Sully-Miller Contracting Co. v. Gledson/Cashman Construction, Inc.

126 Cal. Rptr. 2d 400, 103 Cal. App. 4th 30, 2002 Daily Journal DAR 12319, 2002 Cal. Daily Op. Serv. 10661, 2002 Cal. App. LEXIS 4861
CourtCalifornia Court of Appeal
DecidedOctober 24, 2002
DocketB152582
StatusPublished
Cited by32 cases

This text of 126 Cal. Rptr. 2d 400 (Sully-Miller Contracting Co. v. Gledson/Cashman Construction, Inc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sully-Miller Contracting Co. v. Gledson/Cashman Construction, Inc., 126 Cal. Rptr. 2d 400, 103 Cal. App. 4th 30, 2002 Daily Journal DAR 12319, 2002 Cal. Daily Op. Serv. 10661, 2002 Cal. App. LEXIS 4861 (Cal. Ct. App. 2002).

Opinion

Opinion

PERREN, J.

Appellants signed documents agreeing to dismiss these actions and release their claims against respondents and another defendant in *33 exchange for the payment of money. Those documents, which were prepared by one of the respondents’ attorneys, did not call for any signatures other than appellants’, nor did they specify who was obligated to make the payments on which the agreements were conditioned. When no payment was forthcoming, appellants gave notice that they were withdrawing their agreement to settle. Several months later, respondents attempted to tender payment, which appellants refused.

Respondents subsequently moved for settlement under Code of Civil Procedure section 664.6 (hereafter section 664.6), contending that the documents at issue were enforceable as written settlement agreements. After appellants pointed out that the documents were not signed by the parties as required by that section, one of the respondents simply added its signature to the end of both documents. The trial court granted respondents’ motions, and entered judgment accordingly.

We agree with appellants that the documents they signed are not enforceable as settlement agreements under section 664.6. As drafted, those documents were merely unilateral offers to settle that were revoked prior to their acceptance by the tender of payment. Moreover, they were not signed by the parties as required by section 664.6. Accordingly, we reverse.

Facts and Procedural Background

Appellants Sully-Miller Contracting Company (Sully-Miller) and Hanson Aggregates West, Inc. (Hanson), are building material suppliers that brought actions against a general contractor, respondent Gledson/Cashman Construction, Inc. (Gledson), Gledson’s surety, respondent Ulico Casualty Company (Ulico), and Carpintería Unified School District (District), 1 to recover for unpaid materials on a construction project at Carpintería High School. Appellants sued Gledson and Ulico to recover against a public works payment bond and sued the District to enforce a stop notice.

On June 6, 2000, Gledson’s attorney, John Logan Hunter, wrote to appellants’ attorney, Craig P. Bronstein, “confirm[ing] the agreement reached in our telephone conversation last week.” The letter stated that the District would issue joint checks to Gledson and Hanson for $17,900, and to Gledson and Sully-Miller for $34,500, in exchange for which appellants would “provide Conditional Waivers and Releases upon Final Payment along with dismissals and executed Settlement Agreements] in the forms enclosed.” The documents prepared by Hunter for appellants’ signatures *34 provided that “for and in consideration for” the payments, appellants would dismiss and release all claims against respondents and the District. Those documents contained signature blocks for appellants only and did not specify which of the defendants, if any, was responsible for making the payments to appellants.

On June 20, Bronstein faxed Hunter copies of the executed documents on behalf of Sully-Miller with a fax cover sheet stating: “Here are the executed releases. As we discussed, this is contingent on payment being received by Friday June 24, 2000. . . . Please advise if this is not possible.” On June 21, Bronstein faxed copies of the executed documents on behalf of Hanson with a cover sheet stating: “Here are the executed releases. Please have check cut ASAP. Cut off on this one is next Friday. Thank you.”

Appellants did not receive their payments as contemplated. On July 17, 2000, the District notified appellants that “at this time the funds being withheld by the District pursuant to the stop notices filed by all claimants is insufficient to satisfy the amounts stated in your conditional releases, as well as the remaining stop notices. For this reason we cannot make payment upon your conditional releases.” On July 19, Hunter requested immediate payment from the District, noting that “[t]he premise of [Gledson’s] settlements [with appellants] was that funds would timely be released . . . .” The District responded through its counsel that “[w]e realize that Gledson/Cashman and these vendors have reached an agreement, however, the District is not a party to that agreement and has a separate statutory duty in regard to the moneys withheld due to the numerous stop notices.” The District further noted that Gledson could have resolved the problem by filing additional stop notice release bonds, but had refused to do so.

