Steiny & Co. v. California Electric Supply Co.

93 Cal. Rptr. 2d 920, 79 Cal. App. 4th 285, 2000 Cal. Daily Op. Serv. 2343, 41 U.C.C. Rep. Serv. 2d (West) 439, 2000 Daily Journal DAR 3132, 2000 Cal. App. LEXIS 215
CourtCalifornia Court of Appeal
DecidedMarch 23, 2000
DocketB121149, B124698
StatusPublished
Cited by38 cases

This text of 93 Cal. Rptr. 2d 920 (Steiny & Co. v. California Electric Supply Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Steiny & Co. v. California Electric Supply Co., 93 Cal. Rptr. 2d 920, 79 Cal. App. 4th 285, 2000 Cal. Daily Op. Serv. 2343, 41 U.C.C. Rep. Serv. 2d (West) 439, 2000 Daily Journal DAR 3132, 2000 Cal. App. LEXIS 215 (Cal. Ct. App. 2000).

Opinion

Opinion

NEAL, J.—

Summary

Where a plaintiff’s proper invocation of the trade secrets privilege prevents a defendant from examining the basis for the plaintiff’s damage claim, the trial court may properly bar the plaintiff’s damage evidence at trial. If a buyer and a seller exchange invoice and purchase order with conflicting warranty terms, but their conduct shows that a contract has been formed, California Uniform Commercial Code section 2207 applies to form a contract around the parts of the invoice and purchase order which agree, supplemented by the other applicable provisions of the Commercial Code.

Facts and Trial Court Proceedings

Appellant Morley Construction Company (Morley) was the general contractor for seismic upgrade work at a facility owned by appellant Hughes Aircraft Company (Hughes). Morley subcontracted with appellant Steiny and Company, Inc. (Steiny) for supply and installation of an electric switchboard with circuit breakers. Steiny bought the switchboard from respondent California Electric Supply Company, Inc. (California). The switchboard was manufactured by Cutler Hammer, Inc. (Cutler).

The switchboard exploded two days after it was powered up, causing a 16-hour power outage.

*289 Hughes sued Morley for damages to Hughes’s business caused by the power interruption. Morley sued Steiny for indemnity against damages Morley was required to pay Hughes. Steiny sued Morley for withholding $412,000 in payment for Steiny’s work, claiming interest on its damages “at the maximum legal rate.” Steiny also sued California for supplying defective switchboard equipment. Steiny alleged breach of the express warranties of merchantability and fitness for intended use.

Morley agreed to pay $477,896 to settle with Hughes.

California and Cutler propounded discovery seeking information about the basis for the Hughes-Morley settlement, and about Hughes’s damages from the power outage. For example, they requested production of all documents relating to Morley’s claim for damages against Steiny; and they propounded interrogatories asking that Hughes state the amount of damages it claimed and the way it calculated them.

Morley and Hughes moved for a protective order. They urged that the information needed to support Hughes’s damage calculations was proprietary. They asked that they be required to reveal their damage calculations only in a “general spreadsheet showing final accounting numbers,” and not be required to provide a “detailed accounting breakdown.”

The trial court granted the motion for a protective order, and appointed a special master to “marshall [szc] a spreadsheet summary of Hughes’ damage calculations.” The court ordered that the special master provide the parties only with the information in the spreadsheet, and not a copy of it. The court further ordered that Hughes and Morley need not produce, at any time, “any back-up information underlying [the] spreadsheet summary.” (The trial court was not asked to address, and did not address, the impact of its rulings upon what evidence Hughes and Morley would later be allowed to offer at trial.)

Steiny’s application to this court for an extraordinary writ overturning the protective order was summarily denied.

For reasons the parties do not explain, the special master never prepared or provided the ordered spreadsheet. Hughes eventually tendered a heavily redacted spreadsheet of its own preparation. Neither Hughes nor Morley ever provided the detailed information called for in the document requests and interrogatories.

When the cases proceeded to trial, Steiny moved to exclude Morley’s evidence of damages, arguing that such exclusion was the appropriate and *290 necessary remedy for Morley’s invocation of privilege to prevent disclosure of damages evidence. In response, Morley said it intended to present only: evidence of the sum actually paid to Hughes in settlement, plus evidence that this approximated the amount of damages claimed by Hughes against Morley. Morley argued that the settlement was presumed reasonable, and that it was Steiny’s burden to disprove this, citing Peter Culley & Associates v. Superior Court (1992) 10 Cal.App.4th 1484, 1497 [13 Cal.Rptr.2d 624].

