City of Columbia v. C.F.W. Construction Co.

557 S.W.2d 734, 1977 Tenn. LEXIS 678
CourtTennessee Supreme Court
DecidedNovember 25, 1977
StatusPublished
Cited by122 cases

This text of 557 S.W.2d 734 (City of Columbia v. C.F.W. Construction Co.) is published on Counsel Stack Legal Research, covering Tennessee Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Columbia v. C.F.W. Construction Co., 557 S.W.2d 734, 1977 Tenn. LEXIS 678 (Tenn. 1977).

Opinion

OPINION

BROCK, Justice.

Plaintiff, City of Columbia, sues the defendants, C.F.W. Construction Company, a general contractor, and Sherman Concrete Pipe Company, a pipe manufacturer, for specific performance or, in the alternative, for damages alleging deficiencies in performance of a sewer construction contract. Right to relief was based both upon the original construction contract and a later executed guaranty agreement. At the close of plaintiff’s proof the Chancellor granted defendants’ motion for dismissal of the action. Holding that the subsequently executed guaranty agreement superseded the original construction contract and that the City had failed to offer evidence of a right to relief under the guaranty in that it had not identified specific defects of construction of the sewer line, the Court of Appeals affirmed the trial court. We granted certiorari.

I

In October, 1960, the City of Columbia (City) and C.F.W. Construction Company (CFW) entered into a contract whereby CFW agreed to construct certain sanitary sewer improvements for the City in accordance with plans and specifications prepared by consulting engineers, Zimmerman, Evans and Leopold (Engineer). The contract, together with an addendum, specified the use of reinforced concrete pipe for a portion of the sewer line, to be joined with flexible rubber-joint gaskets in order to obtain water-tight conditions and to allow for settling of the pipes. The specifications called for leakage and infiltration tests:

“The maximum allowable infiltration into the sewer lines shall be limited to 10,000 gallons per 24 hours per mile of sewer. This clause does not relieve the contractor of the necessity of making the sewers as tight as possible. Sewers which exceed this limit will not be accepted and the contractor shall take such steps as are necessary to bring the infiltration within the above allowance. * * * The test shall be made following a period of heavy rain and when the ground is saturated.” (Contract, T4-09(D).)

Before completion of the project, excessive leakage at the pipe joints prompted *736 CFW to undertake repairs by sealing the leaking joints with a cement mortar, although this procedure was not in accordance with contract specifications. Infiltration tests conducted subsequent to the repairs on this segment of the construction indicated 153% and 143% of the maximum allowable infiltration rate. Because of the deviation from contract requirements and the Engineer’s consequent apprehension that defects might eventually appear in the sewer line with the settling of the pipes and consequent cracking of the rigid joints created by the mortar repair, the City ultimately refused to accept the segment of the project between manholes J-32 and J — 1.

In order to induce the City to accept and pay for the work, CFW and the pipe manufacturer and supplier, Sherman Concrete Pipe Company (Sherman Pipe) entered into a guaranty agreement with the City in March, 1962.

Pertinent provisions of the guaranty agreement are as follows:

