TC/American Monorail, Inc. v. Custom Conveyor Corp.

840 N.W.2d 414, 2013 WL 6654280, 2013 Minn. LEXIS 748
CourtSupreme Court of Minnesota
DecidedDecember 18, 2013
DocketNo. A11-2119
StatusPublished
Cited by8 cases

This text of 840 N.W.2d 414 (TC/American Monorail, Inc. v. Custom Conveyor Corp.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
TC/American Monorail, Inc. v. Custom Conveyor Corp., 840 N.W.2d 414, 2013 WL 6654280, 2013 Minn. LEXIS 748 (Mich. 2013).

Opinions

OPINION

DIETZEN, Justice:

The issue in this case is whether a party may take a deposition to preserve trial testimony of an unavailable, out-of-state witness, even though the deposition would occur after a discovery deadline in a scheduling order. Respondent TC/American Monorail, Inc., brought this civil action to recover payment for industrial equipment that it fabricated for appellant Custom [416]*416Conveyor Corporation. Custom Conveyor counterclaimed for breach of contract. Following a jury trial, the district court entered judgment in favor of TC/American for $208,428. Custom Conveyor moved for judgment as a matter of law or a new trial on various grounds, arguing, among other things, that the district court erred by granting TC/American’s motion for a protective order to preclude the depositions of two out-of-state witnesses from going forward shortly before trial. The district court denied the motion, and the court of appeals affirmed. Because we conclude that the district court abused its discretion by denying the motion for a new trial and by granting the underlying motion for a protective order, and that Custom Convey- or was prejudiced by these rulings, we reverse and remand for a new trial.

In 2009 Custom Conveyor entered into a contract with the City of North Las Vegas, Nevada, to supply equipment needed for a wastewater treatment facility construction project. Custom Conveyor manufactured certain components of the equipment itself and solicited bids for fabrication of the other components, including four steel hoppers and support stands.

TC/American submitted a bid of $305,000 for fabrication of the hoppers and support stands. The hoppers would be connected to the stands with field weld joints. In preparing the bid, the TC/American project manager communicated to Custom Conveyor that TC/American was a “Dl.l shop,” which means that its welders were certified to the Dl.l standard of the American Welding Society. The Dl.l standard provides that welds must pass visual inspection, but not electronic testing. Custom Conveyor ultimately selected TC/American’s bid.

When the first shipment of TC/American’s product arrived at the project site, the City expressed dissatisfaction with the quality of the welds. Custom Conveyor notified TC/American, and TC/American agreed to have the product returned to its plant for repairs. Upon return, TC/American’s project manager and quality control manager inspected the product and determined that some of the disputed welds did not conform to Dl.l standards.

TC/American repaired and reshipped the product to the project site and made several additional shipments through December 2009. The City again objected to the quality of the welds. Custom Convey- or asked TC/American to perform additional repairs on the product, but TC/American refused. TC/American asserted that its welds met the Dl.l standard of visual inspection and that is was not obligated to satisfy the City’s higher electronic testing. In the end, Custom Conveyor elected to fix and use the hoppers fabricated by TC/American, but did not use the support stands. TC/American sent invoices for its product, and Custom Conveyor refused to pay the invoices in full.

In April 2010, TC/American sued Custom Conveyor for breach of contract and failure to pay for goods sold and delivered on the North Las Vegas project and two other projects. Custom Conveyor counterclaimed for breach of contract. In September 2010, the district court issued a scheduling order establishing a discovery deadline of January 21, 2011, a deadline to file pretrial motions by March 18, 2011, and a trial date of June 20, 2011.

On April 29, 2011, Custom Conveyor filed a request with the district court for authorization to obtain subpoenas to take trial depositions of two witnesses located in Las Vegas, Jay Brown and Manuel Israel, during the week of June 6, 2011. Custom Conveyor alleged that it intended to call both witnesses to testify at trial, but that when it contacted them in March [417]*4172011, it learned they would not voluntarily travel to Minnesota for trial. TC/American opposed the request and filed a motion for a protective order to preclude the depositions, arguing that the depositions were barred because they were outside the discovery deadline in the scheduling order.

The district court denied Custom Conveyor’s deposition request and granted TC/American’s motion for a protective order. The court reasoned that Custom Conveyor failed to present sufficient reasons for the delay in its request for assistance in compelling the depositions and failed to demonstrate the necessity of the testimony of the witnesses to its case. Additionally, the court concluded that prejudice to TC/American would result if Custom Conveyor was allowed to conduct the depositions two weeks before trial.

Following trial, the jury found for TC/American on its claim for payment of its invoices but also found that TC/American breached a portion of the contract. The net award was in favor of TC/American for $208,428. Custom Conveyor moved for judgment as a matter of law or a new trial, arguing, among other things, that the district court erred in refusing to permit the taking of the depositions of the out-of-state witnesses to preserve their testimony for trial. The district court denied the motion and entered judgment.

The court of appeals affirmed. TC/Am. Monorail, Inc. v. Custom Conveyor Corp., 822 N.W.2d 812, 817-19 (Minn.App.2012). The court concluded that the district court did not abuse its discretion by enforcing the discovery deadline in denying the deposition requests. Id. at 817-18. The court reasoned that Custom Conveyor failed to show good cause for extending the deadline to allow the depositions to be taken. Id. at 818-19.

I.

Custom Conveyor argues that the district court erred in three interrelated ways: by denying its request to take depositions to preserve trial testimony of the unavailable out-of-state witnesses; by granting TC/American’s motion for a protective order to preclude depositions; and by denying its motion for a new trial. According to Custom Conveyor, a deposition to preserve trial testimony, unlike a discovery deposition, is not governed by the discovery deadline in the scheduling order. TC/American responds that the deposition request was barred by the discovery deadline, and that Custom Conveyor failed to show good cause for extending the deadline.

We review the district court’s rulings in this case for an abuse of discretion.1 Frazier v. Burlington N. Santa Fe Corp., 811 N.W.2d 618, 629 (Minn.2012) (reviewing a district court’s ruling on a motion for a new trial for an abuse of discretion), modified, (Minn. Apr. 19, 2012); Erickson v. MacArthur, 414 N.W.2d 406, 407 (Minn.1987) (reviewing a district court’s ruling on a discovery matter for an abuse of discretion). The district court abuses its discretion if it bases its ruling on an improper application of the law to the facts. In re Comm’r of Pub. Safety, 735 N.W.2d 706, 711 (Minn.2007). The interpretation of the rules of civil procedure, however, is a question of law that

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
840 N.W.2d 414, 2013 WL 6654280, 2013 Minn. LEXIS 748, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tcamerican-monorail-inc-v-custom-conveyor-corp-minn-2013.