John Pirtle d/b/a Third Coast Builders v. The Tunney Group, LLC

CourtCourt of Appeals of Tennessee
DecidedOctober 31, 2025
DocketM2023-01830-COA-R3-CV
StatusPublished

This text of John Pirtle d/b/a Third Coast Builders v. The Tunney Group, LLC (John Pirtle d/b/a Third Coast Builders v. The Tunney Group, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John Pirtle d/b/a Third Coast Builders v. The Tunney Group, LLC, (Tenn. Ct. App. 2025).

Opinion

10/31/2025 IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE November 7, 2024 Session

JOHN PIRTLE D/B/A THIRD COAST BUILDERS v. THE TUNNEY GROUP, LLC ET AL.

Appeal from the Chancery Court for Davidson County No. 21-1046-II Anne C. Martin, Chancellor ___________________________________

No. M2023-01830-COA-R3-CV ___________________________________

A general contractor hired a subcontractor to perform plumbing work on a condominium construction project. After completing the first phase of the work, the general contractor paid a portion of the total contract amount to the subcontractor. The general contractor then separately hired the subcontractor to do some excavation work on the project, though no contract was created for this aspect of the work, and no payment amount was discussed. After completion of the excavation work, a dispute arose over the amount charged to the general contractor by the subcontractor. The general contractor refused to pay what it believed to be too high a fee. The subcontractor insisted that the amount charged was reasonable. The general contractor then asserted that the subcontractor had materially breached the plumbing contract during the first phase. The general contractor eventually terminated the contract. The subcontractor filed suit. After a bench trial, the trial court concluded that the general contractor breached the parties’ contract, awarding lost profits and attorney’s fees to the subcontractor pursuant to the plumbing contract. The trial court also awarded damages to the subcontractor for the excavation work under a quantum meruit theory. The general contractor appeals. We affirm.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed and Remanded

JEFFREY USMAN, J., delivered the opinion of the court, in which THOMAS R. FRIERSON II, and W. NEAL MCBRAYER, JJ., joined.

Mark Alexander Carver and Todd E. Panther, Nashville, Tennessee, for the appellants, American Contractors Indemnity Company, The Eagle Nashville, LLC, and The Tunney Group, LLC.

Timothy H. Nichols, Nashville, Tennessee, for the appellee, John Pirtle. OPINION

I.

This case involves a dispute between a general contractor and a subcontractor related to work performed on a condominium project in Nashville. Ed Tunney, an experienced contractor, was the principal of both the project’s owner, The Eagle Nashville, LLC, and the general contractor, The Tunney Group (collectively Tunney). In April 2020, Tunney contracted with Appellee John Pirtle d/b/a Third Coast Builders, a licensed master plumber, to do $120,000 of plumbing work on the project. The scope of work included primarily interior plumbing work, along with additional tap and sewer work.

The interior plumbing work consisted of two phases, the rough-in phase and the trim-out phase. By March 2021, Mr. Pirtle had completed the rough-in phase. In doing so, Mr. Pirtle, who oversaw the work, made use of independent contractors who were not individually licensed to assist in his work. The work passed inspection. Tunney paid Mr. Pirtle 60% of the contract price, approximately $69,000. Although Mr. Pirtle’s expenses exceeded that amount at this point in the process, he accepted the payment, expecting to receive the remainder after completing the trim-out phase. After the rough-in phase was over, Mr. Pirtle had to wait for other subcontractors to finish their work before he could complete the trim-out phase.

During this interregnum, Tunney approached Mr. Pirtle about excavation, hauling, and grading work on the project involving removing a portion of an embankment and allowing the construction of a retaining wall. This work was unrelated to the plumbing contract. In addition to being licensed as a master plumber, Mr. Pirtle is also registered with the Metropolitan Government of Nashville and Davidson County Public Works Department to perform excavation. Mr. Pirtle agreed to perform the work. However, no written contract was created, and no price was discussed. This was not the first time that Mr. Pirtle had done excavation work on the condominium project. In March 2020, he had removed 25 loads of asphalt at a cost of $750 per load, for which Tunney paid him for his services.

Like the plumbing work, the latter excavation work consisted of two phases: rough grading and finish grading. Tunney was “anxious for the work to be done quickly”; accordingly, Mr. Pirtle promptly performed the work over weekends on an expedited basis. In April 2021, Mr. Pirtle completed the rough grading, which involved hauling off 18 loads of dirt. In May 2021, Mr. Pirtle completed the finish grading, which involved hauling off 109 loads of dirt. The work had to be completed at particular elevations pursuant to the site plan because of concerns about storm water and drainage. A laser level had to be used throughout to ensure compliance with the elevation requirements. Mr. Pirtle himself operated the laser level on the site and was directly involved in the work. Because he -2- owned some but not all of the necessary equipment for the project, Mr. Pirtle used some of his own equipment and leased other equipment, including trucks. He also hired contract labor to complete the work. His expenses for this work were $32,686.69. This did not include his time working on the project. Mr. Tunney had personally observed some of the work, and he raised no complaints about the quality of the work either at the time or later.

