State v. OFFICE OF PUBLIC UTILITY COUNSEL

849 S.W.2d 864, 1993 WL 63949
CourtCourt of Appeals of Texas
DecidedApril 28, 1993
Docket3-92-064-CV
StatusPublished
Cited by12 cases

This text of 849 S.W.2d 864 (State v. OFFICE OF PUBLIC UTILITY COUNSEL) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State v. OFFICE OF PUBLIC UTILITY COUNSEL, 849 S.W.2d 864, 1993 WL 63949 (Tex. Ct. App. 1993).

Opinions

KIDD, Justice.

This appeal arises from a suit for judicial review of an order by the Public Utility Commission of Texas (the “Commission”) granting a rate-change petition submitted by Houston Lighting & Power Company (“HL & P”). Following extensive discovery and hearings, the Commission issued a final order under docket numbers 6765, 6766, and 6930 granting HL & P’s petition. In separate causes, the Office of the Public Utility Counsel (the “OPUC”), HL & P, and the State of Texas (the “State”)1 sought judicial review of the Commission’s order in district court. The district court consolidated the causes and affirmed the order in all respects except for the Commission’s decision to include construction work in progress (“CWIP”)2 in HL & P’s rate base. [866]*866Both HL & P and the Commission appeal the district court’s reversal of the Commission’s order allowing inclusion of CWIP. In addition, the State appeals the district court’s decision affirming the Commission’s approval of HL & P’s proposed late-payment penalty. We will affirm in part and reverse and remand in part.

BACKGROUND AND PROCEDURAL HISTORY

This case originated when HL & P filed a system-wide application on March 18, 1986, to increase its rates in the unincorporated areas that it serves. The Commission styled HL & P’s application as docket number 6766 and later consolidated it with docket numbers 6766 and 6960. Docket numbers 6766 and 6960 concerned, respectively, HL & P’s proposed interim accounting treatment for Limestone Unit I and a citizen’s appeal of the City of Houston’s approval of HL & P’s request to increase its rates within Houston’s corporate limits. The Commission held hearings under these docket numbers from June 30, 1986, through August 7, 1986. Based on these hearings and a 422-page examiner’s report, the Commission issued a final order on November 14, 1986, adopting most of the findings of fact and conclusions of law contained in the examiner’s report. The order approved HL & P’s rate-increase request, albeit at levels lower than those the utility requested, and included authorization for the inclusion of $678,072,000 of CWIP in HL & P’s rate base. The order also included a three percent late payment penalty on non-residential customers.3

The Commission’s order authorized the inclusion of $678,072,000 of CWIP in HL & P’s rate base pursuant to section 41(a) of the Public Utility Regulatory Act.4 The Commission took a three-tiered approach in determining whether HL & P was eligible to receive a CWIP allowance pursuant to section 41(a).5 First, the Commission determined whether HL & P met a “threshold test” of “exceptional circumstances,” which controlled whether it was eligible for any CWIP at all.6 Second, the Commission calculated the amount of CWIP necessary to preserve the financial integrity of the utility.7 Finally, the Commission determined that none of this CWIP allowance included major projects that were inefficiently or imprudently planned or managed.

The Commission’s order also adopted findings of fact approving HL & P’s request for a three-percent late-payment penalty for nonresidential customers.8 This approval was pursuant to PUC Substantive Rule section 23.45(b), which authorizes utilities to assess a penalty, not to exceed five percent, on delinquent nonresidential bills.9 Based on this provision, the Commission concluded that HL & P’s request for the late payment penalty was reasonable and approved the request in its final order.

In separate causes, HL & P, the OPUC, and the State sought judicial review of the Commission’s order pursuant to section 69 of PURA and section 19 of the Administrative Procedure and Texas Register Act.10 [867]*867In its petition to the district court, the OPUC objected to the Commission’s decision to include $678,072,000 of CWIP in HL & P’s rate base, in addition to other objections presented during the hearings. The State sought reversal of the Commission’s approval of HL & P’s late payment penalty as applied to state agencies. HL & P’s action sought to overturn those portions of the Commission’s order which did not grant the full rate adjustment it had requested. On May 11, 1990, the district court held a hearing on consolidation and concluded that these causes involved common questions of fact and law, and ordered that the causes be consolidated for all purposes under cause number 411,593.

After considering the parties’ briefs and arguments, the district court rendered a judgment upholding all portions of the Commission’s final order except the Commission’s authorization of the inclusion of CWIP. The district court held that the Commission misapplied the threshold test of section 41(a) by failing to require a showing of “exceptional circumstances.” The district court found that, in place of a showing of exceptional circumstances, the Commission merely required HL & P to show circumstances that deviated from the industry norm.

DISCUSSION

I. Reversal of the Commission’s CWIP Decision

In three points of error, the Commission and HL & P contend that the district court erred in reversing the Commission’s approval of HL & P’s request for the inclusion of CWIP in its rate base. Both parties argue on appeal that the Commission fully complied with PURA section 41(a), and that there is substantial evidence supporting the Commission’s decision.

As a preliminary matter, we will consider HL & P’s first point of error, which contends that the district court improperly construed section 41(a) as requiring a threshold inquiry into whether exceptional circumstances justify the inclusion of CWIP in a utility’s rate base. HL & P argues that the language of section 41(a) does not establish a threshold requirement of “exceptional circumstances” independent from the financial integrity and prudent management requirements expressly stated in the statute. HL & P suggests that section 41(a) requires only a two-tier inquiry: (1) whether CWIP is necessary to maintain the utility’s financial integrity, and (2) whether the utility’s major projects were prudently planned and managed. We disagree with this construction of the statute.

The legislative history of section 41(a) and the Commission’s own substantive rules support the existence of an independent threshold inquiry of exceptional circumstances. Prior to the legislature’s 1983 amendment of section 41(a), the sole requirement for the inclusion of CWIP was a showing by the utility that the CWIP allowance was necessary to maintain the utility’s financial integrity.11 As amended, section 41(a) designates the inclusion of CWIP as an exceptional remedy. The legislature retained the previous financial integrity test, but added an additional requirement excluding any CWIP allowance for projects imprudently planned or managed.12 The floor debate on this amendment clearly reveals that the legislature’s intent was to prevent the Commission from authorizing CWIP allowances as a matter of course, and to restrict CWIP awards to [868]*868only those cases where the utility could demonstrate circumstances justifying an exceptional form of rate relief.13

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
849 S.W.2d 864, 1993 WL 63949, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-v-office-of-public-utility-counsel-texapp-1993.