E.S. Wagner Company v. Plant Process Equipment Inc.

CourtDistrict Court, N.D. Ohio
DecidedMarch 31, 2021
Docket3:19-cv-01759
StatusUnknown

This text of E.S. Wagner Company v. Plant Process Equipment Inc. (E.S. Wagner Company v. Plant Process Equipment Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Ohio primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
E.S. Wagner Company v. Plant Process Equipment Inc., (N.D. Ohio 2021).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE NORTHERN DISTRICT OF OHIO WESTERN DIVISION

E.S. WAGNER CO., CASE NO. 3:19 CV 1759

Plaintiff,

v. JUDGE JAMES R. KNEPP II

PLANT PROCESS EQUIPMENT INC., et al., MEMORANDUM OPINION Defendants. AND ORDER

INTRODUCTION On August 2, 2019, E.S. Wagner Company (“ESW”) brought this action asserting two claims of breach of contract (Counts One and Two) and a single count of unjust enrichment (Count Three) against Defendant Plant Process Equipment, Incorporated (“PPE”). (Doc. 1). Against Defendant Alpont, LLC (“Alpont”), ESW asserts a single breach of contract claim (Count Two) and an unjust enrichment claim (Count Three). Id. The Court has jurisdiction pursuant to 28 U.S.C. § 1332. Currently pending before the Court is Alpont’s Motion for Summary Judgment (Doc. 31), to which ESW responded (Doc. 42), and Alpont replied (Doc. 49). For the following reasons, Alpont’s Motion for Summary Judgment is granted as to Count Two and denied as to Count Three. BACKGROUND Viewing the facts in the light most favorable to Plaintiff, the background of this case is as follows: This dispute arose from the construction of a manufacturing facility in Oregon, Ohio owned by Alpont. (Doc. 1, at ¶8). In September 2015, Alpont contracted with PPE for the design and building of a sodium methylate plant. (Razzano Depo., Doc. 45, at 16). In December 2015, PPE and Alpont entered into a second agreement to add a methanol plant to the project. Id. at 16-18. Alpont expected PPE, as the general contractor, to design and build the plants for a set price as a turnkey project. Id. at 26. In August 2017, ESW entered into a Master Services Agreement (“MSA”) with PPE to

provide site development, earth work, and civil and foundation construction. (Doc. 1, at ¶9). By this time, the total cost of the project was significantly higher than originally agreed between Alpont and PPE for several reasons, including relocating the plant from Pennsylvania to Ohio, changes in scope of work, and changes in materials costs resulting from delays. See Borg Depo., Doc. 46, at 40-41; BuPane Depo., Doc. 47, at 26; Razzano Depo. at 30-31. To cover these additional costs Alpont agreed to change orders issued by PPE. (Borg Depo. at 30-31; Adams Depo., Doc. 48, at 30-32). ESW proceeded with its work on the plant site and was paid directly by PPE for its first nine payment applications. (Doc. 1, at ¶11). However, as the project progressed PPE ran out of

money and stopped paying suppliers and subcontractors, including ESW. (Borg Depo. at 67-68; BuPane Depo. at 21-22). ESW informed PPE and Alpont it could not continue work unless full payment was made. (Razzano Depo. at 49-50; Borg Depo. at 74-75). To keep the project moving and workers on site, Alpont began paying on subcontracts directly. (Razzano Depo. at 32; BuPane Depo. at 28, 31, 40-41; Adams Depo. at 56, 70-72). Over the next few months, Alpont paid ESW for three consecutive payment applications. (Razzano Depo. at 49-56; BuPane Depo. at 44-48). ESW continued to work on the project. (Borg Depo. at 78-79; Adams Depo. at 72). Around December 13, 2018, ESW submitted a payment application covering most of the final work on the job, apart from some change orders and minor work to be completed in the spring (Moser Affidavit, Doc. 43, at ¶3); both PPE and Alpont refused payment (Razzano Depo. at 57- 58; BuPane Depo. at 48-49). The total balance owed to ESW at the time of this last payment application was $586,122.50. (Moser Affidavit, Doc. 43, at ¶3). Thereafter, ESW submitted change orders, for work already approved by PPE and completed by ESW, for an additional $286,481.41. Id. at ¶¶5-7. To date, ESW remains unpaid. (Doc. 1, at ¶15).

