inaccurate. 3

For the reasons explained hereinafter, we find no basis upon which to upset fhe Commission’s orders refusing to reject the tariff filing, either initially or after the disparities in the revenue estimates became known. The Commission’s authority to reject is limited, and within those limits is largely discretionary. Moreover, in this case the Commission carefully examined, and fully responded to, petitioners’ allegations, and we agree with its conclusion that rejection nunc pro tunc of the filing, even if that be within the Commission’s power, is not warranted on the record before us.

I

At the tariff filing stage, the Commission is authorized to make only a limited determination: whether the proposed tariff is “sufficiently complete for it to be able to decide whether or not to investigate and suspend the increased rate,” Municipal Light Boards v. Federal Power Commission, 146 U.S.App.D.C. 294, 450 F.2d 1341 (1971), cert. denied, 405 U.S. 989, 92 S.Ct. 1251, 31 L.Ed.2d 445 (1972), sustaining 18 C.F.R. § 35.5. 4 Federal Power Act § 205(d), 16 U.S.C. § 824d(d) (1970), provides that new tariffs filed with the Commission must “stat[e] plainly the change or changes to be made in the schedule or schedules then in force . . . .” 16 U.S.C. § 824d(d) (1970). The Commission in implementing the provision has required that numerous supporting exhibits accompany the filing of a change in rates, including a comparison of the quantity of service and revenues therefrom obtained under the new and superseded rate schedules, for both the year immediately preceding the rate change and the year immediately succeeding the change. 5 Although the Commission has recently restructured the cost-of-service *1070 data that must be submitted with the tariff filing, 6 the revenue impact data requirement has not been altered since it was introduced.

Consistently with the process described above, Commission authority to reject the rate schedule at the filing stage is limited to those filings which are patently defective on their face, Municipal Light Boards, supra, at 1346. A reviewing court’s ability to require a rejection of a rate filing is even more circumscribed, being limited to a determination of whether the agency acted arbitrarily and capriciously in accepting the filing.

The revenue impact exhibit objected to in the case at bar was not required by the terms of the Federal Power Act, 7 but was submitted pursuant to the filing requirements prescribed by the Commission. 8 Petitioners concede that the exhibit, which contained all required estimates and was over twenty pages in length, was in full “technical” compliance with the specifications in 18 C.F.R. § 35.13(b)(1). They contend, however, the Commission was under an obligation to reject the new tariff because the particular revenue estimates contained in this exhibit were inconsistent with other materials filed with the tariff and because they in fact proved to be inaccurate.

We have previously expressed the view in that the Commission’s filing requirements

are “mere aids to the exercise of the agency’s independent discretion,” and in both language and purpose leave room for a doctrine of “substantial’’ or “reasonable” compliance. American Farm Lines v. Black Ball Freight Service, 397 U.S. 532, 539, [90 S.Ct. 1288, 25 L.Ed.2d 547] (1970).

Municipal Light Boards, supra, at 1348. Although that statement was made with particular reference to certain other rules in § 35.13(b), we think that the same principle applies to the revenue comparison requirement at issue here. Thus, passing over for the moment the precise extent and nature of the alleged misrepresentations in the revenue exhibit, the Commission had broad discretion in deciding not to reject the tariff, either at the time of filing or at a later time. Where, as here, the procedural requirements laid out in the Commission’s filing regulations were complied with, 9 the Commission certainly cannot be said to have abused its discretion in determining that the filing did not require rejection, Municipal Light Boards, supra. 10

*1071 II

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jantzen v. Diller Telephone Co.
511 N.W.2d 504 (Nebraska Supreme Court, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
584 F.2d 1067, 190 U.S. App. D.C. 86, 1978 U.S. App. LEXIS 9642, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-city-of-groton-and-borough-of-jewett-city-v-federal-energy-regulatory-cadc-1978.