State ex rel. Department of Administrative Services v. United Pacific Insurance

18 P.3d 491, 172 Or. App. 435
CourtCourt of Appeals of Oregon
DecidedFebruary 14, 2001
Docket9712-09675; CA A104354
StatusPublished

This text of 18 P.3d 491 (State ex rel. Department of Administrative Services v. United Pacific Insurance) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State ex rel. Department of Administrative Services v. United Pacific Insurance, 18 P.3d 491, 172 Or. App. 435 (Or. Ct. App. 2001).

Opinion

WOLLHEIM, J.

Plaintiff Oregon Waste Systems (OWS) filed this claim against United Pacific Insurance Company (UPIC) and the State of Oregon, seeking payment for work it performed as a subcontractor on a public contract for the removal and disposal of tires and tire shreds. Smith Technology Corporation (Smith), the primary contractor, provided a performance bond to the state on a form provided by UPIC, its surety. OWS seeks payment under the bond or, in the alternative, damages from the state for failure to require a sufficient bond. The state filed a cross-claim against UPIC for indemnification.

On cross-motions for summary judgment on all claims, the trial court ruled that OWS was not entitled to claim payment under the bond and granted UPIC’s motion for summary judgment against OWS. However, the court determined that the state’s practice of accepting performance and payment bonds from contractors for environmental clean-up projects obligated it to require Smith to provide the same kind of bond. The court granted OWS’s motion for summary judgment against the state. The trial court then issued a judgment under ORCP 67 B, awarding UPIC final judgment on all claims by OWS and awarding judgment to OWS on OWS’s claims against the state. OWS appeals, challenging the trial court’s granting of summary judgment to UPIC and asserting that it was entitled to summary judgment. The state cross-appeals, challenging the trial court’s granting of summary judgment to OWS on its claim against the state and seeking entry of judgment in its favor.

There are no factual disputes. We review the trial court’s rulings to determine whether UPIC was entitled to judgment as a matter of law on OWS’s claim on the bond and whether OWS was entitled to judgment as a matter of law on OWS’s claim against the state. ORCP 47 C; Jones v. General Motors Corp., 325 Or 404, 413, 939 P2d 608 (1996). We affirm the trial court’s judgment for UPIC. Because we conclude that the trial court erred as a matter of law with regard to OWS’s claim against the state, we reverse and remand for entry of judgment for the state.

[439]*439In December 1996, as part of a clean-up project of the Department of Environmental Quality (DEQ) and the Department of Transportation, the Oregon Department of Administrative Services (DAS) released a solicitation for bids on a contract for the removal and final disposition of tires and tire shreds on the subject private property, a former tire recycling and soil treatment facility. The solicitation specifically described the bid type as a “service contract” and stated that standard terms and conditions for service contracts were applicable. The solicitation required the successful bidder to furnish a “performance” bond in the amount of 100 percent of the total contract amount on a form prescribed by DAS.

The state awarded the contract for the removal and disposal of the tires (the Contract) to Smith as the successful bidder, for a contract price of $830,694. Smith provided a “performance” bond on a form provided by UPIC, as surety. Under the bond, if Smith performed the Contract promptly and faithfully, then the obligation on the bond would become null and void. In the event of a default by Smith in the performance of the contract, the bond provided that UPIC may

“promptly remedy the default, or shall promptly 1) Complete the Contract in accordance with its terms and conditions, or 2) Obtain a bid or bids for completing the Contract in accordance with its terms and conditions.”

The bond incorporates the Contract, which, in turn, includes a provision for prompt payment “to all persons furnishing services, equipment or supplies to Contractor for the performance of work.” The bond further provides that “no right of action shall accrue on this bond to or for the use of any person or corporation other than the Owner named herein * * *.” DAS is the named “owner” of the bond. Witnesses for the state testified that DAS viewed the Contract as a service contract and chose to accept the UPIC bond, although it did not expressly include payment protection.

Smith subcontracted with OWS, in a “service agreement” for nonhazardous waste disposal, for the “transportation and disposal” of the tires and tire shreds. OWS completed its work under the subcontract, but Smith did not pay OWS the full amount agreed to in the subcontract. OWS made a demand for payment on the performance bond, and [440]*440UPIC denied the claim, reasoning that the bond does not provide payment security to OWS. OWS subsequently filed the complaint in this proceeding, seeking payment on the bond, or in the alternative, damages from the state for its failure to require a sufficient bond. The trial court dismissed OWS’s claim on the bond but granted judgment to OWS on its claim against the state.

ORS chapter 279 governs the advertisement, bidding and award of “public contracts.” When a public contract is for a “public improvement,” ORS 279.029 requires that the successful bidder execute a “good and sufficient bond, to be approved by the public contracting agency, in a sum equal to the contract price for the faithful performance of the contract.” Although the statute says that the “good and sufficient” bond is for the “performance” of the contract, the parties agree that the bond required by ORS 279.029 is a performance and payment bond that guarantees not only that the contractor will perform the work but that it will pay any costs incurred in doing so. Under ORS 279.526, a person claiming to have supplied labor or materials for the prosecution of the work provided for in a public contract has a right of action against the bond of a contractor or subcontractor “as provided for in ORS 279.029” upon giving the required notice. It is under ORS 279.526 that OWS asserts its claim under the bond.

We first consider whether the Contract between the state and Smith was subject to the provisions of ORS 279.029(l)(b). It is agreed that the contract was a “public contract,” which is defined in ORS 279.011(6) as “any purchase, lease or sale by a public agency of personal property, public improvements or services other than agreements which are for personal service.” OWS contends that the Contract was a contract for a “public improvement,” and therefore subject to the bonding requirement of ORS 279.029. In the state’s view, the Contract was a service contract and therefore was not subject to the provisions of ORS 279.029(l)(b).

ORS 279.011(8) defines “public improvement” for purposes of the public contracting law to

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wiley Co. v. Home Indemnity Co.
326 P.2d 123 (Oregon Supreme Court, 1958)
Platt Electric Supply, Inc. v. JC Northwest, Inc.
967 P.2d 924 (Court of Appeals of Oregon, 1998)
Jones v. General Motors Corp.
939 P.2d 608 (Oregon Supreme Court, 1997)
Portland General Electric Co. v. Bureau of Labor & Industries
859 P.2d 1143 (Oregon Supreme Court, 1993)
Platt Electric Supply, Inc. v. JC Northwest, Inc.
976 P.2d 1186 (Court of Appeals of Oregon, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
18 P.3d 491, 172 Or. App. 435, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-department-of-administrative-services-v-united-pacific-orctapp-2001.