Taylor, Cotton & Ridley, Inc. v. Okatie Hotel Group, LLC

641 S.E.2d 459, 372 S.C. 89, 2007 S.C. App. LEXIS 1
CourtCourt of Appeals of South Carolina
DecidedJanuary 8, 2007
Docket4194
StatusPublished
Cited by7 cases

This text of 641 S.E.2d 459 (Taylor, Cotton & Ridley, Inc. v. Okatie Hotel Group, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Taylor, Cotton & Ridley, Inc. v. Okatie Hotel Group, LLC, 641 S.E.2d 459, 372 S.C. 89, 2007 S.C. App. LEXIS 1 (S.C. Ct. App. 2007).

Opinion

SHORT, J.:

Okatie Hotel Group, LLC (Owner) appeals the trial court’s failure to consider settlement payments to seven other subcontractors (Other Subcontractors) and damages to the building when determining Owner’s liability to Taylor, Cotton and Ridley, Inc. (Subcontractor). Owner also appeals the trial court’s disregard of a waiver made by Subcontractor, use of an interest rate greater than the statutory maximum, and award of attorneys’ fees. We affirm in part, reverse in part, and remand.

FACTS

The Devcon Group, Inc. (General Contractor) served as the general contractor for Owner’s development of the Marriott Fairfield Inn. General Contractor hired Subcontractor to install door frames and locks for the development at an original contract price of $91,570.00. This original contract price increased to $115,085.75, due to additional line items, a revised door frame jam, and installation of “Ving card” locks. Subcontractor finished all major work and billed General Contractor by November 23, 1999, but was called back to the job site on several occasions to perform further installations and re *94 pairs. By December 6, 1999, Subcontractor had submitted a notice of non-payment and received $20,000 toward the total contract price of $115,085.75. The last service performed by Subcontractor was on March 8, 2000, when Subcontractor returned to install and repair exterior door locks. On April 24, 2000, Subcontractor filed a mechanic’s lien for the $95,085.75 which remained due under the contract.

The amended total contract between General Contractor and Owner was $2,421,656.00, and prior to Subcontractor’s lien filing, Owner paid General Contractor $2,166,613.00. Other Subcontractors claimed liens totaling $146,330.00, but, following mediation in the spring of 2001, they settled for $92,385.00. All Other Subcontractors participated in this mediation, but Subcontractor did not.

Subcontractor filed suit against General Contractor and Owner to enforce Subcontractor’s lien against the developed property. At trial, the court adjusted the contract price by first decreasing it to $2,417,564.00 to reflect back charges, and then by increasing it to $2,461,510.00 to include change orders. The trial court found no adjustments were necessary for liquidated damages and held General Contractor and Owner were jointly and severally liable to Subcontractor for the lien of $95,085.15 with a 1.5% interest rate beginning in December of 1999. This accrued interest brought the total judgment amount to $184,940.62. In addition to this amount, the court, through a subsequent order issued on September 22, 2005, awarded Subcontractor $31,272.19 in attorney’s fees and costs. This appeal followed.

STANDARD OF REVIEW

“A proceeding for the enforcement of a statutory lien, such as a mechanic’s lien, is legal in nature.” Butler Contracting, Inc. v. Court Street, LLC, 369 S.C. 121, 127, 631 S.E.2d 252, 255 (2006) (citing Willard v. Finch, 123 S.C. 56, 116 S.E. 96 (1923)). In an action at law tried without a jury, the trial court’s findings of fact will be upheld on appeal when the findings are reasonably supported by the evidence. Butler Contracting, 369 S.C. at 126, 631 S.E.2d at 255. The trial court’s findings of fact will not be disturbed on appeal unless wholly unsupported by the evidence or clearly influenced or *95 controlled by an error of law. Id. at 126-28, 631 S.E.2d at 255-56.

LAW/ANALYSIS

I. Credit for Payments to Other Subcontractors

Owner argues that sections 29-5-20, 29-5-40, and 29-5-60 of the South Carolina Code (Supp.2005) require the trial court to credit Owner for the settlement reached with Other Subcontractors before determining the amount owed Subcontractor. Owner paid Other Subcontractors 66.6% of their claimed lien amounts and sought to limit any amount paid to Subcontractor to this same percentage. At the time Owner settled with Other Subcontractors through mediation, Owner was aware of Subcontractor’s outstanding lien. The trial court held that Subcontractor was not bound by the prorated limit in the settlement between Owner and Other Subcontractors. We agree.

Section 29-5-20(a) states:

Every laborer, mechanic, subcontractor, or person furnishing material for the improvement of real estate when the improvement has been authorized by the owner has a lien thereon, subject to existing liens of which he has actual or constructive notice, to the value of the labor or material so furnished, including the costs of the action and a reasonable attorney’s fee which must be determined by the court in which the action is brought but only if the party seeking to enforce the lien prevails. If the party defending against the lien prevails, the defending party must be awarded costs of the action and a reasonable attorney’s fee as determined by the court. The fee and the court costs may not exceed the amount of the lien. The lien may be enforced as herein provided.

Additionally section 29-5-40 states:

Whenever work is done or material is furnished for the improvement of real estate upon the employment of a contractor or some other person than the owner and such laborer, mechanic, contractor or materialman shall in writing notify the owner of the furnishing of such labor or material and the amount or value thereof, the lien given by *96 § 29-5-20 shall attach upon the real estate improved as against the true owner for the amount of the work done or material furnished. But in no event shall the aggregate amount of liens set up hereby exceed the amount due by the owner on the contract price of the improvement made.

(iemphasis added).

The main purposes of sections 29-5-20 and 29-5-40 are (1) the protection through a lien of a party, who furnished labor or material but was not a party to a contract with the owner and (2) the protection of the owner by preventing his liability on the liens from exceeding the amount owner owes on the contract price. Lowndes Hill Realty Co. v. Greenville Concrete Co., 229 S.C. 619, 629, 93 S.E.2d 855, 860 (1956). 1 Subcontractor brought this action in order to enforce his lien after providing labor to Owner.

The trial court adjusted the contract price to $2,461,510.00 based on change orders and back charges. Owner paid General Contractor $2,166,613.00, and Owner settled with Other Subcontractors for $92,385.00, which leaves a difference of $202,512.00 between the contract price and the amount paid by Owner. Subcontractor’s lien is for $95,085.75. Therefore, section 29-5-40 is not violated because the difference between the contract price and amount Owner already paid is greater than Subcontractor’s lien amount.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Associated Receivables Funding, Inc. v. Dunlap, Inc.
Court of Appeals of South Carolina, 2024
Moats Construction v. Sanders
Court of Appeals of South Carolina, 2016
Warren v.Yarborough
Court of Appeals of South Carolina, 2012
Ferguson Fire & Fabrication, Inc. v. Preferred Fire Protection, LLC
725 S.E.2d 495 (Court of Appeals of South Carolina, 2012)
Bodell Construction Co. v. Robbins
2009 UT 52 (Utah Supreme Court, 2009)
Bickerstaff v. Prevost
670 S.E.2d 660 (Court of Appeals of South Carolina, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
641 S.E.2d 459, 372 S.C. 89, 2007 S.C. App. LEXIS 1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/taylor-cotton-ridley-inc-v-okatie-hotel-group-llc-scctapp-2007.