Moosehead v. Eureka

2019 Ohio 3961
CourtOhio Court of Appeals
DecidedSeptember 30, 2019
Docket18 MO 0015
StatusPublished
Cited by3 cases

This text of 2019 Ohio 3961 (Moosehead v. Eureka) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moosehead v. Eureka, 2019 Ohio 3961 (Ohio Ct. App. 2019).

Opinion

[Cite as Moosehead v. Eureka, 2019-Ohio-3961.]

IN THE COURT OF APPEALS OF OHIO SEVENTH APPELLATE DISTRICT MONROE COUNTY

MOOSEHEAD HARVESTING, INC.

Plaintiff-Appellant,

v.

EUREKA MIDSTREAM, LLC f/k/a EUREKA HUNTER PIPELINE, LLC

Defendant-Appellee.

OPINION AND JUDGMENT ENTRY Case No. 18 MO 0015

Civil Appeal from the Court of Common Pleas of Monroe County, Ohio Case No. 2016-299

BEFORE: Cheryl L. Waite, Carol Ann Robb, David A. D’Apolito, Judges.

JUDGMENT: Affirmed in part. Reversed and Remanded in part.

Atty. R. Russell O'Rourke, Atty. R. Scott Heasley, Meyers, Roman, Friedberg & Lewis, 28601 Chagrin Blvd., Suite 600, Cleveland, Ohio 44122, for Plaintiff-Appellant.

Atty. Ramonda C. Marling, Lewis Glasser PLLC, 300 Summers Street, Suite 700, Charleston, West Virginia 25301, for Defendant-Appellee. –2–

Dated: September 30, 2019

WAITE, P.J.

{¶1} Appellant Moosehead Harvesting, Inc. (“Moosehead”) appeals an August

16, 2018 Monroe County Court of Common Pleas decision to grant summary judgment

in favor of Appellee Eureka Midstream, L.L.C. (“Eureka”). Moosehead argues that Eureka

was unjustly enriched by clearing and excavation work completed by Moosehead for

which Moosehead was not paid. For the reasons provided, Moosehead’s arguments

have merit in part. Accordingly, the judgment of the trial court is reversed only as to the

distribution of retainage money, but affirmed as to the determination that Moosehead was

not entitled to the full value of its contract. The matter is remanded for a limited hearing

to determine how much of the retainage money Moosehead is entitled to.

Factual and Procedural History

{¶2} Eureka planned to build a natural gas pipeline, referred to as the “Bobcat

and Jaws Pipeline” (“pipeline”). To install the pipeline, Eureka hired Carl Smith Pipeline

Energy Group, Inc. (“CSP”). The agreement between Eureka and CSP was the “prime

contract.” Under the terms of the contract, Eureka was to pay CSP $12,000,000 for

installation of the pipeline. However, at some point CSP agreed to give Eureka discounts,

which lowered its invoice amounts, in exchange for early payments from Eureka. The

prime contract allowed Eureka to withhold ten percent of each invoice as retainage.

{¶3} The pipeline could not be installed until a right-of-way was cleared. CSP

hired Moosehead as its subcontractor to perform the necessary excavation and to clear

the right-of-way. The CSP/Moosehead subcontract provided that Moosehead was to be

paid $808,538.15 so long as its work was timely completed.

Case No. 18 MO 0015 –3–

{¶4} Moosehead began work on June 15, 2015 and finished on July 14, 2015,

which was timely under the contract. Both Eureka and CSP approved Moosehead’s work.

Moosehead submitted an invoice in the amount of the agreed price, $808,538.15.

However, CSP paid Moosehead only $125,000, fifteen percent of the total amount due.

Moosehead contacted CSP to inquire about the outstanding balance and CSP told

Moosehead that Eureka had been slow in remitting payments to CSP, which resulted in

the delay of complete payment to Moosehead. However, when Moosehead contacted

Eureka about its payment, Eureka claimed that a check for the total amount had already

been paid to CSP.

{¶5} On September 18, 2015, Robert Reed of Moosehead called an official at

Eureka and requested the remainder of the outstanding balance. On October 9, 2015,

Moosehead’s counsel sent a letter to Eureka requesting that future payments to CSP be

withheld until the outstanding balance to Moosehead was satisfied. Eureka then sent a

letter to CSP stating its intent to withhold future payments until CSP obtained a lien waiver

from Moosehead. CSP did not obtain any wavier and Eureka began withholding CSP’s

payments.

