T.A. Schifsky & Sons, Inc. v. Bahr Construction, LLC

773 N.W.2d 783, 2009 Minn. LEXIS 704, 2009 WL 3379128
CourtSupreme Court of Minnesota
DecidedOctober 22, 2009
DocketA08-1295
StatusPublished
Cited by36 cases

This text of 773 N.W.2d 783 (T.A. Schifsky & Sons, Inc. v. Bahr Construction, LLC) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
T.A. Schifsky & Sons, Inc. v. Bahr Construction, LLC, 773 N.W.2d 783, 2009 Minn. LEXIS 704, 2009 WL 3379128 (Mich. 2009).

Opinion

OPINION

MEYER, Justice.

Premier Bank appeals from a district court order determining the validity of four mechanics’ liens held by Consolidated Lumber Company, d/b/a Arrow Building Center (Consolidated Lumber). The district court determined the amount of the liens plus interest, and ruled that Consolidated Lumber was entitled to attorney fees, costs, and disbursements to be submitted to the court for approval. The court stated that there was no just cause for delay and directed entry of judgment. Premier Bank did not appeal from the judgment entered on December 13, 2007, but waited to appeal until after the district court awarded attorney fees in a separate order in May 2008.

The court of appeals dismissed Premier Bank’s appeal as untimely because it was filed more than 60 days after the December 13, 2007, entry of judgment. We affirm as untimely the court of appeals’ dismissal of Premier Bank’s appeal on the validity of the mechanics’ liens and the fair and reasonable value of the liens. However, because Premier Bank also appealed from the district court order awarding Consolidated Lumber its attorney fees, and because Premier Bank’s appeal was filed after judgment for attorney fees was entered, we reverse the court of appeals’ dismissal of Premier Bank’s appeal from that order and remand to the court of appeals for further proceedings.

Consolidated Lumber sought to foreclose four mechanics’ liens against Bahr Construction, LLC. Premier Bank challenged the mechanics’ liens, arguing the mechanics’ lien statements that Consolidated Lumber recorded with the Ramsey County Recorder’s Office were invalid because they failed to describe and identify the liened premises with reasonable certainty, as required by Minn.Stat. § 514.08, subd. 2(5) (2008). The mechanics’ lien statements identified the liened property as being located in section 33, Township 30, Range 22, when, in fact, the property was located in adjacent Section 34, Township 30, Range 22.

After a bench trial, the district court found that each of Consolidated Lumber’s four mechanics’ lien statements contained an incorrect section number and an incorrect and erroneous property identification number, but correctly identified the properties’ street addresses. The court’s *786 November 26, 2007, findings of fact and conclusions of law determined that Consolidated Lumber’s four mechanics’ liens were valid because they identified the property with reasonable certainty as required under Minn.Stat. § 514.08, subd. 2(5). The court concluded that the fair and reasonable value of the mechanics’ liens was $172,958.11, and concluded that Consolidated Lumber was entitled to interest in the sum of $12,197.10. The order further stated that “Consolidated Lumber is entitled to reasonable attorneys’ fees, costs, and disbursements herein, which shall be submitted to the Court for approval by separate Notice of Motion and Motion.” Although neither party had requested the court enter judgment immediately, the court concluded the order with these words: “There being no just cause for delay, let judgment be entered accordingly.” Judgment was entered pursuant to the order on December 13, 2007.

Premier Bank did not file an immediate appeal, but did timely file a post-trial motion to amend the district court’s findings of fact, conclusions of law, and order for judgment, and a motion for a new trial. See Minn. R. Civ.App. P. 104.01, subd. 2. The district court denied the motions on February 1, 2008. Consolidated Lumber served Premier Bank with a notice of filing of that order on February 6, 2008. See Minn. R. Civ.App. P. 104.01, subd. 1. On May 22, 2008, the district court awarded Consolidated Lumber attorney fees and costs of $11,543.74. Consolidated Lumber served Premier Bank with a notice of filing of that order on May 28, 2008; judgment on that order was entered on July 24, 2008.