“The said C.F.W. Construction Company has laid or installed a sewer line improvement for the City of Columbia, Tennessee, under and pursuant to a contract . which contract is hereby incorporated into this agreement by reference.
* * * * * *
“In order to induce the owner to accept said portion of sewer line work and to pay for same in accordance with the contract hereinabove referred to . the undersigned supplier and contractor . obligate . . . themselves . to repair and correct any and all defects arising from defective workmanship and materials that may be found in said portion of said sewer line in question within a period of ten CIO) years. including the replacement of portions of said line when necessary; said ten year period to begin at the expiration date of the one year guaranty provided under Paragraph GC-12 of said contract herein-above referred to.
“Without limiting the generality of the foregoing guaranty provision, the undersigned agree that during this ten year period:
“1. That Paragraph GC-12 of said contract is hereby extended for an additional ten year period insofar as it relates to that portion of the sewer line described above.
“2. That said Engineer, its successors or assigns, shall determine when there has been a defect in said portion of the sewer line. Upon notification by said Engineer or the City of Columbia, the undersigned shall within a reasonable time undertake the necessary repair and corrective measures, including the replacement of any portion of said sewer line that in the judgment of the Engineer requires replacement.
“3. ... In general, Paragraph GC-31 of said contract shall govern the corrective or replacement work if the need arises.
“4. The undersigned agree to pay for all damages caused by any defects determine 1 to result from the unfitness and unsoun Iness of the portion of said line hereinabove referred to, including damages to other work resulting therefrom. ******
“6. The undersigned agree to pay all expenses, including engineer’s fees and costs of plans and specifications incurred because of work required under this contract and guaranty.
******
“8. The Supplier and Contractor shall pay for all damages resulting from their failure to make the necessary repairs promptly after notice from the city or from said engineer that a defect has occurred.
“9. The said contract herein made a part of this agreement shall, where applicable, apply to any replacement work called for by reason of this agreement.
***** *
“11. The City of Columbia by accepting this guaranty does not waive its rights under Paragraph GC-12 of said contract.
******
“The City of Columbia shall be deemed to have accepted this guaranty when pay *737 ment is made of the balance due under said contract.” (Underscoring added.)

A guaranty bond required by the guaranty was executed by a corporate surety and remained in effect for the first five years of the guaranty. Simultaneous with the guaranty agreement, CFW and Sherman Pipe entered into an agreement between themselves to share equally any obligations under the Guaranty with the City.

Thereafter, on August 20, 1962, the City accepted the construction and paid the balance owed under the contract.

Paragraph GC-12 of the original contract, extended for an additional ten years by the guaranty, provides as follows:

“GC-12. GUARANTEE: CORRECTION OF THE WORK:
For a period of at least one year after the completion of the Contract, the Contractor warrants the fitness and soundness of all work done and materials and equipment put in place under the Contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Charles W. Shoffner v. Ephraim Muvire Urevbu
Court of Appeals of Tennessee, 2025
IN Re Zae'Alei R.
Court of Appeals of Tennessee, 2025
Stephen H. Bills v. Joe B. Barton
Court of Appeals of Tennessee, 2024
State of Tennessee v. Capone Carroll Strange
Court of Criminal Appeals of Tennessee, 2022
Candice Mosby v. Fayette County Board of Education
Court of Appeals of Tennessee, 2020
Zula Wortham v. Kroger Limited Partnership I
Court of Appeals of Tennessee, 2020
Lane, Thomas v. Cleveland Utilites
2017 TN WC 59 (Tennessee Court of Workers' Comp. Claims, 2017)
Corley v. Wal-Mart Stores East, LP
637 F. App'x 210 (Sixth Circuit, 2016)
State of Tennessee v. Lesergio Duran Wilson
Court of Criminal Appeals of Tennessee, 2015
Cincinnati Insurance Company v. Larry Banks
610 F. App'x 453 (Sixth Circuit, 2015)
Kathryne B.F. v. Michael B.
Court of Appeals of Tennessee, 2014
Rock Ivy Holding, LLC v. RC Properties, LLC
464 S.W.3d 623 (Court of Appeals of Tennessee, 2014)
In Re: Adoption of Jordan F.J.
Court of Appeals of Tennessee, 2013
In Re Estate of Price
273 S.W.3d 113 (Court of Appeals of Tennessee, 2008)
Building Materials Corp. v. Britt
211 S.W.3d 706 (Tennessee Supreme Court, 2007)
Administrative Resources, Inc. v. Barrow Group, LLC
210 S.W.3d 545 (Court of Appeals of Tennessee, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
557 S.W.2d 734, 1977 Tenn. LEXIS 678, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-columbia-v-cfw-construction-co-tenn-1977.