{¶6} At some point, Eureka penalized CSP $1.3 million for failing to complete the

project on time pursuant to the terms of their prime contract. It is unclear whether Eureka

received payment of the penalty amount from CSP. On February 5, 2016, CSP filed a

voluntary Chapter 7 Bankruptcy Petition in the United States Bankruptcy Court for the

Middle District of Tennessee. The bankruptcy court initially placed a stay on the available

retainage money, which amounted to $484,114.78. The bankruptcy court ultimately lifted

the stay and permitted Eureka to distribute these funds. Using the retainage, Eureka paid

Case No. 18 MO 0015 –4–

the following vendors: Henderson’s GreenPro ($321,129.50), Bare Fencing ($10,000),

J&J Timber ($15,000), and Iron Eagle Enterprises ($60,000). The total amount paid to

these vendors was $406,129.50. According to an affidavit from Eureka representative

Charles D. King, Eureka kept the remaining $77,985.28 as compensation to Eureka for

losses suffered as a result of CSP’s failure to timely complete the project. At oral

argument, Eureka confirmed that it kept the remainder of the retainage money and used

the money to offset costs it incurred in hiring a new contractor to complete the project.

{¶7} On September 19, 2016, Moosehead filed a “complaint for foreclosure of

mechanic’s lien and unjust enrichment” against Eureka, EM Energy Ohio L.L.C., EM

Energy Midstream L.L.C., and EM Employer L.L.C. It appears that the codefendants are

subsidiaries of Eureka. Count one of the complaint alleged that Eureka had been unjustly

enriched by the completion of Moosehead’s clearing and excavation work without

payment. The second claim sought foreclosure of a mechanic’s lien. On November 4,

2016, Eureka filed a response to the complaint and counterclaimed for breach of contract.

{¶8} On June 1, 2017, the trial court denied Eureka’s motion to dismiss the unjust

enrichment claim. On August 15, 2017, the trial court denied a second such motion. On

May 2, 2018, the trial court denied Moosehead’s request to amend the complaint to add

a breach of contract claim. In July of 2018, pursuant to an agreement by the parties,

Moosehead dismissed the claim involving a mechanic’s lien and Eureka withdrew its

counterclaim.

{¶9} On July 3, 2018, Eureka filed a motion for summary judgment on the unjust

enrichment claim, the sole remaining count of the complaint. Moosehead did not file a

competing motion for summary judgment. On August 16, 2018, the trial court granted

Case No. 18 MO 0015 –5–

Eureka’s motion for summary judgment. It is from this entry that Moosehead timely

appeals.

ASSIGNMENT OF ERROR

THE TRIAL COURT ERRED AS A MATTER OF LAW IN GRANTING

DEFENDANT'S MOTION FOR SUMMARY JUDGMENT AS GENUINE

ISSUES OF MATERIAL FACT RELEVANT TO THE DISPUTE REMAINED.

{¶10} Moosehead generally argues that it is entitled to receive the full unpaid

contract price from Eureka, as Eureka was unjustly enriched by Moosehead’s completion

of clearing and excavation work, the prerequisite for Eureka to begin work on the pipeline.

Although Eureka benefitted from the completion of Moosehead’s work, it made no attempt

to compensate Moosehead even though Eureka had money available due to the

retainage, discounts, and penalty clause payment. Moosehead also argues that Eureka

used retainage money to pay other unpaid subcontractors but ignored the outstanding

claim by Moosehead. Additionally, Moosehead argues that Eureka improperly entered

into side deals, where CSP agreed to reduce invoice amounts (presumably including the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

VMI Group, Inc. v. Capstone Constr. Co., L.L.C.
2023 Ohio 3882 (Ohio Court of Appeals, 2023)
Almasoodi v. J. Harris Constr. Inc.
2023 Ohio 895 (Ohio Court of Appeals, 2023)
Sterling Contracting, L.L.C. v. Main Event Entertainment, L.P.
2022 Ohio 2138 (Ohio Court of Appeals, 2022)

Cite This Page — Counsel Stack

Bluebook (online)
2019 Ohio 3961, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moosehead-v-eureka-ohioctapp-2019.