Stone & Webster, Inc. v. Baker Process, Inc.

210 F. Supp. 2d 1177, 2002 U.S. Dist. LEXIS 15842, 2002 WL 1483635
CourtDistrict Court, S.D. California
DecidedJune 18, 2002
Docket3:02-cr-00638
StatusPublished
Cited by5 cases

This text of 210 F. Supp. 2d 1177 (Stone & Webster, Inc. v. Baker Process, Inc.) is published on Counsel Stack Legal Research, covering District Court, S.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stone & Webster, Inc. v. Baker Process, Inc., 210 F. Supp. 2d 1177, 2002 U.S. Dist. LEXIS 15842, 2002 WL 1483635 (S.D. Cal. 2002).

Opinion

ORDER DENYING STONE & WEBSTER’S MOTION FOR JOINDER OF ARBITRATION CLAIMS WITH THIS ACTION [3-1]; AND GRANTING SALTON SEA POWER’S MOTION TO COMPEL ARBITRATION AND STAY THE INSTANT PROCEEDINGS [7-1]

STIVE N, United States Magistrate Judge.

7. INTRODUCTION

On May 24, 2002, Plaintiff Stone & Webster Inc.’s Motion for Joinder of Arbitration Claims with this Action and Defendant Saltón Sea Power LLC’s Motion to Compel Arbitration and Stay the Instant Proceedings came on regularly for hearing in the above entitled Court. Plaintiffs motion was filed on April 16, 2002. 1 Opposition papers were filed on May 10, 2002. Reply papers were filed on May 23, 2002. Defendant’s motion was filed on April 24, 2002. Plaintiff filed an opposition on May 10, 2002. Defendant replied on May 23, 2002. Attorneys Michael F. Boyle, Esq. and Nicholas K. Holmes, Esq. appeared for Plaintiff. Attorneys David Hecker, Esq. and Ann Salisbury, Esq. appeared for Defendant Saltón Sea Power, LLC, and Bill Collier, Esq. appeared on behalf of Defendant Baker Process, Inc. 2

*1179 II. BACKGROUND

A. RELEVANT FACTUAL BACK GROUND 3

In September of 1998, Defendant Saltón Sea Power LLC (“Saltón”) entered into a contract with Plaintiff Stone & Webster, Inc. (“Stone & Webster”) for the design, procurement, and construction of a geothermal power plant — a Silica Control System — in Calipatria, California.

Based on Salton’s specifications, Stone & Webster entered into a subcontract with Baker Process, Inc. (“Baker Process”) to help design as well as supply and erect the components of the Silica Control System.

During the start-up of the power plant, Saltón complained of problems with certain components of the Silica Control System, many of which were provided by Baker Process. Saltón demanded that Stone & Webster correct the problem and/or provide an entirely new system.

In March 2002, Saltón commenced an arbitration proceeding against Stone & Webster to resolve the disputes that had arisen with respect to the Silica Control System pursuant to the arbitration clause contained in the Stone & Webster/Salton contract. Stone & Webster notified Baker Process of Salton’s arbitration demand and requested that Baker Process defend Stone & Webster in the arbitration. Baker Process has not agreed to do so and is not a party to the arbitration proceeding.

B. PRESENT DISPUTE

On April 23, 2002, Plaintiff Stone & Webster commenced the instant federal action for declaratory relief against Saltón and declaratory relief and indemnity against Baker Process. In this action, Stone & Webster seeks a determination of its liabilities under the Stone & Webster/Salton contract and the Stone & Webster/Baker Process contract for any design and construction defects in the Silica Control System. Stone & Webster maintains that Saltón specified the design of the Silica Control System and Baker Process provided and constructed the systems’ components, therefore Saltón and Baker Process are responsible and/or liable for any flaws or defects that may exist in the design and construction of the Silica Control System.

By the instant motion, Plaintiff Stone & Webster moves this Court for an order joining the claims asserted in the arbitration proceeding with the instant action. In support of its motion, Stone & Webster maintains that joinder is necessary so that all of the relevant parties’ rights and obligations may be determined in a consistent fashion, in a single proceeding. Stone & Webster claims that it cannot compel Baker Process to participate in the arbitration proceeding, because Stone & Webster’s purchase order with Baker Process does not contain an arbitration clause. Hence, Baker Process cannot be made a party to the arbitration suit, but can be and is a party to the instant action. Therefore, Plaintiff asserts, Stone & Webster’s rights and liabilities can only be fully adjudicated in the court action, in which all relevant parties can be made to participate.

Conversely, by its motion, Defendant Saltón moves this Court to compel Stone & Webster to arbitrate the disputes arising out of the Stone & Webster/Salton contract pursuant to the parties’ agreement to arbitrate and stay the instant action until such claims are arbitrated.

C.PARTIES’ARGUMENTS

Neither Stone & Webster nor Saltón disputes that there exists a valid agree *1180 ment to arbitrate all disputes arising from their contract 4 and that the Stone & Webster/Salton contract falls within the scope of the Federal Arbitration Act. 5

Plaintiff Stone & Webster simply argues that California Code of Civil Procedure § 1281.2(c) (“Section 1281.2(c)”) was incorporated into the parties’ contract 6 by way of the agreement’s choice-of-law clause which provides that the contract shall be governed by the laws of the State of California; 7 and Section 1281.2(c) allows the joinder of an arbitration proceeding with a court action when, as here: 1) a party to the arbitration agreement is also a party to the court action with a third party; 2) the arbitration and court actions arise out of the same transactions; 3) there are common issues of law and fact in the arbitration proceeding and the lawsuit; and 4) there is a danger of inconsistent rulings on those common issues if the arbitration is not joined with the court action. 8 See Calif.Civ.Proc.Code Ann. § 1281.2(c) (West 2002). Plaintiff Stone & Webster maintains that it is simply invoking its right to move for joinder under the terms of the agreement.

Defendant Saltón, on the other hand, argues that the parties’ contract is governed by the FAA; the FAA preempts Section 1281.2(c); and the choice-of-law clause in the subject contract does not incorporate Section 1281.2(c). Furthermore, the mere possibility of conflicting rulings is not a ground for staying arbitration under the FAA, and finally Plaintiff Stone & Webster is not prejudiced by the possibility of conflicting rulings under the circumstances of this case.

III. DISCUSSION

The principle issue to be decided by this Court is whether federal law (the “FAA”) or California state law (“Section 1281.2(c)”) governs the issue of arbitrability (whether or not arbitration will be had) in the subject contract. More specifically, this Court must determine, using applicable case-law, how to construe the choice-of-law clause in the parties’ contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MegaForce v. Eng
D. Minnesota, 2019
Breazeale v. Victim Services, Inc.
198 F. Supp. 3d 1070 (N.D. California, 2016)
Biomagic, Inc. v. Dutch Brothers Enterprises, LLC
729 F. Supp. 2d 1140 (C.D. California, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
210 F. Supp. 2d 1177, 2002 U.S. Dist. LEXIS 15842, 2002 WL 1483635, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stone-webster-inc-v-baker-process-inc-casd-2002.