TD Properties, LLC v. VP Buildings, Inc.

602 F. Supp. 2d 351, 68 U.C.C. Rep. Serv. 2d (West) 245, 2009 U.S. Dist. LEXIS 20330, 2009 WL 649691
CourtDistrict Court, D. Connecticut
DecidedMarch 13, 2009
Docket3:07CV00629 (DJS)
StatusPublished
Cited by6 cases

This text of 602 F. Supp. 2d 351 (TD Properties, LLC v. VP Buildings, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
TD Properties, LLC v. VP Buildings, Inc., 602 F. Supp. 2d 351, 68 U.C.C. Rep. Serv. 2d (West) 245, 2009 U.S. Dist. LEXIS 20330, 2009 WL 649691 (D. Conn. 2009).

Opinion

MEMORANDUM OF DECISION AND ORDER

DOMINIC J. SQUATRITO, District Judge.

The plaintiff, Mario D’Addario Buick, Inc. and/or Mario D’Addario Buick, Inc. d/b/a Mario D’Addario Buick-Nissan-GMC (“Plaintiff’) 1 brings this action against the defendant, VP Consolidated Holdings, Inc., n/k/a Vareo Pruden Buildings, Inc. (“the Defendant”), 2 alleging a breach of contract, breach of express warranty, breach of implied warranty of merchantability, breach of implied warranty for a particular purpose, and a violation of the Connecticut Unfair Trade Practices Act, Conn. Gen.Stat. §§ 42-110a et seq. (“CUPTA”). Pursuant to Rule 56 of the Federal Rules of Civil Procedure, the Defendant has moved for summary judgment on all the claims in the amended complaint. For the reasons that hereafter follow, the Defendant’s motions for summary judgment (dkt. # s 44 & 65) 3 are GRANTED.

I. FACTS

This is a dispute between the owner of a car dealership and a company that manufactures pre-engineered steel structures. At some point prior to February 2003, the Plaintiff entered into an agreement with Nissan whereby Nissan designated the Plaintiff as a “premier” Nissan franchisee/dealership. As a result of this new status, the Plaintiff was required to construct a new showroom to display Nissan vehicles.

The Plaintiff then contacted the Defendant to purchase a pre-engineered steel structure. Because the Defendant only *355 manufactures steel structure kits, it referred the Plaintiff to International Building Systems, LLC (“IBS”), a pre-approved builder that was authorized to erect the structures manufactured by the Defendant. Both parties agree that the Plaintiff signed a standard construction document with IBS on May 07, 2003. The contract called for IBS to construct, under the direction of the Plaintiffs architects, Anti-nozzi Associates, a showroom with 15,565 square feet in Shelton, Connecticut. Under the terms of the agreement between the Defendant and IBS, the Defendant agreed to manufacture a pre-engineered steel structure according to the specifications provided by the Plaintiff. The Defendant subsequently produced “shop drawings” for approval by the Plaintiff before manufacturing the pre-engineered steel structure. The Plaintiff approved the shop drawings.

The Defendant then manufactured the pre-engineered steel building in accordance with the specifications approved by the Plaintiff. The approved drawings for the pre-engineered steel structure called for supports for two rooftop air conditioning units weighing no more than 600 pounds and 1950 pounds, respectively. IBS installed the two air conditioning units identified in the approved shop drawings. This installation, however, was done in such a manner that the condensate from the air conditioning units drained directly upon the roof.

Moreover, in August 2003, a mezzanine was added to the pre-engineered building by DeLauries Construction. This was done without consulting the Defendant. As a result of this addition, a third air conditioning unit was added to accommodate the mezzanine. This air conditioning unit was placed above the mezzanine area’s roof without the Defendant’s approval of a change in the loads the structure could support, and it was installed without the appropriate roof curbing needed to mount and support the air conditioning unit. In short, this air conditioning unit was installed in an incorrect manner and caused the roof to leak.

In October 2003, the Defendant sent a field inspector to determine the cause of the leaking roof. In the job site report prepared by the field inspector on October 22, 2003, the field inspector determined that root cause of the roof leaks was that the roof had not been installed in accordance with manufacturer’s specifications as outlined in the shop drawings.

IBS replaced portions of the roof between November 2003 and January 2004 because the installation did not meet the Defendant’s installation standards for the type of roof panels used on the Plaintiffs showroom. IBS paid for new roof panels that were ordered from the Defendant. IBS did not, however, use the four-inch insulation approved by the Defendant in the shop drawings, but rather used six-inch insulation provided by E J Davis Company, a local supplier. In addition, while installing the new roof panels, IBS left metal fillings on the roof panels that ultimately contributed to the rusting of the replacement roof.

The plans provided by the Defendant also call for a multi-gutter that was meant to pitch from east to west. The installers from IBS drilled holes for downspouts in the wrong locations and did not install the downspouts with the correct pitch. The installers attempted to correct the problems by patching the holes with tar and putting a vinyl membrane inside the gutter to increase the pitch.

In addition to installing the roof panels and the multi-gutters incorrectly, IBS also installed the roof curbs too low. As a result of this improper installation, when it rains, water pools around the air condition *356 ing units and leaks into the interior of the building.

The Plaintiff obtained a quote from American Steel Erectors, a builder that has experience with erecting pre-engi-neered steel structures, to assess the structure. According to American Steel Erectors, the HVAC units were installed incorrectly; the insulation for the structure was damaged; the roof panels were rusting; and, when HVAC openings were cut, the metal chips rusted on the roof panels, which in turn caused the roof panels to rust.

As construction progressed, all progress invoices submitted by IBS for work performed were paid by the Plaintiff. The final payment for the construction was paid pursuant to an arbitration proceeding because IBS had submitted a claim for final payment and the Plaintiff withheld the final payment, claiming deficient materials and workmanship. The arbitrator found no material or installation deficiencies and awarded IBS the full and final payment plus statutory interest.

The parties agree that the Defendant delivered all the materials and components required for the project. Paragraph nine of the purchase order specifically noted that no agency relation at law or in fact exists between the purchaser and the Defendant. Under the terms and conditions of the purchase order, the Defendant also issued a standard warranty to the end user for the roof panels and the roof panels’ finish, provided that the end user adhered to the terms contained in the written warranty.

The Plaintiff claims that, based upon conversations with William Lewis (“Lewis”) of IBS, it had a twenty-year warranty for all materials provided by the Defendant and that IBS was going to warrant the labor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Zajradhara v. NMC
Sup. Ct. of the Comm. of the N. Mariana Islands, 2025
McMahon v. ADVANCE STORES CO., INC.
705 S.E.2d 131 (West Virginia Supreme Court, 2010)
TD Properties, LLC v. VP Buildings, Inc.
635 F. Supp. 2d 123 (D. Connecticut, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
602 F. Supp. 2d 351, 68 U.C.C. Rep. Serv. 2d (West) 245, 2009 U.S. Dist. LEXIS 20330, 2009 WL 649691, Counsel Stack Legal Research, https://law.counselstack.com/opinion/td-properties-llc-v-vp-buildings-inc-ctd-2009.