Platt Electric Supply, Inc. v. JC Northwest, Inc.

976 P.2d 1186, 159 Or. App. 328, 1999 Ore. App. LEXIS 419
CourtCourt of Appeals of Oregon
DecidedMarch 24, 1999
Docket96P-1093; CA A95274
StatusPublished
Cited by2 cases

This text of 976 P.2d 1186 (Platt Electric Supply, Inc. v. JC Northwest, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Platt Electric Supply, Inc. v. JC Northwest, Inc., 976 P.2d 1186, 159 Or. App. 328, 1999 Ore. App. LEXIS 419 (Or. Ct. App. 1999).

Opinion

LANDAU, P. J.

Respondents Platt Electric Supply, Inc. (Platt), and Adolph’s Electric (Adolph’s) petition for reconsideration of our decision in Platt Electric Supply, Inc. v. JC Northwest, Inc., 157 Or App 79, 967 P2d 924 (1998), arguing that our opinion is based on an incorrect understanding of the sequence of relevant events. We allow the petitions, withdraw our former opinion and dispose of the parties’ contentions as follows.

In Platt, we held that, because the Polk County Housing Authority (PCHA) had declared an emergency before awarding a contract on a public housing project, it was excused from bond requirements to which public contracting agencies ordinarily are subject. Platt and Adolfs contend that our opinion incorrectly assumed that PCHA declared an emergency before it awarded the contract. In actuality, they contend, PCHA awarded the contract first and declared an emergency afterwards, apparently intending its declaration to have retroactive effect. According to Platt and Adolph’s, because the emergency declaration occurred after the contract award, it can have no legal effect.

In its brief, Platt represented the undisputed facts to include a chronology that placed the declaration of an emergency before the contract award:

“1. In 1993 Polk County put out for bid the Independence Duplexes project * * *.
“2. Polk County is the owner of the property on which the project was to take place and the public agency which let the project.
“3. In response to its first solicitation for bids, Polk County did not get any bids from contractors financially able to provide a performance and payment bond that would protect Polk County and subcontractors from failures by the general contractor to perform or to pay subcontractors and material suppliers.
“4. Polk County elected not to rebid the project and instead declared an emergency in order to avoid requiring the general contractor to post a bond to protect Polk County from nonperformance by the general [332]*332contractor and from payment claims by any supplier or subcontractor working on the project.
“5. Cole Chaney, Inc. (Chaney) was awarded the project and was not required to post a bond.
“6. Chaney subcontracted with Adolph’s Electric (Adolph’s) to do the electrical work required to perform the Project. Platt contracted with the subcontractor, Adolph’s, to provide materials and supplies to Adolph’s for the performance of its electrical subcontract with the general contractor, Chaney, on the project.
“7. Chaney defaulted and failed to pay various subcontractors who then, in turn, did not pay various material suppliers.
“8. Adolph’s was one of the unpaid subcontractors * * *.
“9. Platt was one of Adolph’s unpaid suppliers * *

(Citations omitted.) Platt then argued that, notwithstanding the declaration of an emergency, PCHA remained liable, because it had failed to obtain a bond from Chaney. According to Platt, the declaration of an emergency did not relieve PCHA of its liability for failing to post a bond:

“Polk County did not require Chaney to post a bond. It knew Chaney was not financially strong enough to post the bond that was normally required as indicated in its resolution waiving ‘the requirement of a performance bond on account of such emergency, pursuant to ORS 279.029.’ Instead, it took a chance on Chaney. It declared an emergency pursuant to ORS 279.029(5) thereby waiving the bond requirements of the public contracting statutes.
“Where the public agency, in this case Polk County, declares an emergency and waives the bond requirements, the public agency and the officers authorizing the contract take a risk [of joint liability].”

Thus, as posed by Platt, the issue before us was whether the declaration of emergency had the effect of relieving PCHA of joint liability for failing to obtain a bond. Adolph’s, although joining in Platt’s contention that PCHA was liable for failing to obtain a bond, did not join in that particular argument.

[333]*333We took the facts as represented by Platt and held that, under ORS 279.025(5), the declaration did have the effect of excusing PCHA from obtaining a bond and from any liability for failing to do so. Platt, 157 Or App at 83. Now Platt argues that we misunderstood the sequence of events. According to Platt, although a declaration of emergency may have the effect of relieving a public agency of obtaining a bond, in this case it does not have that effect, because the declaration of emergency did not take place until after the contract award.

We certainly did misunderstand the sequence of events. We understood them to be as Platt had represented them in its statement of facts and in its arguments. Nevertheless, careful examination of the record does reveal that the emergency declaration followed the contract award. Ultimately, it is the court’s obligation to examine the record to determine the extent to which the parties have correctly represented the facts. Accordingly, we allow the petitions for reconsideration and determine whether the facts as we now correctly understand them require affirmance of the trial court’s judgment holding PCHA liable to Platt and Adolph’s because it failed to require a bond of the general contractor, which failed to pay for work performed on a public housing project.

We must first determine whether PCHA’s contract with Chaney was governed by the provisions of ORS chapter 279. ORS 279.011 provides the following definitions that are relevant to the questions at issue:

“(6) ‘Public contract’ means any purchase, lease or sale by a public agency of personal property, public improvements or services other than agreements which are for personal service.
“(7) ‘Public agency’ or ‘public contracting agency’ means any agency of the State of Oregon or any political subdivision thereof authorized by law to enter into public contracts and any public body created by intergovernmental agreement.
“(8) ‘Public improvement’ means projects for construction, reconstruction or major renovation on real property by or for a public agency. ‘Public improvement’ does not [334]*334include emergency work, minor alteration, ordinary repair or maintenance necessary in order to preserve a public improvement.”

ORS 279.015 provides that the bidding requirements of the chapter shall apply to “all public contracts,” except for those specifically exempted by ORS 279.015.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Platt Electric Supply, Inc. v. Van Horn
982 P.2d 1 (Court of Appeals of Oregon, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
976 P.2d 1186, 159 Or. App. 328, 1999 Ore. App. LEXIS 419, Counsel Stack Legal Research, https://law.counselstack.com/opinion/platt-electric-supply-inc-v-jc-northwest-inc-orctapp-1999.