Thames Shipyard & Repair Co. v. Willametz

428 A.2d 1143, 37 Conn. Super. Ct. 19, 37 Conn. Supp. 19, 1978 Conn. Super. LEXIS 168
CourtConnecticut Superior Court
DecidedDecember 13, 1978
DocketFile 20066
StatusPublished
Cited by8 cases

This text of 428 A.2d 1143 (Thames Shipyard & Repair Co. v. Willametz) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thames Shipyard & Repair Co. v. Willametz, 428 A.2d 1143, 37 Conn. Super. Ct. 19, 37 Conn. Supp. 19, 1978 Conn. Super. LEXIS 168 (Colo. Ct. App. 1978).

Opinion

Hale, J.

The defendant had seen a wooden forty-six foot yawl founder on rocks at Madison, in the latter part of September, 1973. He contacted the owner who had given it up for lost and purchased the vessel on September 24, 1973, for $500.

I

Facts

The defendant had the boat checked by an expert in wooden ship repairs who is also a skindiver. This man, Mr. Gronback, dove and swam around the vessel and examined it carefully. He testified that the yacht was resting on its starboard (right) side which was impaled on a rock. The hole through the hull was about midship. The keel was caught under another rock. The vessel was pointing about south southwest with its two masts extended toward shore at an angle of less than forty-five degrees.

*20 The boat was thus held in a relatively stable condition. The weather was very calm and remained so until October 25, a Friday.

The defendant had devised a plan to raise the boat by means of sinking and floating tanks to be attached under the masts and over the keel. He had posted a “keep off’ sign on the vessel but within a period of about two hours during which he left the boat to move his equipment from where he had it stored he discovered that someone had sawed the masts off. This thwarted his plans and he had to seek a more standard approach to raising the vessel.

He sought the services of at least two salvagers but neither had heavy enough equipment to raise the boat. The defendant then contacted the plaintiff company which had the necessary equipment and expertise.

The plaintiff sent its foreman to examine the wreck and also examined the charts as to the location of the wreck, depth of the water, location of rocks, etc., and, after negotiations, agreed to raise the boat the next day, October 3, transport it to New London and deliver it to the defendant. Mr. Willametz and two helpers arrived at the plaintiff’s place of business at the appointed time but the plaintiff’s tug was not ready to do the job. The job was delayed three days due to the failure of the plaintiff to prepare its equipment.

Throughout the period the sea was calm. On October 5, however, a storm came up and the yacht was pounded on the rocks for many hours and much more extensively damaged.

The plaintiff got its equipment underway on October 6 and raised the remains of the yacht with little trouble. The boat was then placed upon a lighter and towed to New London where it was placed aboard a flat-bed trailer hired by the defendant on which it was *21 hauled to the defendant’s place of business where it now rests in a yard. The remains are described as about half a hull.

II

Plaintiff’s Claim

The plaintiff claimed that it entered into an oral contract with the defendant based upon time and equipment.

The burden was upon the plaintiff to prove its case by a fair preponderance of the evidence. It failed to carry this burden. Its principal witness was the defendant himself who testified to an oral contract to raise a sunken sailing yacht for an agreed-upon price of $1050. Its next witness, the shipyard superintendent, knew nothing about the actual negotiations. The plaintiff’s president and negotiator of the contract exhibited a convenient memory which although strong on information about the usual method of charging for such a contract as that alleged, could recall very little about the actual negotiations and failed to refute the testimony of the defendant. While unable to recall much about the actual contract and the negotiations in which he was a principal, he could, interestingly enough, recall distinctly that his superintendent reported that a sea was running when it came time to explain why he delayed in picking up the wreck.

The court, therefore, finds the issues for the defendant on the plaintiff’s claim, and accordingly, judgment may enter for the defendant on said claim.

