Moosehead v. Eureka

2019 Ohio 3961
Ohio Court of Appeals·Decided September 30, 2019·No. 18 MO 0015·Published·Cited by 3 cases

Opinion

IN THE COURT OF APPEALS OF OHIO SEVENTH APPELLATE DISTRICT MONROE COUNTY

MOOSEHEAD HARVESTING, INC.

Plaintiff-Appellant,

v.

EUREKA MIDSTREAM, LLC f/k/a EUREKA HUNTER PIPELINE, LLC

Defendant-Appellee.

OPINION AND JUDGMENT ENTRY Case No. 18 MO 0015

Civil Appeal from the

Court of Common Pleas of Monroe County, Ohio Case No. 2016-299

BEFORE:

Cheryl L. Waite, Carol Ann Robb, David A. D’Apolito, Judges.

JUDGMENT:

Affirmed in part. Reversed and Remanded in part.

Atty. R. Russell O'Rourke, Atty. R. Scott Heasley, Meyers, Roman, Friedberg & Lewis, 28601 Chagrin Blvd., Suite 600, Cleveland, Ohio 44122, for Plaintiff-Appellant.

Atty. Ramonda C. Marling, Lewis Glasser PLLC, 300 Summers Street, Suite 700, Charleston, West Virginia 25301, for Defendant-Appellee.

Dated: September 30, 2019

WAITE, P.J.

{¶1} Appellant Moosehead Harvesting, Inc. (“Moosehead”) appeals an August 16, 2018 Monroe County Court of Common Pleas decision to grant summary judgment in favor of Appellee Eureka Midstream, L.L.C. (“Eureka”). Moosehead argues that Eureka was unjustly enriched by clearing and excavation work completed by Moosehead for which Moosehead was not paid. For the reasons provided, Moosehead’s arguments have merit in part. Accordingly, the judgment of the trial court is reversed only as to the distribution of retainage money, but affirmed as to the determination that Moosehead was not entitled to the full value of its contract. The matter is remanded for a limited hearing to determine how much of the retainage money Moosehead is entitled to.

Factual and Procedural History

{¶2} Eureka planned to build a natural gas pipeline, referred to as the “Bobcat and Jaws Pipeline” (“pipeline”). To install the pipeline, Eureka hired Carl Smith Pipeline Energy Group, Inc. (“CSP”). The agreement between Eureka and CSP was the “prime contract.” Under the terms of the contract, Eureka was to pay CSP $12,000,000 for installation of the pipeline. However, at some point CSP agreed to give Eureka discounts, which lowered its invoice amounts, in exchange for early payments from Eureka. The prime contract allowed Eureka to withhold ten percent of each invoice as retainage.

{¶3} The pipeline could not be installed until a right-of-way was cleared. CSP hired Moosehead as its subcontractor to perform the necessary excavation and to clear the right-of-way. The CSP/Moosehead subcontract provided that Moosehead was to be paid $808,538.15 so long as its work was timely completed.

{¶4} Moosehead began work on June 15, 2015 and finished on July 14, 2015, which was timely under the contract. Both Eureka and CSP approved Moosehead’s work. Moosehead submitted an invoice in the amount of the agreed price, $808,538.15. However, CSP paid Moosehead only $125,000, fifteen percent of the total amount due. Moosehead contacted CSP to inquire about the outstanding balance and CSP told Moosehead that Eureka had been slow in remitting payments to CSP, which resulted in the delay of complete payment to Moosehead. However, when Moosehead contacted Eureka about its payment, Eureka claimed that a check for the total amount had already been paid to CSP.

{¶5} On September 18, 2015, Robert Reed of Moosehead called an official at Eureka and requested the remainder of the outstanding balance. On October 9, 2015, Moosehead’s counsel sent a letter to Eureka requesting that future payments to CSP be withheld until the outstanding balance to Moosehead was satisfied. Eureka then sent a letter to CSP stating its intent to withhold future payments until CSP obtained a lien waiver from Moosehead. CSP did not obtain any wavier and Eureka began withholding CSP’s payments.

