City of Elk River v. Bolton & Menk, Inc., Vessco, Inc., Schwing Bioset ...

Supreme Court of Minnesota·Decided January 31, 2024·No. A221771·Published

Opinion

STATE OF MINNESOTA

IN SUPREME COURT

A22-1771

Court of Appeals Hudson, C.J.

Took no part, Procaccini, J.

City of Elk River,

Respondent,

vs.

Bolton & Menk, Inc., Filed: January 31, 2024 Office of Appellate Courts Appellant,

Vessco, Inc. et al., Respondents,

Schwing Bioset Incorporated, Respondent.

Stephen F. Buterin, Droel, PLLC, Minneapolis, Minnesota; and

Jeffrey W. Coleman, Lars C. Erickson, Benjamin J. Kirk, Coleman & Erickson, LLC, Eden Prairie, Minnesota, for appellant.

Nathan R. Sellers, Alexander B. Athmann, Fabyanske Westra Hart & Thomson, P.A., Minneapolis, Minnesota, for respondents Vessco, Inc. and Rice Lake Contracting Corp.

Michael H. Streater, Adam G. Chandler, Taft Stettinius & Hollister, LLP, Minneapolis, Minnesota, for respondent Schwing Bioset Incorporated.

SYLLABUS

The district court did not abuse its discretion in certifying the order as a final partial judgment under Minn. R. Civ. P. 54.02 because the district court explained why certification was necessary, the third-party claims presented distinct issues from the principal claims, and the case was in its early stages at the time of certification.

Reversed and remanded.

OPINION

HUDSON, Chief Justice.

The question presented here is whether the district court abused its discretion in certifying an order as a final partial judgment under Minnesota Rule of Civil Procedure 54.02. The case arises from a dispute over a large construction contract relating to a wastewater treatment plant improvement project entered into between Bolton & Menk, Inc. (“Bolton”) and the City of Elk River (“the City”).

The City sued Bolton, alleging breach of contract and professional negligence.

Bolton, in turn, filed a third-party complaint alleging contribution and indemnification, among other claims, against three other parties to the contract. The district court dismissed Bolton’s third-party complaint pursuant to Minnesota Rule of Civil Procedure 12.02(e). Bolton moved the district court to certify the dismissal order as a final partial judgment under Rule 54.02 to allow an immediate appeal. In a 6-page order explaining its reasoning, the district court granted that motion. Bolton appealed, seeking review of the dismissal order. The court of appeals dismissed Bolton’s appeal for lack of jurisdiction, holding that the district court abused its discretion in certifying the order as a final judgment under

Rule 54.02. Because we conclude that the district court did not abuse its discretion in certifying the dismissal order as final under Rule 54.02, we reverse.

FACTS

The City of Elk River sued Bolton in a dispute over a construction contract, alleging breach of contract and professional negligence. Bolton subsequently filed a third-party complaint alleging contribution, indemnity, and negligence against Schwing Bioset Incorporated (“Schwing”), an equipment manufacturer; Vessco, Inc. (“Vessco”), an equipment supplier agent; and Rice Lake Contracting Corp. (“Rice Lake”), a general contractor (collectively, “Third-Party Defendants”). Bolton also brought a breach of contract claim against Vessco and Rice Lake, as well as negligent misrepresentation and promissory estoppel claims against Schwing.

Third-Party Defendants moved to dismiss Bolton’s third-party complaint for failure to state a claim pursuant to Rule 12.02(e). The district court dismissed Bolton’s third-party complaint with prejudice. Because the order did not adjudicate the principal dispute between the City and Bolton, the order was not immediately appealable. But Bolton moved the district court to certify the dismissal order as a final partial judgment to allow an immediate appeal pursuant to Rule 54.02. The City filed an executed stipulation with Bolton supporting Rule 54.02 certification. Third-Party Defendants objected to the stipulation.

