UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA
STATE OF LIBYA,
Petitioner,
v. No. 1:20-cv-02600 (DLF)
STRABAG SE,
Respondent.
MEMORANDUM OPINION AND ORDER
This case arises out of an arbitration between Libya and Strabag SE (Strabag) over a
series of construction contracts that were disrupted by the 2011 Libyan revolution. Before the
Court is Libya’s Petition to Vacate the Arbitration Award, Dkt. 1, and Strabag’s Cross-Motion to
Confirm the Arbitration Award, Dkt. 12. For the reasons that follow, the Court will deny
Libya’s petition and grant in part Strabag’s cross-motion.
I. BACKGROUND
Respondent Strabag is a publicly listed, international construction firm that is
incorporated in Austria. Resp’t’s Opp’n to Libya’s Pet. to Vacate at 4, Dkt. 11. Following the
relaxation of international sanctions on Libya in 2003, Strabag, through its wholly owned
German subsidiary, Strabag International Ltd. (Strabag International), was awarded contracts to
construct two major road projects in Libya. Arbitration ¶¶ 4–5, Dkt. 1-3; Resp’t’s Opp’n at 6. In
2006, Libya started “requiring that foreign firms engaged in construction carry on business in
conjunction with a Libyan partner.” Arbitration ¶ 6.
In July 2007, to comply with this new requirement, Strabag International entered into a
joint venture with the Libyan Investment and Development Company (LIDCO). Id. They called the venture Al Hani General Construction Company (Al Hani). Id. ¶ 7. Strabag indirectly owns
sixty percent of Al Hani via its one hundred percent ownership of Strabag International. Id. ¶ 7.
Strabag International’s existing contracts in Libya were assigned to Al Hani which then
“subsequently entered into several additional” construction contracts with Libya. Id. ¶ 59.
Strabag contends that it “committed significant resources” to its “investment” in Al Hani and the
Libyan contracts in the form of “acquiring property, building large facilities, . . . importing large
quantities of heavy equipment[,]” and “extend[ing] Al Hani a significant line of credit to ensure
the subsidiary had sufficient working capital when it was suffering from serious cash flow
problems.” Resp’t’s Opp’n at 6.
Each of the two contracts entitled Al Hani to an advance payment (one for fifteen percent
of the contract’s value, the other for twenty percent) from the Libyan government entity
responsible for the contract. Arbitration ¶ 65. These advance payments were to be repaid
through discounts in the amounts owed to Al Hani for the work completed. Id. The contracts
further required that Al Hani secure irrevocable bank guarantees “to be released only after
completion of all work under the Contracts and the expiry of the remedial period under the
guarantee period.” Id.
In February 2011, armed conflict broke out in Libya between the Libyan government and
rebel forces. Id. ¶ 75. As the conflict spread across Libya, Al Hani halted construction and
began moving its employees and equipment to safer locations. Id. ¶ 76. Al Hani suffered
significant losses from both the government’s own forces and the “breakdown of law and order.”
Id. ¶ 77. Al Hani’s vehicles were taken at a checkpoint, one of their construction camps was
overrun, looted, and partially burned by a mob, and a number of their sites were “occupied for
2 varying lengths of time by organized military units loyal to the regime.” Id. ¶¶ 77–79. Much of
Al Hani’s equipment was either stolen or destroyed in the conflict. Id.
After the conflict, Strabag and Al Hani asked the government about “securing payment
for unpaid work done prior to the Revolution; compensation for wartime damage; and resuming
work on major uncompleted contracts.” Id. ¶ 86. But they could not agree, so they commenced
arbitration in June 2015. Resp’t’s Opp’n at 8.
While the contracts themselves provided that “disputes are to be resolved in Libyan
courts,” Strabag brought this dispute to arbitration under the Austria–Libya Bilateral Investment
Treaty (the Treaty). Arbitration ¶ 1. Article 11 of the Treaty “permits a qualifying investor to
submit a dispute to arbitration.” Pet. ¶ 11. Consistent with the Treaty, Strabag submitted the
dispute to the International Centre for Settlement of Investment Disputes (ICSID). Id. The
ICSID has the authority “to administer certain categories of proceedings between States and
nationals of other States that fall outside the scope of the ICSID Convention.” ICSID Additional
Facility Rules, Pet. Ex. 3, at 5, Dkt. 1-5.
