Summit Contracting Group, Inc. v. Ashland Heights, LP

187 F. Supp. 3d 893, 2016 U.S. Dist. LEXIS 60662, 2016 WL 2607056
CourtDistrict Court, M.D. Tennessee
DecidedMay 6, 2016
DocketCivil No. 3:16-CV-17
StatusPublished
Cited by2 cases

This text of 187 F. Supp. 3d 893 (Summit Contracting Group, Inc. v. Ashland Heights, LP) is published on Counsel Stack Legal Research, covering District Court, M.D. Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Summit Contracting Group, Inc. v. Ashland Heights, LP, 187 F. Supp. 3d 893, 2016 U.S. Dist. LEXIS 60662, 2016 WL 2607056 (M.D. Tenn. 2016).

Opinion

MEMORANDUM

ALETA A. TRAUGER, United States District Judge

The defendant, Ashland Heights, LP (“Ashland”), has filed a Motion to Dismiss (Docket No. 5), to which the plaintiff, Summit Contracting Group,. Inc. (“Summit”), has filed a Response (Docket No. 10) and a Supplemental Response (Docket No. 19) in opposition. For the following reasons, the motion will be denied.

I. Background

This is a construction dispute between a commercial general contractor (Summit) and an owner (Ashland) for the construction of an assisted living facility at 2035 Vantage Pointe, Ashland City, Cheatham County, Tennessee. The court focuses on the well-pleaded allegations in the Complaint. (Docket No. 1.) Summit is a Florida corporation with offices in Florida, but it is authorized to do business in Tennessee and is a fully-licensed Tennessee general contractor. Ashland is a limited liability partnership that owned the land that is the subject of this dispute and wished to construct a senior living facility, known as Vantage Point Village, at that location (the “Project”).

A. Contract Between Ashland and Summit

On September 16, 2013, Summit and Ashland entered into a construction contract for the Project (the “Contract”). The Contract provided that Summit would be the general contractor for the Project and [895]*895perform the described “Work” for an initial lump sum price of $8,667,731.00, to be increased or . decreased based on subsequent change orders. The Contract included provisions requiring incremental progress payments when ■ Summit reached monthly Project completion milestones. When Summit was entitled.to a progress payment for approved work on thé Project each month, Ashland was required to pay by the 10th day of the following month if the pay request was' received by the 25th of the preceding month. Ashland was further required to withhold from any progress payment 5% as “Retainage” until 50% of the Project was complete.1 The Contract also provided that Summit was entitled to extended general conditions for the number of days that work is stopped due to inclement, weather that ■ exceeds 30 days. Finally, the Contract provided that Summit was entitled to 6% interest for payments which were untimely - paid by Ash-land. Finally, the Contract provides that, “[i]n the event that any litigation or other dispute resolution proceeding is commenced that involves, arises out of or relates to this contract, the prevailing party shall be entitled to an award of taxable court costs, other related but non-taxable costs and expenses, and reasonable attorney fees.”

B. The Project

Summit began work on the Project in November of 2013. As alleged, Summit’s work on the Project was substantially complete, as agreed to in writing by both Ashland and its architect, in May of 2015. On -November 25, 2013, Summit submitted its Application for Payment No. 1 in the full amount of $279,062.32, which requested approval and payment of the amount of $265,075.00 (“AFP No. 1”>. The difference in the amounts is the 5% Retainage in the amount of $13,951.32. Ashland approved AFP No 1, paid Summit $265,075.00 on December 10, 2013, and withheld 5% as the Retainage called for in the Contract (the “AFP No. 1 Retainage”). Summit alleges, however, that, upon the payment of AFP No. 1, Ashland did not deposit the AFP No. 1 Retainage into an interest bearing escrow account with a third party, as required by Tennessee’s Retainage Laws. Summit further alleges that, for each and every subsequent progress payment application submitted by Summit to Ashland, Ashland withheld Retainage but did not deposit the Retainage into an interest bearing escrow account.' The total Retaináge withheld by Ashland from Summit is alleged to be $320,415.74.

On October 13, 2014, via letter from counsel and pursuant to the Tennessee Retainage Laws, Summit demanded from Ashland details on the third-party Retain-age escrow account that Ashland had been required to create and fund. Summit also informed Ashland that, if such escrow account had not been created with, the total [896]*896Retainage, Summit would seek payment of the mandatory statutory penalty of $300 per day in violation. On October 23, 2014, after receipt of the demand letter, Ashland provided evidence that it deposited an amount- equal to the total Retainage into a bank account with -Max Credit Union, which also held the deed of trust on the subject property and was the lender to Ashland for the Project. The Complaint alleges that, despite the creation of this bank account, Ashland has not provided any evidence to Summit that such account was in fact a third-party escrow account as mandated by the Retainage Laws. According to Summit, therefore, “[a]s such, until and unless [Ashland] provides such evidence, the $300 a day statutory penalty did not stop accruing on October 23, 2014, and continues through the filing of this lawsuit.” (Docket No. 1, ¶ 30.) Summit provided written notice to Ashland of its statutory $300 per day claim and maintains that it is therefore entitled to a monetary judgment against Ashland of, at a minimum, the $300 per day statutory penalty from December 10, 2013 to October 23, 2015, assuming the bank account created was in fact a true “escrow” account.

Summit alleges that it submitted other applications for payment to Ashland, along with change orders for work properly ordered and performed, for which Summit has allegedly not been paid despite multiple written demands. In addition, Summit alleges that many of Ashland’s payments to Summit were not timely, in violation of the Contract, and that Summit is, therefore, entitled to recover interest.

Finally, Summit alleges that it is entitled to recover additional miscellaneous costs and expenses. Summit alleges that the total number of days in which Summit’s work was stopped as a result of inclement weather exceeded 30 days and, therefore, Summit is entitled to payment of its extended general conditions. -Summit also maintains that it incurred other expenses and costs associated with investigations and actions based on unwarranted claims by Ashland that Summit was the cause of the alarm system installed on the Project having “unwanted alarms.”

C. Summit’s Claims and Suits

Summit, therefore, brings a breach of contract claim and a claim under Tennessee’s Prompt Pay Act and Retainage Laws. Summit also “contemporaneously filed with the Cheatham County, Tennessee Chancery Court a lawsuit against Ash-land in order to timely and properly under Tennessee lien law enforce the mechanic’s lien which Summit claims and has filed against the real property of the Project.” (Docket No. 1 ¶ 45.) More specifically, on January 11, 2016, at 1:30 p.m., Summit filed a mechanic’s lien2 action against the Project property in the Cheatham County Register’s Office, naming not only Ashland as a defendant, but also the Trustee (Old Republic Title Company) and Bank (Max Credit Union) under a recorded Deed of Trust on the Property (since both had an interest in the Property and thus the Lien) (the “State Court Lien Action”).3 The State Court Lien Action seeks only the enforcement of the Lien in the amount of $1,074,668.74. Second, on January 11, 2016 at 5:07 pm, Summit filed the pending lawsuit in this court, naming only Ashland as a defendant (the “Federal Court Contract Action”). Because of the nature of the ac[897]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
187 F. Supp. 3d 893, 2016 U.S. Dist. LEXIS 60662, 2016 WL 2607056, Counsel Stack Legal Research, https://law.counselstack.com/opinion/summit-contracting-group-inc-v-ashland-heights-lp-tnmd-2016.