Meridien Marketing Group, Inc. v. J&E Bldg. Group, Inc.

2011 Ohio 4872
CourtOhio Court of Appeals
DecidedSeptember 23, 2011
Docket2011-CA-02
StatusPublished
Cited by8 cases

This text of 2011 Ohio 4872 (Meridien Marketing Group, Inc. v. J&E Bldg. Group, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Meridien Marketing Group, Inc. v. J&E Bldg. Group, Inc., 2011 Ohio 4872 (Ohio Ct. App. 2011).

Opinion

[Cite as Meridien Marketing Group, Inc. v. J&E Bldg. Group, Inc., 2011-Ohio-4872.]

IN THE COURT OF APPEALS OF OHIO SECOND APPELLATE DISTRICT MIAMI COUNTY

MERIDIEN MARKETING GROUP, INC. : dba MERIDIEN STONE : Appellate Case No. 2011-CA-02 : Plaintiff-Appellee : Trial Court Case No. 09-CV-948 : v. : : (Civil Appeal from J&E BUILDING GROUP, INC., et al. : (Common Pleas Court) : Defendant-Appellant : : ...........

OPINION

Rendered on the 23rd day of September, 2011.

.........

JOSE M. LOPEZ, Atty. Reg. #0019580, and JONATHAN S. ZWEIZIG, Atty. Reg. #0069381, Lopez, Severt & Pratt Co., L.P.A., 18 East Water Street, Troy, Ohio 45373 Attorneys for Plaintiff-Appellee

BRYAN K. STEWART, Atty. Reg. #0042122, Stewart & Stewart Lawyers, Ltd., 104 West Main Street, Tipp City, Ohio 45371 Attorney for Defendant-Appellant

HALL, J.

{¶ 1} Defendant-appellant UKP LLC hired defendant J&E Building Group, Inc., to

build a hotel in Troy, Ohio. UKP agreed to pay J&E $4,447,942 but, because of problems

with the construction, ended up paying about $20,000 less. Under the construction 2

specifications, J&E was to install (among other things) custom-designed wood vanity-bases

for sleeping room baths and custom-designed granite pieces, which included vanity

countertops and public-area countertops, window sills, and sleeping-room shelves. J&E

selected plaintiff-appellee Meridien Stone to supply the vanity bases and granite pieces and

agreed to pay $63,579.49. J&E paid Meridien a $29,820.18 pre-delivery deposit. On delivery

day, J&E gave Meridien a check for the balance. But problems with the order were

immediately discovered–twenty-four shelves were broken, three sills were the wrong color,

three countertops were not polished, and one countertop was missing. That same day, UKP’s

managing member, Upendra Patel, sent an email to the bank that asked it to stop payment on

the check J&E had given Meridien “IMMEDIATELY,” explaining, “Granite came in today

and many of the pieces are broken and we need to work this out before ANY further payment

is issued them.” (Plaintiff’s Exhibit 5). Meridien did not dispute the problems, and it credited

J&E $1,332.71 for the broken granite and wrong-colored sills and did not charge it for the

missing countertop. After the adjustments were made, J&E owed Meridien $32,426.61. But

J&E did not give Meridien another check, nor did Patel ask the bank to lift the stop-payment

order on the one it had given Meridien.

{¶ 2} At some point not long after building the hotel, J&E went out of business.

When Meridien’s president, David Murray, spoke with Elenora Vaughn, J&E’s president,

about resolving the payment issue, she told him that J&E was no longer in business. She said

that she, her husband (J&E’s vice president), and son Jeff had moved to Florida. Elenora

explained that they had put around $640,000 of their own money into the business before they

lost it. Elenora told Murray that the bank had taken everything and J&E had no money–no 3

money to pay Meridien or to pay an attorney. J&E’s site supervisor, Jeff Vaughn, sent Patel an

email which said essentially the same thing that Elenora told Murry: banks held J&E’s assets

and J&E had no money to pay an attorney to contest any legal claims.

{¶ 3} On October 8, 2009, Meridien filed suit against J&E and UKP, seeking to

recover the amount it was owed. Meridien asserted a breach-of-contract claim against J&E

and, alternatively, a claim for unjust enrichment against UKP. J&E did not respond and did

not file an appearance. The case went to a bench trial solely on the unjust-enrichment claim.

