Ferguson Fire & Fabrication, Inc. v. Preferred Fire Protection, LLC

725 S.E.2d 495, 397 S.C. 379, 2012 WL 652447, 2012 S.C. App. LEXIS 60
CourtCourt of Appeals of South Carolina
DecidedFebruary 29, 2012
Docket4947
StatusPublished
Cited by1 cases

This text of 725 S.E.2d 495 (Ferguson Fire & Fabrication, Inc. v. Preferred Fire Protection, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ferguson Fire & Fabrication, Inc. v. Preferred Fire Protection, LLC, 725 S.E.2d 495, 397 S.C. 379, 2012 WL 652447, 2012 S.C. App. LEXIS 60 (S.C. Ct. App. 2012).

Opinion

WILLIAMS, J.

On appeal, Ferguson Fire and Fabrication, Inc. (Ferguson Fire) argues the circuit court erred in holding Immedion, LLC (Immedion) was not liable on the materialman’s lien when Immedion paid its general contractor in full after receiving notice from Ferguson Fire. Ferguson Fire also contends the circuit court erred in holding its notice to Immedion was ineffective under South Carolina law. In addition, Ferguson Fire claims the circuit court erred in determining South Carolina law does not protect a materialman’s lien until after the materialman records and serves a statement of the lien. Finally, Ferguson Fire argues the circuit court erred in awarding Immedion attorney’s fees related to the filing and prosecution of a third-party claim. We affirm.

FACTS/PROCEDURAL HISTORY

The facts in this appeal are not in dispute. Immedion contracted with Rescom, LLC (Rescom) to serve as general contractor in performing upfit work to Immedion’s data center. Rescom, in turn, hired Preferred Fire Protection, LLC *382 (Preferred Fire) as a subcontractor to perform work in connection with the upfit of the property. In addition, Immedion separately contracted with Preferred Fire to install a preaction fire suppression system in the data center for a contract price of $30,973. Preferred Fire subsequently hired Ferguson Fire and Fabrication, Inc. (Ferguson Fire) to provide the materials necessary for installation of the pre-action fire suppression system.

Beginning on August 24, 2007, and continuing through October 16, 2007, Ferguson Fire delivered the materials for the pre-action system. On September 21, 2007, Ferguson Fire sent a “Notice of Furnishing Labor and Materials” (Notice) to Immedion stating Ferguson Fire was employed by Preferred Fire and “ha[s] provided or will provide fire sprinkler/pipe/valve/fittings with an estimated value of $15,000.” The Notice did not specify an “amount claimed to be due” and did not indicate when it expected delivery of the materials to be completed. Instead, the Notice provided that materials “were actually furnished or scheduled to be furnished by [Ferguson Fire] to the Project from Sep 10, 2007 [sic] through __” The Notice further stated:

Please be advised that this company is hereby providing you with notice of furnishing labor and materials to the Project described below pursuant to S.C.Code Ann. § 29-5-20(B) and § 29-5-40. It is important to note that this is not a lien. This is a routine procedure to comply with certain state requirements that may exist and should not reflect in any way on the integrity or credit standing of Preferred Fire Protection . . . . 1

On August 30, 2007, prior to receiving Ferguson Fire’s Notice, Immedion issued a check to Preferred Fire for $15,486.50, according to their agreement. After receiving Ferguson Fire’s Notice, but prior to the date all materials were delivered by Ferguson Fire, Immedion issued a second check to Preferred Fire on October 3, 2007, in the amount of $14,513.50. On October 31, 2007, Immedion issued a third and final check to Preferred Fire for the remaining contract balance of $973. Although Immedion made full payment to *383 Preferred Fire for the installation of the pre-action system, Preferred Fire failed to pay Ferguson Fire $15,548.93 for the materials it furnished.

On January 8, 2008, Ferguson Fire filed and served a notice of mechanic’s lien to Preferred Fire and Immedion. Ferguson Fire subsequently filed a summons and complaint against Preferred Fire and Immedion alleging Ferguson Fire provided certain “materials, services, and/or labor to the improvements located on the Property pursuant to a binding contract and agreement with Preferred Fire and with the knowledge and permission of Immedion ...” and sought to foreclose its mechanic’s lien. Preferred Fire did not answer Ferguson Fire’s complaint, and on January 14, 2009, Ferguson Fire obtained a default judgment against Preferred Fire that it has been unable to collect. Immedion answered, asserting Ferguson Fire’s complaint should be dismissed because Immedion paid Preferred Fire all sums due to Preferred Fire on the contract prior to receiving Ferguson Fire’s Notice. In addition, Immedion filed a third-party complaint against Rescom for breach of contract and attorney’s fees. Immedion and Rescom subsequently settled the third-party claims and dismissed that action on July 20, 2009.

In the present action, Immedion filed a motion for summary judgment, contending it paid in full all work performed by its contractors. Ferguson Fire filed a cross-motion for summary judgment, arguing Immedion should have been on notice of its claim because Ferguson Fire provided Immedion the Notice prior to Immedion’s full payment to Preferred Fire. The circuit court issued an order granting Immedion’s motion for summary judgment, holding the Notice that Ferguson Fire provided was ineffective under section 29-5-40 of the South Carolina Code (Supp.2011) as a notice of lien. The circuit court’s order also awarded Immedion attorney’s fees for successfully defending against the mechanic’s lien. This appeal followed.

STANDARD OF REVIEW

Summary judgment is proper when no genuine issue of material fact exists, and the moving party is entitled to judgment as a matter of law. See Rule 56(c), SCRCP; Tup *384 per v. Dorchester Cnty., 326 S.C. 318, 325, 487 S.E.2d 187, 191 (1997). When plain, palpable, and indisputable facts exist on which reasonable minds cannot differ, summary judgment should be granted. Ellis v. Davidson, 358 S.C. 509, 518, 595 S.E.2d 817, 822 (Ct.App.2004).

When reviewing the grant of summary judgment, this court applies the same standard that governs the circuit court under Rule 56, SCRCP. Pittman v. Grand Strand Entm’t, Inc., 363 S.C. 531, 536, 611 S.E.2d 922, 925 (2005) (internal citations omitted). “On appeal, all ambiguities, conclusions, and inferences arising in and from the evidence must be viewed in a light most favorable to the non-moving party.” Id. at 536, 611 S.E.2d at 925.

In addition, “the award of attorney’s fees is left undisturbed absent abuse of the [circuit] court’s discretion.” Taylor, Cotton & Ridley, Inc. v. Okatie Hotel Group, LLC, 372 S.C. 89, 100, 641 S.E.2d 459, 464 (Ct.App.2007) (internal citation omitted).

LAW/ANALYSIS

I. Ferguson Fire’s Notice 2

Ferguson Fire asserts the circuit court erred in holding its Notice was ineffective as a notice of lien under section 29-5^10. We disagree.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ferguson Fire & Fabrication, Inc. v. Preferred Fire Protection, L.L.C.
762 S.E.2d 561 (Supreme Court of South Carolina, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
725 S.E.2d 495, 397 S.C. 379, 2012 WL 652447, 2012 S.C. App. LEXIS 60, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ferguson-fire-fabrication-inc-v-preferred-fire-protection-llc-scctapp-2012.