Sterling Contracting, L.L.C. v. Main Event Entertainment, L.P.

2022 Ohio 2138
CourtOhio Court of Appeals
DecidedJune 23, 2022
Docket110965
StatusPublished
Cited by5 cases

This text of 2022 Ohio 2138 (Sterling Contracting, L.L.C. v. Main Event Entertainment, L.P.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sterling Contracting, L.L.C. v. Main Event Entertainment, L.P., 2022 Ohio 2138 (Ohio Ct. App. 2022).

Opinion

[Cite as Sterling Contracting, L.L.C. v. Main Event Entertainment, L.P., 2022-Ohio-2138.]

COURT OF APPEALS OF OHIO

EIGHTH APPELLATE DISTRICT COUNTY OF CUYAHOGA

STERLING CONTRACTING, LLC, :

Plaintiff-Appellant,

v. : No. 110965 MAIN EVENT : ENTERTAINMENT, LP, ET AL.,

Defendants-Appellees. :

JOURNAL ENTRY AND OPINION

JUDGMENT: AFFIRMED RELEASED AND JOURNALIZED: June 23, 2022

Civil Appeal from the Cuyahoga County Court of Common Pleas Case No. CV-18-906890

Appearances:

Wilson & Wilson Co., L.P.A., Robert D. Wilson, and Michael J. Wilson, for appellant.

Franz Ward, LLP, Ian H. Frank, and Allison Taller Reich, for appellees. SEAN C. GALLAGHER, A.J.:

Sterling Contracting, LLC appeals the grant of summary judgment in

favor of Main Event Entertainment, LP, and National Retail Properties, LP. For the

following reasons, we affirm.

There is no dispute over the facts of this case; the sole focus of this

appeal is on the application of legal principles to those facts. Main Event leased

property located in Avon, Ohio, from National Retail for an initial term of fifteen

years, with the right to renew for an additional ten-year term followed by an optional

five-year term. Main Event executed a construction contract with Omni

Construction Company, Inc., to build a commercial entertainment center on the

leased property. In exchange for the sum of $8,681,026, Omni agreed to complete

the project in 220 calendar days, starting from July 2017. Through addendums and

approved changes during the course of the project, the contract price increased to

$9,460,969.42. Under the terms of the agreement, periodic payments were due for

completed work and materials, but Main Event had the contractual right to withhold

10 percent of all payments as a “retainage.”1 Main Event’s lease agreement with

National Retail obligated Main Event to fund and manage the construction project.

The two companies, although separate entities, were related enterprises.

1 “Retainage” is the withholding of a portion of the periodic or final payments designed to permit the owner the opportunity to ensure that the contractor or subcontractor has completed the project correctly and is considered a standard practice in the construction industry. Liberty Excavating, Inc. v. Welty Bldg. Co., 9th Dist. Summit No. 21807, 2004-Ohio-4873, ¶ 11; Gillard v. Green, 4th Dist. Washington No. 00CA54, 2001-Ohio-2644, 20, fn. 12. Omni subcontracted concrete work necessary to the project to

Sterling. Sterling’s contract was entered solely as between it and Omni. Omni

agreed to pay Sterling $745,000 in the initial contract, and $32,978.70 through

approved change orders. Omni paid, and Sterling received, $663,255 over the

course of the project. Through Main Event’s retainage, which Omni withheld from

Sterling, and the outstanding balance on the change orders, Omni owed Sterling

$114,723.70 after Sterling completed its work. That amount was never paid.

Disputes between Omni and Main Event arose with respect to the lack

of work being performed and delays in the project schedule. Omni walked off the

project in the beginning of July 2018, almost a full year after the parties agreed to

the 220-day project. After breaching its contract with Main Event, Omni failed to

pay several subcontractors.