STANDARD OF REVIEW

Summary judgment is appropriate where there is “no genuine issue as to any material fact” and “the moving party is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(c). When considering a motion for summary judgment, the Court must draw all inferences from the record in the light most favorable to the nonmoving party. Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 587 (1986). The court is not permitted to weigh the evidence or determine the truth of any matter in dispute; rather, the court determines only whether the case contains sufficient evidence from which a jury could reasonably find for the nonmoving party. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248-49 (1986). The moving party bears the burden of proof. Celotex Corp. v. Catrett, 477 U.S. 317, 325 (1986). This burden “may be discharged by ‘showing’—that is, pointing out to the district court— that there is an absence of evidence to support the nonmoving party’s case.” Id. Thereafter, the nonmoving party has an affirmative duty to direct the court’s attention to those specific portions of the record upon which create a genuine issue of material fact. See Fed. R. Civ. P. 56(c)(3) (noting that the court “need consider only the cited materials”); see also Street v. J.C. Bradford & Co., 886 F.2d 1472, 1479 (6th Cir. 1989) (a court “no longer has a duty to search the entire record to establish that it is bereft of a genuine issue of material fact.”). “Instead, when the non-movant has failed to point out a question of fact on an issue, a district court’s ‘reliance on the facts advanced by the movant is proper and sufficient.’” Wardle v. Lexington-Fayette Urban Cty. Gov’t, 45 F. App’x 505, 509 (6th Cir. 2002) (quoting Guarino v. Brookfield Twp. Trs., 980 F.2d 399, 404 (6th Cir. 1992)). DISCUSSION Alpont moved for summary judgment on ESW’s breach of contract (Count Two) and unjust

enrichment (Count Three) claims. (Doc. 31). For the following reasons, the Court grants the motion as to Count Two and denies the motion as to Count Three. Breach of Contract ESW’s breach of contract claim is an action on an account; this is “appropriate where the parties have conducted a series of transactions for which a balance remains to be paid.” Taylor Steel, Inc. v. Keeton, 417 F.3d 598, 604 (6th Cir. 2005). To succeed in an action on an account ESW must establish the existence of a contract with Alpont. Id. But ESW fails to show either an express or implied contract between it and Alpont, nor does it raise a genuine issue of material fact as to the contract’s existence.

“The general rule is that, absent an agreement otherwise, there is no privity of contract between a property owner and subcontractor.” G.R. Osterland Co. v. Cleveland, 748 N.E.2d 576, 578 (Ohio Ct. App. 2000). The only written agreement to which ESW draws the Court’s attention is the MSA. Yet, Alpont is never mentioned in the MSA. (Doc. 45-1, at 1-6). All the obligations of the MSA exist solely between PPE and ESW. Id. There is no provision identifying or setting out the rights of a third-party beneficiary. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Taylor Steel, Inc. v. Lana C. Keeton
417 F.3d 598 (Sixth Circuit, 2005)
Sobh v. American Family Insurance Co.
755 F. Supp. 2d 852 (N.D. Ohio, 2010)
Meridien Marketing Group, Inc. v. J&E Bldg. Group, Inc.
2011 Ohio 4872 (Ohio Court of Appeals, 2011)
Coyne v. Hodge Constr., Inc., Unpublished Decision (2-18-2004)
2004 Ohio 727 (Ohio Court of Appeals, 2004)
Cooper & Pachell v. Haslage
756 N.E.2d 1248 (Ohio Court of Appeals, 2001)
G.R. Osterland Co. v. City of Cleveland
748 N.E.2d 576 (Ohio Court of Appeals, 2000)
Wardle v. Lexington-Fayette Urban County Government
45 F. App'x 505 (Sixth Circuit, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
E.S. Wagner Company v. Plant Process Equipment Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/es-wagner-company-v-plant-process-equipment-inc-ohnd-2021.