Ferguson Fire & Fabrication, Inc. v. Preferred Fire Protection, L.L.C.

762 S.E.2d 561, 409 S.C. 331
CourtSupreme Court of South Carolina
DecidedAugust 13, 2014
DocketAppellate Case 2012-212191; 27410
StatusPublished
Cited by18 cases

This text of 762 S.E.2d 561 (Ferguson Fire & Fabrication, Inc. v. Preferred Fire Protection, L.L.C.) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ferguson Fire & Fabrication, Inc. v. Preferred Fire Protection, L.L.C., 762 S.E.2d 561, 409 S.C. 331 (S.C. 2014).

Opinion

ORDER

The Petition for Rehearing in the above matter is denied. However, the opinion is refiled to eliminate a sentence from the factual recitation that does not affect the result.

/s/COSTA M. PLEICONES A.C.J. /s/DONALD W. BEATTY, J. /s/JOHN W. KITTREDGE, J.

FOR THE COURT.

Acting Justice D. CRAIG BROWN and Acting Justice DOROTHY MOBLEY JONES, not participating.

Justice BEATTY.

This Court granted a petition for a writ of certiorari to review the decision in Ferguson Fire & Fabrication, Inc. v. Preferred Fire Protection, L.L.C., 397 S.C. 379, 725 S.E.2d 495 (Ct.App.2012), in which a supplier of materials (“Ferguson Fire”) brought an action for foreclosure of a mechanic’s lien against the owner of a data center (“Immedion”) and its contractor (“Preferred Fire”). Ferguson Fire contends, and we agree, that the Court of Appeals erred in adding requirements to S.C Code Ann. § 29-5-40 (2007), governing a notice of furnishing, that are not in the statute itself and in concluding Ferguson Fire did not establish an effective lien upon which a foreclosure action could be premised. We reverse and remand.

I. FACTS

This case arises out of Ferguson Fire’s efforts to obtain payment for materials it supplied to Preferred Fire for Immedion’s data center. An outline of the events leading to Fergu *336 son Fire’s mechanic’s lien action and the lower courts’ rulings follow.

Contracts for Improvements to Immedion’s Data Center

In 2007, Immedion, a telecommunications company, hired Rescom, L.L.C. to be the general contractor for improvements planned for its data center on property Immedion leased in Greenville. This contract excluded the performance of part of the fire protection work that was needed. Rescom, in turn, hired Preferred Fire, a fire sprinkler company, as a subcontractor.

In addition, Immedion directly hired Preferred Fire under a separate contract for $30,973.00 to install a special “preaction” fire suppression system 1 in its data center. To complete this work, Preferred Fire purchased materials from Ferguson Fire. Ferguson Fire began delivering materials to Preferred Fire on August 24, 2007, and the deliveries continued through October 16, 2007.

Notice of Furnishing Labor and/or Materials

On September 21, 2007, while its deliveries were in progress, Ferguson Fire sent a “Notice of Furnishing Labor and Materials” (“Notice of Furnishing”) to Immedion advising it in relevant part that it had been employed by Preferred Fire to deliver labor, services, or materials with an estimated value of $15,000.00 to Immedion’s premises. The Notice of Furnishing advised that it was being given as “a routine procedure to comply with certain state requirements that may exist,” and that it was not a lien, nor any reflection on Preferred Fire’s credit standing.

Immedion paid Preferred Fire $15,486.50 of the $30,973.00 contract price for installation of the system before receiving Ferguson Fire’s Notice of Furnishing on September 21, 2007. After receiving the Notice of Furnishing, Immedion issued two additional checks to Preferred Fire totaling $15,486.50 for the unpaid balance of the contract price.

*337 It is undisputed that Immedion paid everything it owed to Rescom, and it also paid its contractor Preferred Fire in full under the separate contract for the fire suppression system. However, Preferred Fire never paid Ferguson Fire for the materials it furnished.