On July 30, 2008, Premier Bank filed a notice of appeal that referenced both the December 13, 2007, judgment and the May 22, 2008, order, which Premier described as “a final adjudication of all remaining issues set forth in the partial judgment ... entered on December 13, 2007.” 1 On August 27, 2008, after briefing by the parties, the court of appeals dismissed Premier Bank’s appeal as untimely, concluding that the December 13, 2007, judgment had been immediately appeal-able because the order “contains the express determinations under Minn. R. Civ. App. P. 104.01 and Minn. R. Civ. P. 54.02 to allow an immediate appeal.” The court concluded that Premier Bank should have appealed within 60 days of Consolidated Lumber’s notice of filing of the February order denying Premier Bank’s post-trial motions — in other words, by April 9, 2008.

I.

Premier Bank argues that the November 26, 2007, order was not properly certified as a final partial judgment under Minn. R. Civ. P. 54.02 because the judgment did not fully adjudicate an entire claim. Whether an order can properly be certified under Minn. R. Civ. P. 54.02 raises a legal question that requires construction and application of a procedural rule, which we review de novo. Engvall v. Soo Line R.R. Co., 605 N.W.2d 738, 741 (Minn.2000). If an order can properly be certified, we review the district court’s decision *787 whether or not to do so for an abuse of discretion. Novus Equities Corp. v. EMTY P’ship, 381 N.W.2d 426, 428 (Minn.1986).

We first address whether the November 26, 2007, order could properly be certified as a final partial judgment under Minn. R. Civ. P. 54.02. “In construing procedural rules, we first look to the plain language of the rule and its purpose.” Rubey v. Vannett, 714 N.W.2d 417, 421 (Minn.2006). Minnesota Rule of Civil Procedure 54.02 states:

When multiple claims for relief or multiple parties are involved in an action, the court may direct the entry of a final judgment as to one or more but fewer than all of the claims or parties only upon an express determination that there is no just reason for delay and upon an express direction for the entry of judgment.

Rule 54.02 is intended to reduce piecemeal appeals by limiting appeals from judgments that resolve only part of the litigation. Engvall, 605 N.W.2d at 744. At the same time, the rule is meant to liberalize the appellate process for parties who might be prejudiced by waiting to appeal a decision where other claims or liabilities are yet to be decided. See David F. Herr & Roger S. Haydock, 2 Minnesota Practice Series: Civil Rules Annotated § 54.11 (2004).

The district court’s use of Rule 54.02’s language — “There being no just cause for delay, let judgment be entered accordingly” — does not necessarily make the resulting judgment a final partial judgment pursuant to Minn. R. Civ. P. 54.02. 2 See Brookfield Trade Ctr., Inc. v. County of Ramsey, 609 N.W.2d 868, 873 n. 6 (Minn.2000); accord Liberty Mut. Ins. Co.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carsten James Quinlan v. Fraser, Alissa Puls
Court of Appeals of Minnesota, 2025
Craig A. Reichel v. Wendland Utz, LTD
Supreme Court of Minnesota, 2024
Tokvan Ly v. Jodi Harpstead, Minnesota Commissioner of Human Services
7 N.W.3d 560 (Supreme Court of Minnesota, 2024)
Raymond Kvalvog v. Park Christian School, Inc.
66 F.4th 1147 (Eighth Circuit, 2023)
Abuzeni v. Mutschler
926 N.W.2d 59 (Court of Appeals of Minnesota, 2019)
Woischke v. Stursberg & Fine, Inc.
920 N.W.2d 419 (Supreme Court of Minnesota, 2018)
Cox v. Mid-Minnesota Mut. Ins. Co.
909 N.W.2d 540 (Supreme Court of Minnesota, 2018)
All Finish Concrete, Inc. v. Erickson
899 N.W.2d 557 (Court of Appeals of Minnesota, 2017)
City of Rochester v. Kottschade
896 N.W.2d 541 (Supreme Court of Minnesota, 2017)
Madison Equities, Inc. v. Robert L. Crockarell
889 N.W.2d 568 (Supreme Court of Minnesota, 2017)
Marriage of Baertsch v. Baertsch
886 N.W.2d 235 (Court of Appeals of Minnesota, 2016)
McCullough and Sons, Inc. v. City of Vadnais Heights, A14-1992
883 N.W.2d 580 (Supreme Court of Minnesota, 2016)
Contractors Edge, Inc. v. City of Mankato
863 N.W.2d 765 (Supreme Court of Minnesota, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
773 N.W.2d 783, 2009 Minn. LEXIS 704, 2009 WL 3379128, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ta-schifsky-sons-inc-v-bahr-construction-llc-minn-2009.