The trial court granted Steiny’s motion and excluded the evidence, noting that the protective order obtained by Hughes and Morley had rendered Steiny unable to challenge the amount or reasonableness of the Hughes-Morley settlement.

The parties then entered a “stipulation of facts re entry of judgment” which recited that Morley could not proceed with its case in light of exclusion of its damage evidence; that the court could therefore enter judgment in Steiny’s favor dismissing Morley’s claims and awarding Steiny the sum due from Morley on the subcontract; that Morley reserved its right to appeal the ruling excluding the settlement sum evidence; and that “[wjhether Steiny is entitled to prejudgment interest . . . shall be determined by the court subsequent to the entry of judgment.” The court entered judgment the same day.

Steiny requested an award of attorney fees, costs, and prejudgment interest. It cited, inter alia, paragraph 19 of the subcontract, which required Steiny to pay Morley’s costs of “effecting compliance” with the contract, including attorney fees, and argued this clause was made reciprocal by Civil Code section 1717. Steiny presented its counsel’s declaration attesting to the number of hours billed, the hourly rates, and the tasks performed. Supporting billing records were not supplied. Steiny also claimed as costs fees paid to its litigation experts. The trial court awarded Steiny its attorney fees, expert witness fees, and prejudgment interest.

Trial went forward on Steiny’s claim against California for supplying defective equipment. The evidence concerning the contract included Steiny’s purchase order to California, and California’s invoice to Steiny. These contained diametrically opposing provisions concerning warranties. The purchase order specified express warranties of merchantability and fitness for particular use, which were stated to be “in addition to any and all warranties of Seller arising by operation of law . . . nothing contained herein shall be construed as limiting or restricting such warranties.” The invoice expressly disclaimed all express and implied warranties. The invoice *291 recited that any inconsistent terms contained in Steiny’s order were not binding, and that Steiny’s acceptance of the goods would constitute acceptance of California’s terms. Neither party signed the other party’s document. The evidence was in conflict as to which party’s document was first tendered to the other.

Steiny presented expert evidence that the circuit breaker supplied by California was defective; California presented expert evidence that errors in installation caused the failure.

Steiny requested the trial court to instruct the jury on the rules in California Uniform Commercial Code section 2207, which deals with conflicting contract forms, and also to instruct on the implied warranties of merchantability and fitness. The trial court declined these requests.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Qassimyar v. Ortega CA4/1
California Court of Appeal, 2026
Bettelheim v. Rios CA6
California Court of Appeal, 2025
Byers v. Super. Ct.
California Court of Appeal, 2024
Robertson v. Robertson CA1/5
California Court of Appeal, 2023
Isom v. MacCarthy CA2/4
California Court of Appeal, 2023
Isom v. McCarthy
California Court of Appeal, 2023
Rainsdon v. Grant
D. Idaho, 2023
Mooney v. Argus Realty Investors CA4/3
California Court of Appeal, 2023
Vera v. FlexShopper, LLC
N.D. California, 2022
Appel v. Wolf
S.D. California, 2022
Solis v. Clean Harbors, Inc.
N.D. California, 2022
Shane v. Rumiano CA3
California Court of Appeal, 2021
Albertini v. Acebo-Houlihan CA4/1
California Court of Appeal, 2021
Kivel v. McInerney CA4/1
California Court of Appeal, 2021
Rancho Mirage Country Club Homeowners Ass'n v. Hazelbaker
2 Cal. App. 5th 252 (California Court of Appeal, 2016)
Watson Bowman Acme Corp. v. RGW Construction, Inc.
2 Cal. App. 5th 279 (California Court of Appeal, 2016)
Robles v. McErlain CA1/4
California Court of Appeal, 2015
Rockroller v. Koljonen CA4/1
California Court of Appeal, 2015

Cite This Page — Counsel Stack

Bluebook (online)
93 Cal. Rptr. 2d 920, 79 Cal. App. 4th 285, 2000 Cal. Daily Op. Serv. 2343, 41 U.C.C. Rep. Serv. 2d (West) 439, 2000 Daily Journal DAR 3132, 2000 Cal. App. LEXIS 215, Counsel Stack Legal Research, https://law.counselstack.com/opinion/steiny-co-v-california-electric-supply-co-calctapp-2000.