The Arbitration took place over two weeks in Paris in July 2018. Arbitration ¶ 46. The
parties and the ICSID Tribunal (the Tribunal) determined that the “legal seat” of the Arbitration
would be Washington, D.C., as allowed by the Additional Facility Rules of the ICSID, and thus
both parties agreed that the Federal Arbitration Act (FAA) would govern the Arbitration. The
Tribunal concluded that Libya had breached its obligations under the Treaty and awarded
Strabag €74,937,003.60 (plus interest) in damages. Resp’t’s Opp’n at 12; Arbitration ¶ 979.
Libya now petitions this Court to vacate the award of the Tribunal on the grounds that it
violates § 10(a)(4) of the FAA. Pet. ¶ 58. Libya claims that the award is not sufficiently final
and that the Tribunal exceeded its powers. Id. Alternatively, Libya claims that the award should
3 be modified to avoid double recovery for Strabag. Id. ¶ 63. Strabag seeks to confirm the award.
Resp’t’s Opp’n at 1. This Court has jurisdiction to hear the parties’ claims under 9 U.S.C.
§ 10(a).
II. LEGAL STANDARDS
“[T]he burden facing petitioners who seek judicial vacatur of arbitration awards is
exceedingly high.” FBR Cap. Mkts. & Co. v. Hans, 985 F. Supp. 2d 33, 36 (D.D.C. 2013) (citing
Stolt-Nielsen S.A. v. AnimalFeeds Int’l Corp., 559 U.S. 662, 671 (2010)). “[J]udicial review of
arbitral awards is extremely limited,” and courts “do not sit to hear claims of factual or legal
error by an arbitrator as [they would] in reviewing decisions of lower courts.” Kurke v. Oscar
Gruss & Son, Inc., 454 F.3d 350, 354 (D.C. Cir. 2006) (quoting Teamsters Loc. Union No. 61 v.
United Parcel Serv., Inc., 272 F.3d 600, 604 (D.C. Cir. 2001)). “It is only when [an] arbitrator
strays from interpretation and application of the agreement and effectively ‘dispense[s] his own
brand of industrial justice’ that his decision may be unenforceable.” Stolt-Nielsen, 559 U.S. at
671 (quoting Major League Baseball Players Ass’n v. Garvey, 532 U.S. 504, 509 (2001) (per
curiam)). “The courts are not authorized to reconsider the merits of an award even though the
parties may allege that the award rests on errors of fact or on misinterpretation of the contract.”
United Paperworkers Int’l Union v. Misco, Inc., 484 U.S. 29, 36 (1987). This highly deferential
standard “maintain[s] arbitration’s essential virtue of resolving disputes straightaway,” and
prevents allowing arbitration to become “merely a prelude to a more cumbersome and time-
consuming judicial review process.” Oxford Health Plans LLC v. Sutter, 569 U.S. 564, 568–69
(2013) (quoting Hall St. Assocs., L.L.C. v. Mattel, Inc., 552 U.S. 576, 588 (2008)).
Under the FAA, a party to an arbitration can, within one year of the award, apply to a
federal court in the district where the award was made, see 9 U.S.C. § 10(a), for “an order
4 confirming the award,” id. § 9. “[T]he court must grant such an order unless the award is
vacated, modified, or corrected . . . .” Id. As the Supreme Court has explained, this is a clear
mandate that is not “malleable” and leaves no discretion to the district court. Hall St. Assocs.,
552 U.S. at 587. The party seeking to vacate or modify the award bears the burden of proof. See
Republic of Argentina v. AWG Grp. Ltd., 211 F. Supp. 3d 335, 344 (D.D.C. 2016), aff’d,
894 F.3d 327 (D.C. Cir. 2018). A court may vacate the award “where the arbitrators exceeded
their powers, or so imperfectly executed them that a mutual, final, and definite award upon the
subject matter was not made.” 9 U.S.C. § 10(a)(4). A court also may modify an award “[w]here
there was an evident material miscalculation of figures or an evident material mistake in the
description of any person, thing, or property referred to in the award.” Id. § 11(a). A party that
“seeks to set aside an award in the country where it was issued” may seek a pre-judgment bond
when “the other party seeks to enforce the award elsewhere.” United Nations Comm’n on Int’l
Trade L., Convention on Recognition and Enforcement of Foreign Arbitral Awards (the “New
York Convention”), art. VI, Introduction ¶ 1 (2016).
