Thalle Construction Company

CourtArmed Services Board of Contract Appeals
DecidedAugust 13, 2025
Docket63685, 63719, 63720, 63721, 63734
StatusPublished

This text of Thalle Construction Company (Thalle Construction Company) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thalle Construction Company, (asbca 2025).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeals of - ) ) Thalle Construction Company ) ASBCA Nos. 63685, 63719, 63720 ) 63721, 63734 ) Under Contract No. W912P5-16-C-0001 )

APPEARANCES FOR THE APPELLANT: Lochlin B. Samples, Esq. Alexander S. Hoppestad, Esq. Zachary B. Zimmerman, Esq. Smith, Currie Oles LLP Atlanta, Georgia

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Thomas M. Taff, Jr., Esq. Kelsey C. Morgan, Esq. Monique M. Raub, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Nashville

OPINION BY ADMINISTRATIVE JUDGE SWEET ON THE GOVERNMENT’S MOTION FOR PARTIAL SUMMARY JUDGMENT

These appeals involve a contract between the United States Army Corps of Engineers, Nashville District (government) and the appellant Thalle Construction Company (Thalle) for the construction of an auxiliary dam reinforcing berm and left rim stabilization at Center Hill Reservoir in Dekalb County, Tennessee. Thalle raises several claims on appeal, including that: (1) it had to use a higher-cost concrete quartz aggregate supplier than the supplier prequalified in the specifications upon whom Thalle had based its proposal because the original supplier went out of business (Aggregate Supplier Claims) (ASBCA No. 63685); (2) Thalle had to import topsoil to use in areas where the contract did not require topsoil (Non-Topsoil Areas) instead of using topsoil from the stripped areas (Topsoil Claims) (ASBCA No. 63721); and (3) government delays pushed Thalle’s performance into a period of worse seasonal adverse weather (Weather Delay Claims) (ASBCA No. 63734). The government has filed a motion for partial summary judgment (Motion) on the Aggregate Supplier, the Topsoil, and the Weather Delay Claims (gov’t mot. at 1).

As discussed in greater detail below, we grant the Motion as to the Aggregate Supplier Claims because Thalle has failed to raise a genuine issue of material fact suggesting that having to use a higher-cost quartz aggregate supplier constituted a constructive change, involved superior knowledge, constituted a breach of the duty of good faith and fair dealing, or involved a defective specification. We also grant the Motion as to the Topsoil Claims to the extent that Thalle alleges that the government improperly required Thalle to import Topsoil because the contract did not indicate that all of the needed topsoil was available from the stripped areas. However, we deny the Motion as to the Topsoil Claims to the extent that Thalle alleges that the government improperly required Thalle to install topsoil in Non-Topsoil Areas because there is a genuine issue of material fact as to whether the government required Thalle to install topsoil in Non-Topsoil Areas. Finally, we deny the Motion as to the Weather Delay Claims because there is a genuine issue of material fact as to if government delays pushed Thalle’s performance into a period of worse seasonal adverse weather than it would have experienced but-for the government delay.

SUMMARY JUDGMENT STANDARD

We will grant summary judgment only if there is no genuine issue as to any material fact, and the moving party is entitled to judgment as a matter of law. Celotex Corp. v. Catrett, 477 U.S. 317, 322-23 (1986). All significant doubt over factual issues must be resolved in favor of the party opposing summary judgment. Mingus Constructors, Inc. v. United States, 812 F.2d 1387, 1390-91 (Fed. Cir. 1987). In deciding summary judgment motions, we do not resolve controversies, weigh evidence, or make credibility determinations. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 255 (1986). Moreover, we draw all reasonable inferences in favor of the non-movant. Id. A genuine issue of material fact arises when the non-movant presents sufficient evidence upon which a reasonable fact-finder, drawing the requisite inferences and applying the applicable evidentiary standard, could decide the issue in favor of the non-movant. C. Sanchez & Son, Inc. v. United States, 6 F.3d 1539, 1541 (Fed. Cir. 1993).