The trial court found that J&E is insolvent and unavailable for judgment, and the court

ordered UKP to pay Meridien the full amount J&E still owed, finding that this amount is both

the reasonable value of the material Meridien provided and the value of the benefit UKP

received.

{¶ 4} UKP appealed and now assigns two errors to the trial court. In the first, UKP

argues that the trial court should have dismissed the unjust-enrichment claim because

Meridien failed to present admissible evidence that J&E is insolvent and unavailable for

judgment. Alternatively, in the second assignment of error, UKP argues that the amount the

court ordered it to pay Meridien is unlawful because it exceeds the unpaid balance of UKP’s

contract with J&E and because it includes Meridien’s profit.

1. UKP’s Liability to Meridien

{¶ 5} A subcontractor may not assert an unjust-enrichment claim against a property

owner if the possibility exists that, for the same work or material supplied, the subcontractor

can also recover from the contractor or the property owner might also have to pay the 4

contractor. Booher Carpet Sales, Inc. v. Erickson (Oct. 2, 1998), Greene App. No.

98-CA-0007; BFI Waste Systems of Ohio, Inc. v. Professional Constr. and Safety Servs., Inc.,

Lorain App. No. 06CA008972, 2008-Ohio-1450, at ¶7, quoting Booher. In other words, no

danger may exist of double recovery or double payment. To ensure that neither danger does

exist, “[w]hen a subcontractor is pursuing an action against a property owner it is necessary

that the general contractor be unavailable for judgment and unable to pursue the owner for the

money that the subcontractor is seeking.” Booher; BFI Waste Systems, at ¶7.

{¶ 6} UKP argues that the trial court erred when it concluded that neither danger

exists in this case. 1 Meridien presented sufficient evidence that J&E is insolvent and

unavailable for judgment. In fact, UKP contends, the evidence supports the contrary.

{¶ 7} The evidentiary standard in civil cases is this: “a judgment supported by some

competent, credible evidence going to all the essential elements of the case must be affirmed.”

State v. Wilson, 113 Ohio St.3d 382, 2007-Ohio-2202, at ¶26 (Citation omitted.). We

conclude that competent, credible evidence supports the trial court’s finding.

1 The first assignment of error assigns error to the trial court’s failure to dismiss Meridien’s unjust enrichment claim. Before presenting its defense, UKP orally moved “to dismiss or [] for a directed verdict,” asserting that Meridien failed to prove that J&E is unavailable for judgment. (Tr. 128). As Meridien argues in its brief, and UKP concedes in reply, “[a] motion for directed verdict is inappropriate in a bench trial.” Miami Valley Hospital v. Payson (Dec. 7, 2001), Montgomery App. No. 18736 (Citation omitted.). Such a motion made in a non-jury trial is construed as a motion for involuntary dismissal under Civ.R. 41(B). Id. Civ.R. 41(B)(2) provides that “when a motion to dismiss is made, the trial court can choose either to dismiss the action or to proceed with further evidence,” so a court that chooses the later path does not err. Pacher v. Invisible Fence of Dayton, 154 Ohio App.3d 744, 2003-Ohio-5333, at ¶34. In the present case, the trial court overruled UKP’s motion, choosing instead to hear its evidence. The court did not err by doing so. On page one of its reply brief, UKP says that “the trial court did make an incorrect finding upon consideration of the evidence presented with respect to Appellee proving that the general contractor, J&E Building group [sic], was not collectible.” UKP argues that Meridien presented no evidence that J&E is unavailable for judgment. Therefore we consider the sufficiency of the evidence supporting the trial court’s unavailability finding. See id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

VMI Group, Inc. v. Capstone Constr. Co., L.L.C.
2023 Ohio 3882 (Ohio Court of Appeals, 2023)
Almasoodi v. J. Harris Constr. Inc.
2023 Ohio 895 (Ohio Court of Appeals, 2023)
Sterling Contracting, L.L.C. v. Main Event Entertainment, L.P.
2022 Ohio 2138 (Ohio Court of Appeals, 2022)
Moosehead v. Eureka
2019 Ohio 3961 (Ohio Court of Appeals, 2019)
Acme Co. v. Saunders TopSoil
2011 Ohio 6423 (Ohio Court of Appeals, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
2011 Ohio 4872, Counsel Stack Legal Research, https://law.counselstack.com/opinion/meridien-marketing-group-inc-v-je-bldg-group-inc-ohioctapp-2011.