Notice or Certifícate of Lien

On January 8, 2008, Ferguson Fire served upon Immedion, Preferred Fire, and others (and later filed) a “Statement and Notice of Mechanic’s Lien,” which gave notice of the existence of a lien and included a Statement of Account. Ferguson Fire indicated it had supplied $15,548.93 in materials to Preferred Fire for Immedion’s premises from August 24, 2007 through October 16, 2007 pursuant to an agreement with Preferred Fire that was entered into “with the knowledge and consent and permission and authorization of Immedion.” Ferguson Fire stated $15,548.93 was still owing and due, and it asserted a mechanic’s lien upon the described premises.

Complaint for Foreclosure of Lien & Summary Judgment Motions

On April 11, 2008, Ferguson Fire filed a complaint and a lis pendens against Preferred Fire, Fair Forest of Greenville, L.L.C., Thomas F. Wong, and Immedion seeking foreclosure of a mechanic’s lien as to all defendants, as well as attorney’s fees, costs, and interest. 2

Immedion answered 3 and thereafter moved for summary judgment, maintaining (1) there was no evidence Ferguson Fire had furnished any materials for the benefit of property owned by Immedion, as it was a mere leaseholder; (2) there was no contractual relationship giving rise to liability between *338 Ferguson Fire and Immedion; and (3) Immedion paid in full for all work performed by its contractors, so it had no further liability pursuant to S.C.Code Ann. § 29-5-20(B).

Ferguson Fire filed a cross-motion for summary judgment, arguing (1) under S.C.Code Ann. § 29-5-30 a leasehold interest in property is subject to a materialman’s lien; (2) a materialman supplying materials to a contractor has a lien for the value of the materials on the leaseholder’s interest under S.C.Code Ann. § 29-5-20, and the value of the lien is limited to the amount due to the contractor by the owner/leaseholder as of the date of notice under sections 29-5-20 and 29-5-40; and (3) Immedion should have been aware of its potential claim because Ferguson Fire gave Immedion the Notice of Furnishing prior to Immedion’s full payment to Preferred Fire.

Ferguson Fire asserted since it gave Immedion notice on September 21, 2007 that it was furnishing materials for its premises, under South Carolina’s mechanic’s lien statutes, it was entitled to a lien up to the amount Immedion paid to its contractor, Preferred Fire, after that date, plus attorney’s fees and interest. 4 Ferguson Fire noted that the value of the materials it supplied to Preferred Fire was actually greater than the amount of its lien, but acknowledged that under the statutory provisions its lien was limited to the unpaid balance of the contract between Immedion and Preferred Fire as of the date of its Notice of Furnishing.

Decisions of Circuit Court & Court of Appeals

The circuit court granted summary judgment to Immedion and extinguished the mechanic’s lien filed by Ferguson Fire. The court stated, “The issue is whether the Notice of Furnishing was sufficient to notify the owner [Immedion] of the lien given by § 29-5-20.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Kenneth W. Signor, Sr.
Court of Appeals of South Carolina, 2025
ARM Quality Builders, LLC v. Joseph Golson
Court of Appeals of South Carolina, 2024
McEntire Produce v. SCDOR
Court of Appeals of South Carolina, 2023
Jack's Custom Cycles v. SCDOR
Court of Appeals of South Carolina, 2023
Carla Denise Garrison v. Target Corporation
Supreme Court of South Carolina, 2022
Powell v. Keel
Supreme Court of South Carolina, 2021
The Kitchen Planners v. Friedman
Court of Appeals of South Carolina, 2020
Carolina Comfort v. Weddle
Court of Appeals of South Carolina, 2019
Terlizzi Home Improvement v. Boheler
Court of Appeals of South Carolina, 2017
Vision Contracting v. Geter
Court of Appeals of South Carolina, 2016
Moats Construction v. Sanders
Court of Appeals of South Carolina, 2016
State v. Jones
Court of Appeals of South Carolina, 2015
Tucker v. Doe
776 S.E.2d 121 (Court of Appeals of South Carolina, 2015)
Greens of Rock Hill, LLC v. Rizon Commercial Contracting, Inc.
766 S.E.2d 876 (Court of Appeals of South Carolina, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
762 S.E.2d 561, 409 S.C. 331, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ferguson-fire-fabrication-inc-v-preferred-fire-protection-llc-sc-2014.