Tennessee Asphalt Company v. Brian Fultz

CourtCourt of Appeals of Tennessee
DecidedSeptember 20, 2013
DocketE2013-00240-COA-R3-CV
StatusPublished

This text of Tennessee Asphalt Company v. Brian Fultz (Tennessee Asphalt Company v. Brian Fultz) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tennessee Asphalt Company v. Brian Fultz, (Tenn. Ct. App. 2013).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE August 7, 2013 Session

TENNESSEE ASPHALT COMPANY V. BRIAN FULTZ

Appeal from the Chancery Court for Knox County No. 1811593 Hon. Michael W. Moyers, Chancellor

No. E2013-00240-COA-R3-CV-FILED-SEPTEMBER 20, 2013

This is a breach of contract case in which Company sought to hold Defendant personally liable for the amount remaining on a contract. During Company’s proof-in-chief, Defendant used parol evidence attempting to show that while he signed the contract, the parties understood that he was signing as a representative of his business. Following Company’s presentation of its proof, Defendant moved for involuntary dismissal pursuant to Rule 41 of the Tennessee Rules of Civil Procedure. The trial court granted Defendant’s motion, finding that Company failed to establish that Defendant was personally liable. Company appeals. We affirm the decision of the trial court.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed; Case Remanded

J OHN W. M CC LARTY, J., delivered the opinion of the Court, in which C HARLES D. S USANO, J R., P.J., and T HOMAS R. F RIERSON, II, J., joined.

Dale Bohannon, Cookeville, Tennessee, for the appellant, Tennessee Asphalt Company.

Edward J. Shultz, Knoxville, Tennessee, for the appellee, Brian Fultz.

OPINION

I. BACKGROUND

Brian Fultz (“Defendant”), through his construction company Fultz Holdings, LLC (“Fultz Holdings”), was building Briarcliff Subdivision (“Briarcliff”) in Harrogate, Tennessee. Defendant contracted with Tennessee Asphalt Company (“Company”) to grade and pave the roads and to install water and sewer lines for Briarcliff. The initial agreement consisted of four estimates, which Defendant signed without any mention of Fultz Holdings. The first estimate related to the grading of the property, the second and third estimates related to the installation of water and sewer lines, and the fourth estimate related to the paving of the property. The Company submitted five change orders and several applications for payment. Each change order and application for payment was addressed to Fultz Holdings. The site drawings for the project also listed Fultz Holdings as the owner of the property. As the work progressed, Defendant became unhappy with the work and eventually refused to submit the amount allegedly remaining on the contract, namely $40,125.

Company filed suit, alleging that Defendant was personally liable for the amount remaining on the contract, prejudgment interest, and attorney fees. Defendant admitted signing the estimates but asserted that he was not personally liable because he intended to contract with Company as Fultz Holdings. He alternatively asserted that neither he nor Fultz Holdings were liable for any amount remaining pursuant to the contract because Company “failed to correct defects in work it performed pursuant to the contract.”

The case proceeded to trial, where several witnesses testified. Brad Cabbage, a grading estimator for Company, testified that he was responsible for meeting with customers, preparing bids, and billing. He stated that he met with Defendant to discuss grading the roads and getting “everything ready for the installation of stone and asphalt and curb.” He prepared an estimate that listed Defendant as the purchaser, referred to the site drawings, and detailed the work that was to be performed and the price for the labor and materials. He stated that in lieu of producing a separate contract, Company required customers to either sign the estimate or generate a separate contract for attachment to the estimate. He claimed that Defendant signed the estimate on August 21, 2007. He asserted that he continually met with Defendant, who never mentioned the involvement of Fultz Holdings.

Mr. Cabbage testified that Defendant also asked him to install the water and sewer lines. He related that while Company did not normally provide those services, he hired a separate company to complete the project. He prepared two additional estimates that listed Defendant as the purchaser, referred to the site drawings, and detailed the work that was to be performed and the price for the labor and materials. Defendant signed the estimates on September 17, 2007. Approximately one month later, he met with Defendant to discuss changes to the project. As a result of the meeting, someone in his office prepared a change order. Further meetings with Defendant led to three additional change orders. Neither party signed the four change orders, which listed Fultz Holdings as the owner and Company as the contractor.

Mr. Cabbage conceded that in preparing his estimates, he referred to Defendant’s site drawings, which listed Fultz Holdings as owner and Defendant as the person to contact. He

-2- acknowledged that the applications for payment also listed Fultz Holdings as owner and that Company never billed Defendant personally.