III

Defendant’s Counterclaim

As to the defendant’s counterclaim, the court is of the opinion that he has proved by a fair preponderance of the evidence that an oral contract *22 was entered into on October 2, 1973, for the plaintiff to raise the sunken yawl, “Trick’s End” on October 3, 1973, for the sum of $1050. Further, the court is of the opinion that the contract was breached by the plaintiff and that the failure of the plaintiff to perform the contract on time as agreed caused substantial loss to the defendant. The court is also of the opinion that the defendant had no choice but to wait for the plaintiff to do the job since he had investigated other salvagers and found the plaintiff company to be the only one in the area capable of handling the job.

In the opinion of the court, the correct measure of damages does not limit the defendant to the price paid for the boat as alleged by the plaintiff.

IV

Damages

Many of the questions posed in this case can be answered by turning to the principle laid out in the old English case of Hadley v. Baxendale, 9 Exch. 341 (1854). A fair statement of the principle presented therein can be found in 22 Am. Jur. 2d, Damages § 56: “. . . the damages recoverable for breach of contract are such as may fairly and reasonably be considered as arising naturally-that is, according to the usual course of things-from the breach of the contract itself, or such as may reasonably be supposed to have been in the contemplation of both parties at the time they made the contract, as the probable result of its breach.” See also McCormick, Damages § 138. In other words, Hadley lays down two rules: (1) losses must be of the type usually resulting from the breach of like contracts, or (2) if there are special circumstances, and the damages arise as a result of those special circumstances, recovery can only be allowed if the defaulting party was aware of the special circumstances at the time of entering into the contract. Obviously, as formulated, this rule is suffi *23 cient to be applicable to every breach of contract case. In point of fact, the rule’s wide applicability has caused it to be adopted by virtually every state. In Connecticut the rule of Hadley has been the law since at least the early 1900s and continues today. Shopper Publishing Co. v. Skat Co., 90 Conn. 317, 97 A. 317 (1916); Mazzotta v. Bornstein, 104 Conn. 430, 133 A. 677 (1926); Valente v. Affinito, 118 Conn. 581, 173 A. 235 (1934); Talbot v. Waterbury Hospital Corporation, 22 Conn. Sup. 149, 164 A.2d 162 (1960); Duffy v. Woodcrest Builders, Inc., 2 Conn. Cir. Ct. 137, 196 A.2d 606 (1963); Manning v. Pounds, 2 Conn. Cir. Ct. 344, 199 A.2d 188 (1963).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lone Wolf Advertising v. Penniman, No. Cv 99 043 0737 (Nov. 15, 2000)
2000 Conn. Super. Ct. 13926 (Connecticut Superior Court, 2000)
Ambrogio v. Beaver Road Associates, No. Cv96-0475509s (Nov. 19, 1999)
1999 Conn. Super. Ct. 14891 (Connecticut Superior Court, 1999)
Torres v. Allen, No. Cvnh 96037424 (Feb. 18, 1997)
1997 Conn. Super. Ct. 696-O (Connecticut Superior Court, 1997)
New Haven Savings Bank v. Saldamarco, No. Cv91-0323203s (Sep. 16, 1996)
1996 Conn. Super. Ct. 5360 (Connecticut Superior Court, 1996)
Ajl Enterprises Ltd. v. Arrow Paper Party Stores, No. 529862 (Jan. 18, 1995)
1995 Conn. Super. Ct. 755 (Connecticut Superior Court, 1995)
Prishwalko v. Schaefer Insp. Serv., No. 286826. (Jan. 31, 1991)
1991 Conn. Super. Ct. 270 (Connecticut Superior Court, 1991)
Gargano v. Heyman
525 A.2d 1343 (Supreme Court of Connecticut, 1987)
Thames Shipyard & Repair Co. v. Willametz
439 A.2d 948 (Supreme Court of Connecticut, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
428 A.2d 1143, 37 Conn. Super. Ct. 19, 37 Conn. Supp. 19, 1978 Conn. Super. LEXIS 168, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thames-shipyard-repair-co-v-willametz-connsuperct-1978.