III. ANALYSIS
Libya alleges three claims in support of its petition to vacate or modify the arbitration
award: (1) that the award is not sufficiently final because it failed to fully address the set-off
payments owed to Libya, see Libya’s Mem. in Supp. of Pet. to Vacate at 5, Dkt. 1-1; (2) that the
Tribunal lacked jurisdiction to arbitrate the matter, id. at 28; and (3) that the Tribunal
impermissibly based its decision on “good order and fundamental fairness” instead of the
relevant provisions of the applicable treaty or contracts, id. at 30. All of Libya’s claims lack
merit, particularly given the high degree of deference accorded to arbitration awards, see Stolt-
Nielsen, 559 U.S. at 671; Oxford Health, 569 U.S. at 568. Accordingly, the Court will deny
5 Libya’s petition to vacate or modify the award and grant Strabag’s cross-motion to affirm the
award.
A. The Arbitration Award Was Final
“[I]t is a cardinal principle of arbitration that awards are reviewable and enforceable only
if they are ‘final’—that is, if they purport to resolve all aspects of the dispute being arbitrated.”
Am. Fed’n of Gov’t Emps., AFL–CIO, Local 3090 v. Fed. Lab. Rels. Auth., 777 F.2d 751, 755
(D.C. Cir. 1985); see also 9 U.S.C. § 10(a)(4). The finality of an arbitration award “does not
require that the arbitration award resolve every outstanding issue that might arise in later
litigation between the parties.” Pasha v. Janseshki, 597 F. App’x 25, 26 (2d Cir. 2015)
(quoting ConnTech Dev. Co. v. Univ. of Conn. Educ. Props., Inc., 102 F.3d 677, 686 (2d Cir.
1996) (arbitration was final despite defendant’s “speculation that subsequent litigation will be
required to ascertain respective project costs” because arbitrators considered parties’ arguments
about project costs when calculating the arbitration award amount)). Rather, an arbitration
award is final when it is “intended by the arbitrator to be his complete determination of every
issue submitted to him.” Am. Postal Workers Union v. U.S. Postal Serv., 422 F. Supp. 2d 240,
246 (D.D.C. 2006) (quoting McKinney Restoration Co. v. Ill. Dist. Council No. 1, 392 F.3d 867,
871 (7th Cir. 2004)); see also Gas Aggregation Servs., Inc. v. Howard Avista Energy, LLC,
319 F.3d 1060, 1069 (8th Cir. 2003) (arbitration was not final when panel declined to decide an
issue presented and left it for litigation).
Here, Libya argues that the arbitration award is not final because the Tribunal did not
fully consider Libya’s “set-off” claim. See Libya’s Mem. at 2. To the contrary, the Tribunal
thoroughly considered and rejected Libya’s claim that any award to Strabag should be “set off”
or reduced based on the pre-payments Libya made to Al Hani for work that Al Hani never
6 completed. The Tribunal first found “that it ha[d] jurisdiction to address [Libya’s] set-off
claim.” Arbitration ¶ 897. It then went on to reject Libya’s set-off claim with sixteen pages of
thorough analysis. See id. ¶¶ 875–921. In doing so, the Tribunal addressed every argument
offered by Libya, including unjust enrichment, id. ¶¶ 899–900, misuse of the advance payments,
id. ¶¶ 901–02, bank guarantees, see id. ¶¶ 903–09, 918–21, the “wrapping up” of the contracts’
requirements, id. ¶¶ 910–16, and restitution, id. ¶ 917.
Libya points to a single sentence in the 335-page decision to support its baseless claim
that the Tribunal “deliberately refused to adjudicate the set-off,” Libya Mem. 2: “In the view of
the majority, this is a matter that must be addressed by the Parties, if it is to be addressed, outside
the context of this arbitration,” Pet. ¶ 58 (quoting Arbitration ¶ 921). But, as the Tribunal
explained, it had no legal basis for awarding Libya a set-off because it did not have jurisdiction
to address the outstanding guarantees, the very existence of which was disputed. Id. ¶¶ 918–20
(“If Respondent’s claimed set-off were to be applied, those guarantees would remain. Claimant
would be left exposed to the risk of what would in essence be double recovery by Respondent.”);
see also id. ¶ 919 (“A bank that extends an ‘unconditional’ and ‘irrevocable’ letter of guarantee
has no duty, and perhaps no right, to pay some lesser amount on the basis of an arbitration ruling
to which it is not party.”). The Tribunal further found that Strabag and Al Hani used the advance
payments consistent with the contracts, and thus, there was no double recovery in the award.