Kelly McCartt, who was employed by Company as an estimator, testified that he worked with Defendant regarding the base and paving of Briarcliff. He admitted that he prepared an estimate that referred to the site plans and was signed by Defendant on August 22, 2007. He also altered the terms of the original estimate with a change order that was addressed to “Fultz Holdings Inc.” and signed by Defendant as follows:

/s/ Brian Fultz Brian Fultz, Fultz Holdings Inc.

Likewise, he sent three letters to Defendant that also referred to “Fultz Holdings Inc.” He insisted that he “always dealt with” Defendant, but he conceded that the application for payment, the work order, and the final invoice listed Fultz Holdings as owner of the property.

Phil Brown, Vice President of Company, testified that he was responsible for collecting “old receivables.” He identified the summary of open accounts prepared by his office and admitted that according to the document, Fultz Holdings was liable for the amount remaining on the contract.

At the close of Company’s case, Defendant moved for involuntary dismissal, arguing that Company had failed to prove that he was a party to the contract. He admitted that he failed to indicate on the estimates that he was signing in his representative capacity but asserted that the parol evidence rule did not prohibit the introduction of additional documents to correctly identify the parties to the contract. The trial court agreed, finding that the estimates did not constitute the entirety of the contract when the change orders altered the terms and when the contract could not be fulfilled without referring to the site drawings, which were specifically referenced in the estimates. The court found that the addition of the change orders and the site drawings to the contract created an ambiguity as to the identify of the party with whom Company had contracted. The court held that it was necessary to consider additional documentation to ascertain the relationship between the parties and the identity of those involved. In consideration of the additional evidence, the court stated, that

the actual course of dealings and intent of the parties was that [Fultz Holdings] was the party with whom [Company] had contracted, and from whom [Company] expected to be paid.

The court dismissed the complaint against Defendant. This timely appeal followed.

-3- II. ISSUE

We consolidate and restate the issues raised on appeal as follows:

Whether the trial court erred in holding that Defendant was not personally liable for the remaining amount due on the contract.

III. STANDARD OF REVIEW

The Tennessee Rules of Civil Procedure provide for involuntary dismissal as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Christenberry v. Tipton
160 S.W.3d 487 (Tennessee Supreme Court, 2005)
Realty Shop, Inc. v. RR Westminster Holding, Inc.
7 S.W.3d 581 (Court of Appeals of Tennessee, 1999)
Wilson v. Moore
929 S.W.2d 367 (Court of Appeals of Tennessee, 1996)
Gredig v. Tennessee Farmers Mutual Insurance Co.
891 S.W.2d 909 (Court of Appeals of Tennessee, 1994)
Airline Construction, Inc. v. Barr
807 S.W.2d 247 (Court of Appeals of Tennessee, 1990)
Stickley v. Carmichael
850 S.W.2d 127 (Tennessee Supreme Court, 1992)
City of Columbia v. C.F.W. Construction Co.
557 S.W.2d 734 (Tennessee Supreme Court, 1977)
Planters Gin Co. v. Federal Compress & Warehouse Co.
78 S.W.3d 885 (Tennessee Supreme Court, 2002)
Bonastia v. Berman Bros., Inc.
914 F. Supp. 1533 (W.D. Tennessee, 1995)
GuestHouse International, LLC v. Shoney's North America Corp.
330 S.W.3d 166 (Court of Appeals of Tennessee, 2010)
Cole v. Clifton
833 S.W.2d 75 (Court of Appeals of Tennessee, 1992)
Hanover Insurance Company v. Haney
425 S.W.2d 590 (Tennessee Supreme Court, 1968)
Maddox v. Webb Construction Co.
562 S.W.2d 198 (Tennessee Supreme Court, 1978)
Frank Rudy Heirs Associates v. Moore & Associates, Inc.
919 S.W.2d 609 (Court of Appeals of Tennessee, 1995)
Guiliano v. Cleo, Inc.
995 S.W.2d 88 (Tennessee Supreme Court, 1999)
Brewer v. Haynes
681 S.W.2d 551 (Court of Appeals of Tennessee, 1984)
United American Bank of Memphis v. First Citizens National Bank of Dyersburg
764 S.W.2d 555 (Court of Appeals of Tennessee, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
Tennessee Asphalt Company v. Brian Fultz, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tennessee-asphalt-company-v-brian-fultz-tennctapp-2013.