Before defaulting under the terms of the construction contract, Main

Event paid Omni $7,631,846.12. Between the retainage and the residual for the

unpaid portion of the contract, Main Event retained $1,829,123.30 of cash and

value. Thirty mechanic’s liens were filed by other subcontractors after Omni

breached the construction contract and failed to pay the subcontractors for their

completed work. In total, Main Event issued payments to resolve the liens in an

amount totaling $2,030,244.10, well exceeding the retainage amount. After

incurring additional costs related to finalizing the construction project, Main Event’s

final payments exceeded the construction contract price by $288,256.85. Sterling did not file a mechanic’s lien. After, or while, Main Event

resolved the mechanic’s liens filed against the lessee’s interest in the property,

Sterling initiated a breach of contract action against Omni and included equitable

claims against Main Event and National Retail for unjust enrichment based on the

work Sterling performed for Omni. Omni predictably defaulted in answer, and

Sterling obtained a judgment in its favor against Omni for the $114,723.70 balance

owed under Sterling and Omni’s contract.

Nothing in the record directly demonstrates Omni’s inability to

satisfy the judgment. According to Sterling, the inability to satisfy the judgment is

demonstrated by the fact that the sole owner of Omni, Richard Stone, filed a

personal bankruptcy action in federal court. In that petition, Stone alleged himself

to be the sole owner of Omni, which had no monetary value. Sterling, Main Event,

and National Retail were listed as unsecured creditors by Stone. We have no other

information regarding Stone’s personal bankruptcy action that impacts Omni’s

solvency.

In the trial court proceedings, Sterling, Main Event, and National

Retail all agreed the matter could be resolved under Civ.R. 56. Both sides filed

motions for summary judgment claiming that application of equitable legal

principles to the undisputed facts necessitated judgment in their respective favor.

Sterling claimed entitlement to compensation based on the benefit conferred upon

Main Event, and the defendants claimed that the benefit had not been unjustly

retained in light of the expenditures necessary to complete Omni’s work and the exhaustion of the retainage funds. The trial court ultimately agreed with Main Event

and National Retail and granted judgment in their favor upon all claims. Sterling’s

judgment against Omni was not affected by that decision. This appeal timely

followed.

Summary judgment rulings are reviewed de novo, and appellate

courts apply the same standard as the trial court. Grafton v. Ohio Edison Co., 77

Ohio St.3d 102, 105, 671 N.E.2d 241 (1996). Review of summary judgment is

governed by the standard set forth in Civ.R. 56. Argabrite v. Neer, 149 Ohio St.3d

349, 2016-Ohio-8374, 75 N.E.3d 161, ¶ 14. Summary judgment is appropriate only

when “[1] no genuine issue of material fact remains to be litigated, [2] the moving

party is entitled to judgment as a matter of law, and [3] viewing the evidence in the

light most favorable to the nonmoving party, reasonable minds can reach a

conclusion only in favor of the moving party.” Id., citing M.H. v. Cuyahoga Falls,

134 Ohio St.3d 65, 2012-Ohio-5336, 979 N.E.2d 1261, ¶ 12. Appellate courts provide

no deference to the trial court’s decision and independently review the record to

determine whether summary judgment is appropriate.

On a motion for summary judgment, the moving party carries an

initial burden of identifying specific facts in the record that establish his or her

entitlement to summary judgment. Dresher v. Burt, 75 Ohio St.3d 280, 292-293,

662 N.E.2d 264 (1996). If the moving party fails to meet this burden, summary

judgment is not appropriate; if the moving party meets this burden, the nonmoving

party must then point to evidence of specific facts in the record demonstrating the existence of a genuine issue of material fact for trial. Id. at 293. If the nonmoving

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Figgie v. Figgie
2025 Ohio 451 (Ohio Court of Appeals, 2025)
Bavaria v. Ohio State Univ.
2024 Ohio 3217 (Ohio Court of Claims, 2024)
VMI Group, Inc. v. Capstone Constr. Co., L.L.C.
2023 Ohio 3882 (Ohio Court of Appeals, 2023)
Almasoodi v. J. Harris Constr. Inc.
2023 Ohio 895 (Ohio Court of Appeals, 2023)
Ferguson v. Univ. Hosp. Health Sys., Inc.
2022 Ohio 3133 (Ohio Court of Appeals, 2022)

Cite This Page — Counsel Stack

Bluebook (online)
2022 Ohio 2138, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sterling-contracting-llc-v-main-event-entertainment-lp-ohioctapp-2022.