{¶6} At some point, Eureka penalized CSP $1.3 million for failing to complete the project on time pursuant to the terms of their prime contract. It is unclear whether Eureka received payment of the penalty amount from CSP. On February 5, 2016, CSP filed a voluntary Chapter 7 Bankruptcy Petition in the United States Bankruptcy Court for the Middle District of Tennessee. The bankruptcy court initially placed a stay on the available retainage money, which amounted to $484,114.78. The bankruptcy court ultimately lifted the stay and permitted Eureka to distribute these funds. Using the retainage, Eureka paid

the following vendors: Henderson’s GreenPro ($321,129.50), Bare Fencing ($10,000), J&J Timber ($15,000), and Iron Eagle Enterprises ($60,000). The total amount paid to these vendors was $406,129.50. According to an affidavit from Eureka representative Charles D. King, Eureka kept the remaining $77,985.28 as compensation to Eureka for losses suffered as a result of CSP’s failure to timely complete the project. At oral argument, Eureka confirmed that it kept the remainder of the retainage money and used the money to offset costs it incurred in hiring a new contractor to complete the project.

{¶7} On September 19, 2016, Moosehead filed a “complaint for foreclosure of mechanic’s lien and unjust enrichment” against Eureka, EM Energy Ohio L.L.C., EM Energy Midstream L.L.C., and EM Employer L.L.C. It appears that the codefendants are subsidiaries of Eureka. Count one of the complaint alleged that Eureka had been unjustly enriched by the completion of Moosehead’s clearing and excavation work without payment. The second claim sought foreclosure of a mechanic’s lien. On November 4, 2016, Eureka filed a response to the complaint and counterclaimed for breach of contract.

{¶8} On June 1, 2017, the trial court denied Eureka’s motion to dismiss the unjust enrichment claim. On August 15, 2017, the trial court denied a second such motion. On May 2, 2018, the trial court denied Moosehead’s request to amend the complaint to add a breach of contract claim. In July of 2018, pursuant to an agreement by the parties, Moosehead dismissed the claim involving a mechanic’s lien and Eureka withdrew its counterclaim.

{¶9} On July 3, 2018, Eureka filed a motion for summary judgment on the unjust enrichment claim, the sole remaining count of the complaint. Moosehead did not file a competing motion for summary judgment. On August 16, 2018, the trial court granted

Eureka’s motion for summary judgment. It is from this entry that Moosehead timely appeals.

ASSIGNMENT OF ERROR

THE TRIAL COURT ERRED AS A MATTER OF LAW IN GRANTING DEFENDANT'S MOTION FOR SUMMARY JUDGMENT AS GENUINE ISSUES OF MATERIAL FACT RELEVANT TO THE DISPUTE REMAINED.

{¶10} Moosehead generally argues that it is entitled to receive the full unpaid contract price from Eureka, as Eureka was unjustly enriched by Moosehead’s completion of clearing and excavation work, the prerequisite for Eureka to begin work on the pipeline. Although Eureka benefitted from the completion of Moosehead’s work, it made no attempt to compensate Moosehead even though Eureka had money available due to the retainage, discounts, and penalty clause payment. Moosehead also argues that Eureka used retainage money to pay other unpaid subcontractors but ignored the outstanding claim by Moosehead. Additionally, Moosehead argues that Eureka improperly entered into side deals, where CSP agreed to reduce invoice amounts (presumably including the Moosehead invoice) in exchange for early payments.

{¶11} Eureka responds that the Moosehead contract included a waiver of lien, meaning that Moosehead could not place a lien on either CSP or Eureka. Hence, Eureka believes that Moosehead is not entitled to any portion of the retainage money, which it claims is reserved only for lienholders. Eureka cites to several cases from Ohio appellate courts which have held that once payment is made to a contractor, the subcontractor cannot collect from the owner. See Wickford Metal Products v. Tri-Valley Church, 5th

Free access — add to your briefcase to read the full text and ask questions with AI

Moosehead v. Eureka, 2019 Ohio 3961 (Ohio Ct. App. 2019).

2019 Ohio 3961 (Moosehead v. Eureka) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

VMI Group, Inc. v. Capstone Constr. Co., L.L.C.
2023 Ohio 3882 (Ohio Court of Appeals, 2023)
Almasoodi v. J. Harris Constr. Inc.
2023 Ohio 895 (Ohio Court of Appeals, 2023)
Sterling Contracting, L.L.C. v. Main Event Entertainment, L.P.
2022 Ohio 2138 (Ohio Court of Appeals, 2022)