Other courts confronted with similar extra-arbitral claims have likewise found that the existence
of such claims does not defeat the finality of an arbitration. See, e.g., Ranger Offshore Mexico,
S. de R.L. de C.V. v. Grupo Tradeco, S.A. de C.V., No. 4:15-cv-635, 2018 WL 780707, at *4
(S.D. Tex. Feb. 7, 2018), appeal dismissed, No. 18-20513, 2018 WL 7138080 (5th Cir. Dec. 26,
2018) (arbitration was final even though the panel did not resolve the issue of promissory notes
7 owed to one party as they were governed by Mexican law, outside the jurisdiction of the panel,
and the panel “did not tie the outcome of arbitration award to the enforcement” of the notes).1
Because the Tribunal clearly addressed the issues before it, including the arguments
relating to Libya’s set-off claim, its award was sufficiently final as required by § 10(a)(4) of the
FAA.2
B. The Tribunal Did Not Exceed Its Powers
Libya next argues that the Tribunal exceeded its power in two respects. First, it alleges
that the Tribunal “exceeded its powers in exercising jurisdiction over the parties’ dispute.”
Libya’s Mem. at 28. Alternatively, Libya alleges that the Tribunal’s majority exceeded its
powers “in refusing to resolve the single largest issue in the arbitration—whether the set-off for
the approximately €98 million in unearned advance payments that Strabag received under the
[c]ontracts” resulted in a double recovery for Strabag. Id. at 28–30. Both claims fail.
1. Jurisdiction
The Tribunal properly found that it had the authority to determine its own jurisdiction.
Arbitration ¶ 1. Because the arbitration was brought under the Treaty, the ICSID Additional
Facility Rules applied. Agreement between the Republic of Austria and the Great Socialist
People’s Libyan Arab Jamahiriya for the Promotion and Protection of Investments, Austria-
Libya, art. XI, § 2(c)(ii), June 18, 2002, Dkt. 1-6. Thus, “the Tribunal ha[d] the power to rule on
1 Given that the Tribunal spent sixteen pages thoroughly considering and rejecting the petitioner’s arguments, see Arbitration ¶¶ 875–921, it is unethical for petitioner to assert that the Tribunal “deliberately refused to adjudicate the set-off,” Libya’s Mem. at 2. 2 Libya’s arguments that the award should be modified, see Libya’s Mem. at 33–39, fail for the same reason—the Tribunal considered and rejected them with reasoned analysis, see Arbitration ¶¶ 899–921.
8 its own competence.” ICSID Rules, art. 45; see also Gold Rsrv. Inc. v. Bolivarian Republic of
Venezuela, 146 F. Supp. 3d 112, 122 (D.D.C. 2015).
Far from “ignor[ing] the plain language” of the Treaty, Republic of Argentina v. AWG
Grp. Ltd., 211 F. Supp. 3d 335, 344 (D.D.C. 2016), aff’d, 894 F.3d 327 (D.C. Cir. 2018)
(quoting United Paperworkers Int’l Union, AFL–CIO v. Misco, Inc., 484 U.S. 29, 38 (1987)), in
deciding unanimously that it had jurisdiction over the dispute, the Tribunal fully construed and
applied the relevant sections of the Treaty, considered the arguments of both parties, and
consulted international law. Arbitration ¶¶ 97–210. The Tribunal found that the arbitration was
brought under the Treaty because Strabag qualified as an “investor,” id. ¶ 119; the contribution
Strabag made to Al Hani was an “investment,” id. ¶ 110; Al Hani “operated under the clear
control of Strabag;” and “[t]here was no separation between Strabag and Al Hani,” id. ¶ 134. It
then considered and dismissed Libya’s arguments that Strabag, as the parent company, could not
bring the arbitration because neither it nor the state of Libya were parties to the contract. Id.