On June 3, 2021, Mr. Pirtle sent a $74,400 invoice for the excavation work to Tunney. The invoice requested $9,000 for the April work, charging $500 for each of the 18 loads hauled. It also requested $65,400 for the May work, charging $600 for each of the 109 loads of dirt hauled. Mr. Pirtle testified that this was his first excavating job like this, so he based the invoice amount on the industry standard of charging per load, which he learned from talking to other contractors and searching on the internet.

Tunney deemed the invoice to be exorbitant and refused to pay it. Just over a week later, on June 11, Tunney sent a letter to Mr. Pirtle notifying him that he was in default on the plumbing contract. Tunney alleged three grounds for default: (1) improperly installed shower controls and showerheads; (2) failing to install the elevator pit pump; and (3) potentially using unlicensed workers to complete the rough-out phase. In the letter, Tunney provided only five days to cure the alleged errors, despite the plumbing contract providing Mr. Pirtle 30 days to cure.

Mr. Pirtle’s attorney responded by letter, addressing each of the three alleged breaches separately. As to the installation of the shower controls and showerheads, the letter explained that they were installed to be ADA-compliant and passed inspection. Mr. Pirtle offered to relocate the items for an additional $925. Next, Mr. Pirtle explained that the elevator pit pump fell outside the scope of the plumbing contract, but he asked for any documentation that would show otherwise. Finally, as to the allegedly unlicensed workers, the letter stated that Mr. Pirtle was unaware of “any licensing violations” related to the project. Mr. Pirtle asked that if Tunney had any information to the contrary to “please provide it.” After considering Mr. Pirtle’s responses, Tunney agreed to pay Mr. Pirtle an additional $925 to change the location of the shower controls and showerheads, resolving that dispute. The parties also appeared to have resolved the elevator pit pump issue after discussing it. Tunney provided no response or additional information related to alleged licensing violations.

Months later, in September 2021, Tunney asked Mr. Pirtle to begin working on the trim-out phase. When Mr. Pirtle arrived at the site, it was not ready for him to do the trim- out work, with other work being performed that impeded his access.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dick Broadcasting Company, Inc. of Tennessee v. Oak Ridge FM, Inc.
395 S.W.3d 653 (Tennessee Supreme Court, 2013)
R. Douglas Hughes v. New Life Development Corporation
387 S.W.3d 453 (Tennessee Supreme Court, 2012)
ALLSTATE INSURANCE COMPANY v. Diana Lynn TARRANT Et Al.
363 S.W.3d 508 (Tennessee Supreme Court, 2012)
Baugh v. Novak
340 S.W.3d 372 (Tennessee Supreme Court, 2011)
Main Street Market, LLC v. Emily v. Weinberg
432 S.W.3d 329 (Court of Appeals of Tennessee, 2013)
Sneed v. Board of Professional Responsibility
301 S.W.3d 603 (Tennessee Supreme Court, 2010)
House v. Estate of Edmondson
245 S.W.3d 372 (Tennessee Supreme Court, 2008)
Barnes v. Barnes
193 S.W.3d 495 (Tennessee Supreme Court, 2006)
State v. Binette
33 S.W.3d 215 (Tennessee Supreme Court, 2000)
Mitch Grissim & Associates v. Blue Cross & Blue Shield of Tennessee
114 S.W.3d 531 (Court of Appeals of Tennessee, 2002)
Billie Mclemore v. J.W. Powell & Raymond Nelson
968 S.W.2d 799 (Court of Appeals of Tennessee, 1997)
In Re the Adoption of E.N.R.
42 S.W.3d 26 (Tennessee Supreme Court, 2001)
Burress v. Sanders
31 S.W.3d 259 (Court of Appeals of Tennessee, 2000)
Ashley v. Volz
404 S.W.2d 239 (Tennessee Supreme Court, 1966)
City of Columbia v. C.F.W. Construction Co.
557 S.W.2d 734 (Tennessee Supreme Court, 1977)
Pullman Standard, Inc. v. Abex Corp.
693 S.W.2d 336 (Tennessee Supreme Court, 1985)
Memphis Light, Gas & Water Division v. Starkey
244 S.W.3d 344 (Court of Appeals of Tennessee, 2007)
In Re Estate of Marks
187 S.W.3d 21 (Court of Appeals of Tennessee, 2005)
Penske Truck Leasing Co. v. Huddleston
795 S.W.2d 669 (Tennessee Supreme Court, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
John Pirtle d/b/a Third Coast Builders v. The Tunney Group, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-pirtle-dba-third-coast-builders-v-the-tunney-group-llc-tennctapp-2025.