Sterkx v. Gravity Drainage Dist. No. 1 of Rapides Par.

214 So. 2d 552
CourtLouisiana Court of Appeal
DecidedNovember 15, 1968
Docket2343
StatusPublished
Cited by28 cases

This text of 214 So. 2d 552 (Sterkx v. Gravity Drainage Dist. No. 1 of Rapides Par.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sterkx v. Gravity Drainage Dist. No. 1 of Rapides Par., 214 So. 2d 552 (La. Ct. App. 1968).

Opinion

214 So.2d 552 (1968)

Walter STERKX, Plaintiff-Appellant,
v.
GRAVITY DRAINAGE DISTRICT NO. 1 OF RAPIDES PARISH, La., Defendant-Appellee.

No. 2343.

Court of Appeal of Louisiana, Third Circuit.

June 18, 1968.
On Rehearing October 3, 1968.
Writ Refused November 15, 1968.

*553 Downs & Gremillion, by James C. Downs, Alexandria, for plaintiff-appellant.

Mansour & Lauve, by Alfred Mansour, Alexandria, for defendant-appellee.

Before LEAR, HOOD, and SAVOY, JJ.,

LEAR, Judge.

Petitioner is the owner of an undivided one-fifth interest in certain valuable property situated partly within the corporate limits of the City of Alexandria, Louisiana, and the remainder adjoining said limits.

Defendant, a body corporate with power to sue and be sued, constructed a drainage canal across this property. Plaintiff alleged trespass, unlawful and uncompensated confiscation, and certain incidental damages. He asked total recovery in the sum of $25,194.40.

Respondent admits the construction of the drainage facilities upon the described property, as alleged. It sets forth, however, that this construction was had in accordance with an agreement entered into by and between defendant and all of the co-owners of the property. It sets forth that written agreements were entered into it and Mr. Sterkx's co-owners, and further alleges that the said construction was in strict compliance with an agreement entered into between it and Mr. J. B. Nachman, who had full authority from plaintiff to negotiate on plaintiff's behalf for a contract with defendant; that Mr. Nachman agreed to accept the price of $2,574.40 for his part of the compensation to be paid for the drainage servitude, and "* * * that a copy of the agreement was delivered to his said attorney, and it was agreed by all that the said plaintiff would execute the agreement."

Defendant then asserts that plaintiff was estopped to repudiate the agreement made by Mr. Nachman and should have and recover judgment only for the sum of $2,574.40.

A great portion of the evidence adduced, plus a lengthy opinion written by the district court, and the briefs of both appellant and appellee deal with the question of whether Mr. Nachman had apparent authority from petitioner to enter into such an agreement; whether petitioner's clothing Mr. Nachman with such apparent authority would estop him from repudiating an agreement made by Mr. Nachman, and whether a servitude can be granted by oral title or achieved by estoppel.

However, these complex and troublesome problems need not concern us here. It is a fundamental rule of our law that when negotiating parties agree that the final contract will be reduced to writing, then that agreement is an integral part of the contract itself. Therefore, until such agreement is reduced to writing there is no contract, and either party may retract or refuse to abide by what had been orally agreed upon. See Ferre Canal Co. v. Burgin, 106 La. 309, 30 So. 863; Barrelli v. Wehrli, 121 La. 540, 46 So. 620; Breaux Bros. Construction Co. v. Associated Contractors, 226 La. 720, 77 So.2d 17, as examples of many, many cases deciding this point.

*554 As pointed out above, the defendant affirmatively avers in its answer that it was agreed upon between the parties that a formal, written instrument should be signed by petitioner and the entire record is rife with testimony to that effect. That being the case, no binding contract came into being between plaintiff and defendant, and it now becomes necessary for this court to assess the damages done by defendant's unauthorized entry upon the land owned, in indivision, by petitioner.

As stated above, plaintiff sued not only for the value of the actual land taken, but also asked for severance damages as to a portion of the entire tract, and alleged other items of substantial damage such as the destruction of valuable trees, the establishment of spoil banks, and the changing of natural drainage upon the remaining property, the cost of the construction of bridges across said canal necessary for the full utilization of plaintiff's property, etc.

However, plaintiff, in his brief before this court, concedes that he is restricted to compensation based on the fair market value of the property actually taken.

Defendant relied entirely upon its defense of estoppel, and offered no testimony to confute the evidence of petitioner's experts who testified as to the value of the land taken.

The uncontradicted testimony establishes that the value of the land taken is the sum of $6,032.80, and thus the award made herein should be increased to that amount.

Therefore, this court affirms the judgment of the lower court in granting judgment for plaintiff, but increases the amount of that award from the sum of $2,574.40 to the sum of $6,032.80. Defendant to pay all costs of this appeal.