¶¶ 167–88. And it examined the terms of the contract between Al Hani and the Libyan
Government, including those that specified Libyan courts as the proper venue for dispute
resolution, before determining that Strabag was entitled to pursue his claims before the Tribunal,
consistent with principles of international law. Id. ¶¶ 189–207. In short, “[t]he evidence
show[ed]” that “[Strabag] could not pursue its contract-related claims in Libyan courts in safety
or with any reasonable expectation of a considered and expeditious outcome.” Id. ¶ 208. Even if
this Court were to conclude that the Tribunal committed serious error, which it does not, this
Court would lack the power to overturn the Tribunal’s award because the Tribunal “constru[ed]
or appl[ied] the contract and act[ed] within the scope of [its] authority.” Republic of Argentina,
9 211 F. Supp. 3d at 344 (quoting United Paperworkers Int’l Union, 484 U.S. at 38). The Tribunal
did not clearly exceed its authority in exercising jurisdiction over this dispute.
2. “Good order and fundamental fairness”
As discussed above, see supra section III.A., the Tribunal did not refuse to resolve
Libya’s request for a set-off, see Arbitration ¶ 921. Nor did it deny Libya’s proposed set-off
based on “good order and fundamental fairness,” as Libya claims. Pet’r’s Reply at 11, Dkt. 14.
The majority mentioned “fairness” as a consideration because the Tribunal had no jurisdiction
over the Libyan banks that held the guarantees. But it denied Libya’s set-off request because it
found (among numerous other reasons) that Al Hani had used all the advance payments for uses
that the contracts permitted. See Arbitration ¶ 900 (“[T]he advance payments . . . were utilized
by Al Hani to carry forward the several construction projects in the face of delayed or non-
payment” by the Libyan government). The Tribunal did not view its award as permitting a
double recovery for Strabag.
Libya again misconstrues the record when it asserts that the dissenting arbitrator
criticized the majority for rejecting Libya’s request for a set-off on fundamental fairness grounds.
See Libya’s Mem. at 20–21. To be sure, the dissent disagreed with the majority’s conclusion on
the set-off claim. And he noted that the majority’s decision to treat Strabag’s award and Libya’s
payment and bank guarantees separately was, in his view, “not conducive to ‘good order and
fundamental fairness,’ to which the majority—and indeed the entire Tribunal—aspired.”
Arbitration Dissent ¶ 44, at 12 (emphasis added). But it is improper to interpret this single
sentence as criticizing the majority for deciding the set-off issue based on its own sense of the
fairness.
10 Because the Tribunal did not deny the set-off based on a sense of good order and
fundamental fairness, but rather as a result of its reasoned interpretation of the relevant contracts,
the treaty, and international law, the Tribunal did not exceed its authority.
C. Requested Relief
None of Libya’s arguments in support of its set-off or other claims support vacatur,
modification, or correction of the Tribunal’s award. Thus, the Court will deny Libya’s petition
and grant Strabag’s cross-motion to confirm the award. See, e.g., Equitas Disability Advocs.,
LLC v. Daley, Debofsky & Bryant, P.C., 177 F. Supp. 3d 197, 219 (D.D.C. 2016). Because
neither party alleges that other litigation relating to this litigation is pending in any other court,
the Court will also deny Strabag’s request for a pre-judgment bond under Article VI of the New
York Convention. See Crytstallex Int’l Corp. v. Bolivarian Republic of Venezuela,
244 F. Supp. 3d 100, 108 n.11 (D.D.C. 2017) (denying a pre-judgment bond request as moot).
IV. CONCLUSION
For the reasons stated, it is
ORDERED that Libya’s Petition to Vacate the Arbitration Award is DENIED. It is
further
ORDERED that Strabag SE’s Cross-Motion to Confirm the Arbitration Award is
GRANTED IN PART as to the confirmation of the arbitration award and DENIED IN PART
as to the request that Libya post a bond during the pendency of this litigation.
The respondent is directed to file a proposed judgment amount with all pre-judgment
interest calculations performed as required under the Arbitration Award as of October 15, 2021.
Respondent shall file this on the docket on or before October 15, 2021, along with a proposed
11 judgment order, a sworn declaration by the respondent’s counsel who performs the calculations,
and an exhibit with the spreadsheet documenting the calculations.
SO ORDERED.
________________________ DABNEY L. FRIEDRICH United States District Judge September 30, 2021