Kentucky Utilities Company v. Federal Energy Regulatory Commission, Jackson Purchase Electric Cooperative Corp., Cities of Barbourville, Intervenors

689 F.2d 207, 223 U.S. App. D.C. 24, 1982 U.S. App. LEXIS 25890
CourtCourt of Appeals for the D.C. Circuit
DecidedSeptember 7, 1982
Docket81-2027
StatusPublished
Cited by2 cases

This text of 689 F.2d 207 (Kentucky Utilities Company v. Federal Energy Regulatory Commission, Jackson Purchase Electric Cooperative Corp., Cities of Barbourville, Intervenors) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kentucky Utilities Company v. Federal Energy Regulatory Commission, Jackson Purchase Electric Cooperative Corp., Cities of Barbourville, Intervenors, 689 F.2d 207, 223 U.S. App. D.C. 24, 1982 U.S. App. LEXIS 25890 (D.C. Cir. 1982).

Opinion

WALD, Circuit Judge:

In this appeal, Kentucky Utilities Company (“KU” or “Company”) challenges an order of the Federal Energy Regulatory Commission (“FERC” or “Commission”) suspending implementation of a rate increase until five months and 21 days after the Company proposed that the new rate take effect. The Company argues first that FERC had no authority to delay the effective date for a period longer than five months, and, second, that FERC failed to state adequately its reasons for imposing even the maximum allowable suspension of five months. We find, however, that the Commission properly calculated the five-month suspension period from 60 days after the rate filing was brought into compliance with the applicable regulations. Further, we hold that the Commission adequately stated its reasons for imposing the maximum suspension period.

I. Background

In accordance with the requirement of the Federal Power Act that a utility give at least sixty days notice to the Commission and public of an increase in wholesale rates, 16 U.S.C. § 824d(d), KU submitted to FERC on March 17, 1981, 1 “revised provisions for electric service to KU’s wholesale for resale customers.” Letter from J. W. Bradley to Kenneth Plumb (Mar. 16, 1981), Joint Appendix (“J.A.”) at 11. The same Act authorizes the Commission to suspend the operation of a filed rate for a period not longer than “five months beyond the time when it would otherwise go into effect” upon “delivering to the public utility affected thereby a statement in writing of its reasons for such suspension.” 16 U.S.C. § 824d(e). Citing its “dire financial straits,” KU requested a June 1 effective date for its new rate and urged a nominal suspension of one day.

The Company proposed rate WPS-81 for its full requirements customers, the majority (26) of which were then subject to rate WPS-78. Fourteen of its full requirements customers, however, were charged under a separate 1967 contract. The Company proposed a different rate for its only other wholesale customer, the City of Paris, Kentucky, which was charged in accordance with a partial requirements agreement. 2 Letter from J. W. Bradley to Kenneth Plumb, List A (Mar. 16, 1981), J.A. at 14. Although WPS-81 was not intended to apply to the City of Paris, it applied to the remainder of KU’s wholesale customers, including the parties to the 1967 full requirements contract, since the Company had notified them that their agreement would terminate May 31, 1981. The Company had previously submitted a rate increase which would bring these customers under WPS-78 effective June 1. This was the same day as the Company now proposed that its new rate WPS-81 would take effect.

FERC publicly acknowledged receipt of the WPS-81 submissions in a “Notice of Filing” dated March 23, 1981, advising parties who wished to protest the proposed rate to file their petitions by April 13. J.A. at 229. On April 7, however, FERC notified the Company that its filing was “deficient.” Letter from Office of the Secretary to J. W. Bradley (undated), J.A. at 230. Specifically, FERC asked the Company to provide (1) data comparing revenues under the expir *209 ing full requirements contract rate with projected revenues under WPS-81; (2) a copy of the recently revised agreement between the Company and the City of Paris; and (3) a more detailed explanation of the operation of the fuel adjustment clause. 3 Pending receipt of the requested information, a filing date would not be assigned to the Company’s WPS-81 submissions.

On April 21, the Company responded that it was “happy to provide the information requested but [did] not concede that its filing was deficient with respect to any requirements of the Commission’s regulations.” Letter from Leonard Belter to Kenneth Plumb (April 21, 1981), J.A. at 255. Although conceding that the revised Paris agreement, which the Company enclosed, was “apparently inadvertently omitted” from the original submission, the Company expressed the view that the “pertinent rate information was contained in [its] filing letter” 4 and that “[t]o the extent that this omission constitute^] a technical deficiency, it [did] not . .. affect the filing with respect to any other customers.” The Company maintained that “nothing in the Commission’s filing regulations” required the other requested information. Nonetheless, the Company enclosed the requested revenue comparisons between the 1967 full requirements contract and WPS-81, although apparently assuming the adequacy of its initial submission of data comparing WPC-81 revenues with revenues generated under WPS-78. As to the fuel clause information, the Company stated that it had explained to Commission personnel that the original figures were composites and had been advised that further explanation was unnecessary.

The Company asserted, in sum, that its initial submissions were in substantial compliance with the regulations and that the Commission was without authority to delay the filing date. But, as alternatives, the Company asked that the Commission either assign the submissions a filing date no later than April 1 (so that, allowing for 60 days notice, June 1 could remain as the proposed effective date) or that FERC waive its regulations, 18 C.F.R. § 35.13, requiring cost-of-service data from the most recent calendar year, to permit the use of the data submitted (calendar year 1979).

On the basis of the March 17 submissions and the information provided in the letter of April 21, FERC issued an order, FERC Docket Nos. ER81-267-000 & ER81341:-000, (May 29, 1981) [hereinafter Order], J.A. at 262, which suspended implementation of the rate “for five months from 60 days after completion of the filing, to become effective on November 21, 1981, subject to refund pending hearing and decision,” id. at 7, J.A. at 268, thereby ruling that the filing date was April 21, not March 17. On June 24, the Company applied for rehearing, J.A. at 288, arguing again that the March 17 submission as to WPS-81 substantially complied with FERC regulations and additionally questioning the basis for the maximum five months suspension. The Company chose not to contest the delay of the effective date of the Paris contract filing. A month later, FERC “confirmed the propriety of the ‘deficiency letter’ ” and affirmed the five-month suspension. Order on Rehearing, FERC Docket Nos. ER81— 341-000 & ER81-267-000, July 24, 1981, at 3-4, J.A. at 303, 305-06. On August 19, the Company filed a petition for reconsideration, J.A. at 308, which was denied by operation of law on September 18. Pursuant to the judicial review provisions of the Federal Power Act, 5 the Company now appeals those orders.

*210 II. Analysis

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
689 F.2d 207, 223 U.S. App. D.C. 24, 1982 U.S. App. LEXIS 25890, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kentucky-utilities-company-v-federal-energy-regulatory-commission-jackson-cadc-1982.