By letter dated August 7, 2000, appellants notified respondents that they were revoking and withdrawing their offers to settle for the previously stated amounts because “[i]t has now been over two months since [appellants] agreed to discount [their] claim[s] ... in expectation of immediate payment of the agreed-upon amount” and because appellants had “incurred additional costs as a result of the delay . . . .” Appellants submitted increased demands reflecting these additional costs, which included accrued interest and attorney fees. Gledson did not respond to appellants’ August 7 letter or to subsequent letters sent the following October and November.

On January 24, 2001—over seven months after appellants had returned signed copies of the documents prepared by Gledson’s attorney—Gledson submitted checks to appellants in the form and amounts provided in the *35 earlier documents, along with a letter from Hunter stating that “[w]e are fully cognizant of your recent position concerning the agreements] reached between our respective clients and believe the enclosed draft[s] fiilfill[] our obligations thereunder. If you dispute the settlement, please advise and we will move to enforce the written agreements] . . . .”

Bronstein promptly returned the checks along with a letter reiterating that appellants had withdrawn their offers to settle for the previously stated amounts. Bronstein noted that appellants had never received any response to their August 7, 2000, revocation letters or their subsequent correspondence, and that appellants had been “forced to incur substantial additional attorneys’ fees related to the delay in payment, including those related to our being forced to participate in various hearings in the consolidated cases.”

Respondents subsequently moved to enforce the documents as settlement agreements under section 664.6. Appellants opposed the motions, contending that the documents were not enforceable under that section because (1) they were merely unilateral offers to settle that had been revoked prior to acceptance, and (2) they were not signed by all of the parties as required by the statute. In an effort to belatedly comply with the signature requirement, Gledson simply tacked on its undated signature at the end of both documents and submitted them in reply to appellants’ opposition.

After a hearing, the trial court granted respondents’ motions without comment and entered judgment pursuant to the terms stated in the documents. The court also ordered each of the appellants to pay Gledson $473 pursuant to an attorney fee provision in the documents.

Discussion

I.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Temple View Capital Funding v. Garnicki CA1/2
California Court of Appeal, 2026
Bhakta v. Bhakta CA4/2
California Court of Appeal, 2024
Wheeler v. Safeway CA3
California Court of Appeal, 2023
Andrew Roley v. Google LLC
40 F.4th 903 (Ninth Circuit, 2022)
Rezzadeh v. Chiu CA5
California Court of Appeal, 2021
Nunn v. JPMorgan Chase Bank
California Court of Appeal, 2021
WindAirWest v. Castle & Cooke etc. CA2/3
California Court of Appeal, 2021
Thompson v. Casas CA2/4
California Court of Appeal, 2020
Mesa RHF Partners v. City of LA
California Court of Appeal, 2019
Mesa RHF Partners, L.P. v. City of L. A.
245 Cal. Rptr. 3d 512 (California Court of Appeals, 5th District, 2019)
Juen v. Alain Pinel Realtors, Inc.
California Court of Appeal, 2019
Juen v. Alain Pinel Realtors, Inc.
244 Cal. Rptr. 3d 411 (California Court of Appeals, 5th District, 2019)
Marriage of Corona CA2/8
California Court of Appeal, 2016
Clever Hospitality v. Patel CA2/2
California Court of Appeal, 2016
Tanasescu v. Raphs Grocery Co. CA4/3
California Court of Appeal, 2015
Tanasescu v. Ralphs Grocery Co. CA4/3
California Court of Appeal, 2015
Depew v. Hazan CA2/2
California Court of Appeal, 2015
J.B.B. Investment Partners v. Fair
California Court of Appeal, 2014
J.B.B. Investment Partners, Ltd. v. Fair
232 Cal. App. 4th 974 (California Court of Appeal, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
126 Cal. Rptr. 2d 400, 103 Cal. App. 4th 30, 2002 Daily Journal DAR 12319, 2002 Cal. Daily Op. Serv. 10661, 2002 Cal. App. LEXIS 4861, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sully-miller-contracting-co-v-gledsoncashman-construction-inc-calctapp-2002.