The district court granted Bolton’s motion and directed that the dismissal order be revised to add language consistent with Rule 54.02, that “there being no just reason for delay, let judgment be entered accordingly.” The court entered the amended order as a

final judgment, concluding that “judicial economy is best served by permitting an immediate appeal.” The court explained its reasoning, noting that (1) the risk of time and expense caused by excluding Third-Party Defendants, if they are necessary parties, outweighs the burden of delay from an immediate appeal; (2) delaying the appeal until resolution of the claims between the City and Bolton “will not result in a simplified appeal” because the resolution of the third-party claims “could impact the resolution of the claims between the remaining parties”; and (3) the City and Bolton agree it is in the best interest of the parties and stipulated to the entry of a final partial judgment.

Bolton appealed the final partial judgment to the court of appeals. The court of appeals dismissed the appeal, concluding that it lacked appellate jurisdiction because the district court abused its discretion by entering final partial judgment under Rule 54.02. City of Elk River v. Bolton & Menk, Inc., No. A22-1771, 2023 WL 2662339, at *3 (Minn. App. Jan. 17, 2023). The court of appeals reasoned that allowing an immediate appeal to proceed would conflict with the general policy against piecemeal appeals because the third-party claims and principal claims all relate to the same construction project and the third-party claims “are contingent on Bolton incurring liability.” Id. at *2. The court acknowledged that an immediate appeal might facilitate settlement negotiations between Bolton and the City “and potentially avoid the time and expense of additional proceedings, such as a second trial.” Id. at *3. The court concluded, however, that these considerations do not outweigh the general policy against piecemeal appeals. Id.

We granted Bolton’s petition for further review. 1 ANALYSIS

A.

The “thrust” of the rules of civil appellate procedure “is that appeals should not be brought or considered piecemeal.” Emme v. C.O.M.B., Inc., 418 N.W.2d 176, 179 (Minn. 1988). This general policy conserves judicial resources and expedites trial proceedings. Id. Nevertheless, the rules of civil appellate procedure permit interlocutory appeals in certain circumstances. One such circumstance is the entry of final partial judgment pursuant to Rule 54.02. See Minn. R. Civ. App. P. 103.03(a). A party may appeal from a partial judgment entered pursuant to Rule 54.02 if an action involves “multiple claims for relief or multiple parties,” the district court makes “an express determination that there is no just reason for delay,” and the district court expressly directs the entry of a final judgment.

“Rule 54.02 is intended to reduce piecemeal appeals by limiting appeals from judgments that resolve only part of the litigation,” and “to liberalize the appellate process for parties who might be prejudiced by waiting to appeal a decision where other claims or liabilities are yet to be decided.” T.A. Schifsky & Sons, Inc., 773 N.W.2d 783,787 (Minn. 2009).

1 The City filed a letter with the court of appeals stating its agreement with Bolton that the case was appropriately certified for immediate appeal under Rule 54.02, but the City did not participate in the appeal before our court.

Free access — add to your briefcase to read the full text and ask questions with AI

City of Elk River v. Bolton & Menk, Inc., Vessco, Inc., Schwing Bioset ..., (Mich. 2024).

City of Elk River v. Bolton & Menk, Inc., Vessco, Inc., Schwing Bioset ... (City of Elk River v. Bolton & Menk, Inc., Vessco, Inc., Schwing Bioset ...) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Curtiss-Wright Corp. v. General Electric Co.
446 U.S. 1 (Supreme Court, 1980)
Emme v. C.O.M.B., Inc.
418 N.W.2d 176 (Supreme Court of Minnesota, 1988)
T.A. Schifsky & Sons, Inc. v. Bahr Construction, LLC
773 N.W.2d 783 (Supreme Court of Minnesota, 2009)
Sommers v. Thomas
88 N.W.2d 191 (Supreme Court of Minnesota, 1958)
Contractors Edge, Inc. v. City of Mankato
863 N.W.2d 765 (Supreme Court of Minnesota, 2015)
Melrose Gates, LLC v. Chor Moua
875 N.W.2d 814 (Supreme Court of Minnesota, 2016)