Liberty Excavating v. Welty Bldg Co., Ltd., Unpublished Decision (9-15-2004)

2004 Ohio 4873
CourtOhio Court of Appeals
DecidedSeptember 15, 2004
DocketC.A. No. 21807.
StatusUnpublished
Cited by3 cases

This text of 2004 Ohio 4873 (Liberty Excavating v. Welty Bldg Co., Ltd., Unpublished Decision (9-15-2004)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Liberty Excavating v. Welty Bldg Co., Ltd., Unpublished Decision (9-15-2004), 2004 Ohio 4873 (Ohio Ct. App. 2004).

Opinion

DECISION AND JOURNAL ENTRY
{¶ 1} Plaintiff-Appellant/Cross-Appellee Liberty Excavating, Inc. has appealed from a decision of the Summit County Court of Common Pleas that entered judgment in favor of Defendant-Appellee/Cross-Appellant Welty Building Company, Ltd. on its counterclaim. Defendant-Appellee/Cross-Appellant Welty Building Company, Ltd. has filed a cross appeal. This Court affirms in part, and reverses in part.

I
{¶ 2} On November 2, 2001, Plaintiff-Appellant Liberty Excavating, Inc. ("Liberty") filed suit against Defendant-Appellee Welty Building Company, Ltd. ("Welty") for breach of contract and fraud.1 In the complaint, Liberty alleged that the parties entered into a subcontract on July 23, 1998, for Liberty to perform "earth work" and "site utility" work on behalf of Welty. Liberty claimed that it substantially performed all the material terms of the subcontract, but that Welty breached the terms of the subcontract by failing to pay Liberty for the work completed. Liberty alleged that there remained an outstanding overdue balance in an amount in excess of $25,000 for work it performed under the subcontract.2 Liberty further alleged that Welty fraudulently induced Liberty to do additional work by falsely promising Liberty it would be paid the overdue monies owed under the subcontract. Liberty claimed that in reliance upon these promises, it suffered damages in excess of $25,000.

{¶ 3} Welty filed an answer and counterclaim on December 21, 2001. As one of the many defenses asserted by Welty in its answer, Welty alleged that Liberty was barred from asserting a breach of contract claim because of its own breach of contract. In its counterclaim, Welty further alleged that as a result of Liberty's breach of contract, it was "damaged in an amount that cannot yet be reasonably determined, inasmuch as the work for which [Liberty] contracted Welty has not yet been completed."3 Liberty replied to Welty's counterclaim. The matter proceeded to a bench trial after many attempts to mediate the issues.

{¶ 4} After hearing testimony from Delores Kavocic, David Berger, Donzell Taylor, and James Regan, the trial court granted judgment in favor of Liberty in the amount of $83,196 on its complaint. The trial court also granted judgment in favor of Welty in the amount of $40,306 on its counterclaim. The trial court's conclusions were based on the following findings of fact. In 1998, Welty was awarded a contract with the Veteran's Association ("VA") to construct and develop a new National Cemetery located in Rittman, Ohio ("VA project"). Welty then subcontracted with Liberty to perform certain specified earth work and site utilities. The trial court found that "[t]he subcontract also provided that Liberty was only entitled to compensation for work it performed necessitated by acts or omissions of other subcontractors to the extent Welty was paid by the VA on account of such failure." The subcontract further provided that the terms and conditions could be varied, but such variations would only be binding upon the parties by a writing signed by the contractor. During the course of construction, Welty requested Liberty to perform extra work, over and above the original subcontract value of $2,147,000. The "extra work" was followed by a "writing signed by the contractor," in which Welty agreed to take the risk of paying Liberty for any outstanding quotes in the absence of prior approval by the VA of the quotes. The trial court found that the outstanding balance Welty owed Liberty as of August 3, 2001, amounted to $83,196 and that Welty was legally obligated to pay Liberty that amount, subject to Liberty's completion of the punch list items. The trial court granted judgment in favor of Liberty in the amount of $83,196.

{¶ 5} The trial court further found that Liberty failed to complete the punch list items and that Welty sent Liberty a letter on October 17, 2001 that provided Liberty with 72 hour notice regarding its failure to complete those items. Despite receiving the notice, Liberty did not complete the punch list items and Welty terminated the subcontract. Welty was then forced to hire another subcontractor, Kiehl Excavating, Inc. ("Kiehl"), to complete the punch list items; at the time of trial, Kiehl was in the process of completing those items at an estimated cost of $13,250. With regard to the back charges Welty assessed against Liberty, the trial court specifically found that other subcontractors were hired to repair or complete: 1) extra seeding, "cutting and patching," which was completed by Richfield Landscape Contractors, Inc. ("Richfield"); 2) the resetting of sprinkler heads, which was completed by S M Irrigation ("S M"); and 3) crypt damage, which was repaired by Lindsay Concrete Products, Inc. The trial court found that the value of the work performed by the replacement subcontractors was $27,056, and that Welty validly assessed this cost against Liberty as back charges pursuant to Article 6 of the subcontract. The trial court awarded Welty $13,250 for punch list items Liberty failed to complete and $27,056 in "back charge damages." The trial court deducted $7,480 from the total amount awarded in Welty's counterclaim for the final retainage amounts still being withheld against Welty by the VA; Welty conceded in its post-trial brief that Liberty was owed the $7,480. As a result, the trial court awarded Welty $32,826 in damages. After set-off of Welty's counterclaim award in the amount of $32,826 against Liberty's award in the amount of $83,196, Liberty was granted judgment in the amount of $50,370.

{¶ 6} Liberty has timely appealed, asserting three assignments of error. We have consolidated Liberty's first and second assignments of error for ease of analysis. In addition, Welty has asserted one cross-assignment of error.

II
Assignment of Error Number One
"The trial court committed prejudicial error in awarding * * * [Welty] a set-off of $27,056 in claimed backcharges."

Assignment of Error Number Two
"The trial court committed prejudicial error in awarding [Welty] a set-off of $13,250 for `punchlist' work."

{¶ 7} In Liberty's first and second assignments of error, it has argued that the trial court erred when it awarded Welty damages for back charges and uncompleted punch list items.

{¶ 8} This Court will not reverse a trial court's judgment so long as it is supported by competent, credible evidence going to all of the essential elements of the case. C.E. Morris Constr.Co. v. Foley Constr. Co. (1978), 54 Ohio St.2d 279, 280; see, also, Wallick Enters. v. Loran Metro. Hous. Auth., 10th Dist. No. 01AP-1383, 2002-Ohio-3855, ¶ 12; Gillard v. Green (Dec. 28, 2001), 4th Dist. No. 00CA54, 2001 Ohio App. LEXIS 6019, *11. "This standard is highly deferential and even `some' evidence is sufficient to sustain the judgment and to prevent a reversal."Barkley v. Barkley (1997), 119 Ohio App.3d 155, 159. Therefore, this Court does not decide whether it would have come to the same conclusion as the trial court.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sterling Contracting, L.L.C. v. Main Event Entertainment, L.P.
2022 Ohio 2138 (Ohio Court of Appeals, 2022)
Luo v. Gao, Unpublished Decision (3-7-2007)
2007 Ohio 959 (Ohio Court of Appeals, 2007)
Kimbel v. Clark, Unpublished Decision (12-29-2006)
2006 Ohio 6959 (Ohio Court of Appeals, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
2004 Ohio 4873, Counsel Stack Legal Research, https://law.counselstack.com/opinion/liberty-excavating-v-welty-bldg-co-ltd-unpublished-decision-ohioctapp-2004.