AGGREGATE SUPPLIER CLAIMS (ASBCA NO. 63685)

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. On September 30, 2015, the government issued Request for Proposals No. W912P5-14-R-003 (Request for Proposals) for the construction of an auxiliary dam reinforcing berm and left rim stabilization at Center Hill Reservoir in Dekalb County, Tennessee (R4, tab 1 at 1-2; GSUMF ¶ 1; ARGSUMF ¶ 1). 1

1 “GSUMF” refers to the government’s statement of undisputed material fact. “ARGSUMF” refers to Thalle’s response to the GSUMF. 2 2. Specification 03 37 23 (CONCRETE), ¶ 2.1.4.2 (CONCRETE AGGREGATE SOURCES) stated that:

Concrete aggregates may be furnished from a source designated by the Contractor and accepted by the [contracting officer’s (CO’s) representative (COR)], subject to the conditions stated herein. The COR will evaluate the quality of data based on the criteria of the paragraph QUALITY. The proposed aggregate source shall be capable of meeting the requirements in the paragraph QUALITY.

a. List of Prequalified Sources. The following sources were evaluated during the design phase of the project in 2012-2013 and were found at that time capable of meeting the quality requirements when suitably processed and the listed restrictions applied. . . . These sources shall meet the requirements in paragraph QUALITY.

PREQUALIFIED AGGREGATE SOURCES QUARTZ FINE ASTM C33/C33M LIMESTONE D-BASE and COARSE AGGREGATE 2 AGGREGATE F1: Monterey Sand C1: Vulcan Materials Company Monterey, TN Cookeville, TN

Restriction: must be used with a Restriction: Must be used with a minimum 30% Class F Fly Ash and Low minimum 30 % Class F Fly Ash Alkali Cement Only the top 151 feet of bench one is acceptable, material below 151 feet is

2 Concrete is a mixture of cementious material, aggregate, and water. Aggregate is an inert filler, but it is a necessary component that defines the concrete’s thermal and elastic properties and dimensional stability. There are two different types of aggregate—coarse and fine—which have different gradation. The Effect of Aggregate Properties on Concrete, https://www.engr.psu.edu/ce/courses/ce584/ concrete/library/materials/aggregate/aggregatesmain.htm (last visited Jul. 21, 2025). ASTM C33 is the specification from the American Society for Testing and Materials that defines the requirements for grading and quality of fine and coarse aggregate for use in concrete. ASTM International, ASTM C33/C33M- 24a Standard Specification for Concrete Aggregates, https://store.astm.org/ c0033_c0033m-24a.html (last visited Jul 21, 2025).

3 rejected and must not be included in project aggregate. F2: Sand Products C2: Rogers Group Monterey, TN Liberty, TN

Restriction: must be used with a Restriction: Must be used with a minimum 30% Class F Fly Ash and Low minimum 30 % Class F Fly Ash Alkali Cement Only the top 62 feet of bench 1 is acceptable; material below 62 feet is rejected and must not be included in project aggregate.

Both prequalified sources have restrictions on mining depth. . . . If the Contractor cannot prove the aggregate comes from the acceptable depths, the Government shall refuse the aggregate and the Contractor shall remove and replace the aggregate at no cost to the Government.

b. Non-prequalified Sources. Any source proposed by the Contractor shall meet the requirements in paragraph QUALITY.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Holland v. United States
621 F.3d 1366 (Federal Circuit, 2010)
Stockton East Water District v. United States
583 F.3d 1344 (Federal Circuit, 2009)
Bell Bci Co. v. United States
570 F.3d 1337 (Federal Circuit, 2009)
Centex Corp. v. United States
395 F.3d 1283 (Federal Circuit, 2005)
Brock & Blevins Company, Inc. v. The United States
343 F.2d 951 (Court of Claims, 1965)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
C. Sanchez and Son, Incorporated v. United States
6 F.3d 1539 (Federal Circuit, 1993)
Coast Federal Bank, Fsb v. United States
323 F.3d 1035 (Federal Circuit, 2003)
Scott Timber Co. v. United States
692 F.3d 1365 (Federal Circuit, 2012)
bell/heery v. United States
739 F.3d 1324 (Federal Circuit, 2014)
Metcalf Construction Company v. United States
742 F.3d 984 (Federal Circuit, 2014)
Agility Public Warehousing Co. KSCP v. Mattis
852 F.3d 1370 (Federal Circuit, 2017)
Wunderlich Contracting Co. v. United States
351 F.2d 956 (Court of Claims, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
Thalle Construction Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thalle-construction-company-asbca-2025.