Wiley Co. v. Home Indemnity Co.

326 P.2d 123, 213 Or. 493, 1958 Ore. LEXIS 210
CourtOregon Supreme Court
DecidedJune 4, 1958
StatusPublished
Cited by4 cases

This text of 326 P.2d 123 (Wiley Co. v. Home Indemnity Co.) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wiley Co. v. Home Indemnity Co., 326 P.2d 123, 213 Or. 493, 1958 Ore. LEXIS 210 (Or. 1958).

Opinion

SLOAN, J.

This is an action by plaintiff, a general contractor, to recover from defendant, a subcontractor’s bondsman, for the cost of materials supplied the subcontractor and for which judgment has been rendered against plaintiff and the judgment paid. The facts are these:

On May 20, 1949, plaintiff entered into a general contract with the Josephine county school district for *495 the construction of a high school at Cave Junction, Oregon. On June 4, 1949, plaintiff awarded a subcontract in the nature of a written memorandum agreement to one Lawrence L. Tennison, dba Tennison Electric Co., whereby Tennison agreed to “furnish all labor and materials and other items necessary to perform the electrical work in accordance with plans and specifications” as required by the general contract. The total consideration to be paid Tennison was $12,371.49. The sole method of payment set forth in this memorandum is as follows: “Monthly estimates on or about the 10th based on percentage of completion and as approved by Architect with 10% retained until 35 days after completion and acceptance.” On the same date as this agreement Tennison as principal and defendant as surety delivered to plaintiff two bonds. One of these was designated a “Labor and Material Payment Bond” and the other “Performance Bond.” In each bond plaintiff was obligee. Further reference to these bonds will be made later in this opinion.

Tennison entered upon the performance of this subcontract, and the performance was completed sometime in November or December of 1949 or January of 1950; of this the record is indefinite. On January 12, 1950, plaintiff paid to Tennison all the amount due him, including the retained percentage. Plaintiff completed his contract with the school district and was paid.

A short time thereafter the school district and plaintiff received notice of a claim in the amount of $1,177.15 by the General Electric Supply Corporation that Tennison had failed to pay to it on account of a bill for materials supplied to Tennison for use in performance of the contract. Defendant was notified of the claim and denied any responsibility. On or about May 12, *496 1950, the General Electric Supply Corporation filed action on this claim against plaintiff in the circuit court for Multnomah county, and summons and complaint were served upon plaintiff on that date. Defendant was notified of pendency of the claim and the defense of the action was tendered by plaintiff.

Defendant declined to defend and plaintiff proceeded to do so. This action resulted in judgment against plaintiff for $1,177.15, plus interest at the rate of 6 per cent per annum from January 30, 1950, until paid, and an additional sum of $250 attorneys’ fees and costs. Plaintiff immediately notified defendant of the entry of the judgment and that if defendant did not desire an appeal be prosecuted, plaintiff would be compelled to pay said judgment. No appeal was perfected, and on October 4, 1951, plaintiff paid $1,623.91 in full satisfaction of this judgment.

Thereafter plaintiff filed this action on defendant’s performance bond to recover such sum plus the sum of $250 expended by it for attorneys’ fees in the defense of the above action, together with court costs in the amount of $8. Plaintiff also seeks its attorneys’ fees in this action. The cause was tried to the court without the intervention of a jury, and after trial the court made findings of fact and, based thereon, concluded as a matter of law that the “defendant is not liable to plaintiff” and entered judgment accordingly.

It should be noted that between the time of the events just related and the trial in the lower court plaintiff’s corporate name was changed from Settergren-Wiley Co. to Wiley Co. and appropriate amendment and order were entered in the pleadings.

Plaintiff appeals and asserts three assignments of error. All are based upon the same contention that the findings do not support the judgment entered *497 and that such findings warrant a judgment for plaintiff.

The findings must sustain the judgment. Maeder Steel Products Co. v. Zanello, 109 Or 562, 220 P 155. And if, in fact, the findings do require a judgment for plaintiff the cause should he reversed and judgment entered accordingly. Neilson v. Title Guaranty & Surety Co., 81 Or 422, 159 P 1151.

The above statement of the chronological course of events leading to this action is a summarization of the court’s findings numbered I, II, III, and IV, which likewise find the corporate capacity of the parties and the execution of the contract between plaintiff and the school district. The other findings pertinent to the questions to be determined are as follows:

“V.
“That thereafter Mr. Lawrence L. Tennison, doing business as Tennison Electric Co., as subcontractor, entered into an agreement with the plaintiff to furnish and install all electrical wiring, fixtures and appliances required of the plaintiff by its certain prime contract, and that on or about the 4th day of June, 1949, the said Lawrence L. Tennison as principal, and the defendant as surety made, executed and delivered to the plaintiff two bonds, one entitled a performance bond in the penal sum of $12,500.00 conditioned that Lawrence L. Tennison, the subcontractor, and the principal of said bond would faithfully perform his said contract, and the other entitled a labor and material payment bond in the penal sum of $12,500.00, the condition of which bond was that Lawrence L. Tennison as principal should promptly make payment to all persons performing labor or supplying material in connection with the plaintiff.
“VI.
“That thereafter Lawrence L. Tennison entered upon the performance of his said subcontract and *498 completed the work of installing and furnishing electrical wiring, fixtures and appliances.
“VII.
“That Lawrence L. Tennison failed and neglected to pay General Electric Supply Corporation $1,177.15 which was due and owing for materials sold to Lawrence L. Tennison for use in the performance of Ms said subcontract with the plaintiff.
“VIII.
“That subsequent to the time at wMch said sum became owing by Tennison to General Electric Supply Corporation the plaintiff, without receiving any evidence that Tennison had paid his material bills and without inquiring of Tennison as to whether or not TenMson’s material bills were paid, paid to Tennison an amount retained by the plaintiff from Tennison, which amount was in excess of $1,177.15.”

Findings numbered IX, X, XI, XII, XIII, XIV, and XV all refer to the notification of defendant by plaintiff of the General Eleertic Supply Corporation claim, the filing of the action against plaintiff by it, notice and tender to defendant, the entry of the judgment, and its satisfaction heretofore related.

Findings numbered XVI and XVII are as follows:

“XVI.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gilbert Pacific Corp. v. State ex rel. Department of Transportation
822 P.2d 729 (Court of Appeals of Oregon, 1991)
GILBERT PACIFIC v. Dept. of Transp.
822 P.2d 729 (Court of Appeals of Oregon, 1991)
Fry v. Ashley
363 P.2d 555 (Oregon Supreme Court, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
326 P.2d 123, 213 Or. 493, 1958 Ore. LEXIS 210, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wiley-co-v-home-indemnity-co-or-1958.