Judgment amended, and as amended, affirmed.

On Rehearing.

En Banc.

TATE, Judge.

In granting rehearing, we requested that argument be limited to three issues: (1) the circumstance that our award was greater than the amount prayed for in plaintiff's petition; (2) whether legal interest should be awarded and from what date; (3) the question of to which party court costs should be assessed.

We discuss these issues in that order.

(1)

Plaintiff prayed for $5,024.40 as the value of the property appropriated.[1] In application for rehearing the defendant-appellee points out that this court awarded $6,032.80, that is, an amount in excess of the demand. The plaintiff-appellant contends, however, that the award in excess of the demand is proper because without objection evidence to this effect so enlarged the pleadings.

When otherwise inadmissible evidence is admitted without objection, the pleadings are enlarged to this extent. See LSA-C.C.P. Art. 1154: "When issues not raised by the pleadings are tried by express or implied consent of the parties, they shall be treated in all respects as if they had been raised by the pleading. * * *"

By this principle judgment may be awarded in excess of the amount prayed for, when (1) evidence otherwise inadmissible is admitted without objection, (2) such evidence establishes that the party is entitled to this larger award, and (3) the circumstances are such that it may reasonably be implied that the parties consented to the enlargement of the pleading to include the increased demand. Blodgett Construction Co. v. Board of Commissioners, 153 La. 623, 96 So. 281; Huval v. Burke, La.App., *555 3 Cir., 160 So.2d 810; State Through Dept. of Highways v. Watkins, La.App., 3 Cir., 155 So.2d 245; Wright v. Holder, La.App., 2 Cir., 72 So.2d 529; Ethridge-Atkins Corp. v. Abraham, La.App., 2 Cir., 1935, 160 So. 817.

The essential reason why an excess award is permitted in such cases is that the issue was litigated by the implied consent of the opponent. The uncontradicted evidence proves an award larger than that originally demanded, with the pleadings automatically amended with regard to that issue by the evidence admitted without objection. LSA-C.C.P. Art. 1154.

Nevertheless, the implied consent so found does not automatically result from a failure to object to evidence enlarging the pleadings. As stated by the authoritative treatise, James, Civil Procedure (1965), Section 5.7:

"Nonobjection to evidence does not always fairly indicate that the adversary was in fact, or should reasonably have been aware of the full implications of the evidence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mathis v. City of DeRidder
599 So. 2d 378 (Louisiana Court of Appeal, 1992)
Anmac Foundation v. St. Patrick Hosp.
594 So. 2d 951 (Louisiana Court of Appeal, 1992)
Martin v. Schluntz
589 So. 2d 1208 (Louisiana Court of Appeal, 1991)
Guillory v. Trinity Universal Insurance Co.
520 So. 2d 1071 (Louisiana Court of Appeal, 1987)
McBride v. Hebert
490 So. 2d 454 (Louisiana Court of Appeal, 1986)
STATE, DEPT. OF TRANSP. & DEV. v. C. Schexnayder, Inc.
485 So. 2d 939 (Louisiana Court of Appeal, 1986)
STATE DEPT. OF TRANSP. AND DEVELOPMENT v. Winn
463 So. 2d 648 (Louisiana Court of Appeal, 1984)
Stovall v. Tom Hicks Transfer Co.
425 So. 2d 833 (Louisiana Court of Appeal, 1982)
Smith v. Moncrief
421 So. 2d 1127 (Louisiana Court of Appeal, 1982)
Ehrhardt v. Cummins
369 So. 2d 213 (Louisiana Court of Appeal, 1979)
Wexler v. Martin
367 So. 2d 111 (Louisiana Court of Appeal, 1979)
State Dept. of Highways v. Terrebonne
349 So. 2d 936 (Louisiana Court of Appeal, 1977)
Jerry Joseph Fontenot, Ind. v. STATE, ETC.
346 So. 2d 849 (Louisiana Court of Appeal, 1977)
Alexander v. STATE DEPT. OF HIGHWAYS
342 So. 2d 1201 (Louisiana Court of Appeal, 1977)
Watson v. Morrison
340 So. 2d 588 (Louisiana Court of Appeal, 1977)
Segura v. Louisiana Architects Selection Board
340 So. 2d 369 (Louisiana Court of Appeal, 1976)
James, Robinson, Felts & Starnes v. Powell
303 So. 2d 229 (Louisiana Court of Appeal, 1974)
Stallworth v. McFarland
350 F. Supp. 920 (W.D. Louisiana, 1972)
Parish of East Baton Rouge v. Harrison
260 So. 2d 106 (Louisiana Court of Appeal, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
214 So. 2d 552, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sterkx-v-gravity-drainage-dist-no-1-of-rapides-par-lactapp-1968.