Standard Accident Ins. v. Rose

234 S.W.2d 728, 314 Ky. 233, 1950 Ky. LEXIS 1059
CourtCourt of Appeals of Kentucky
DecidedDecember 5, 1950
StatusPublished
Cited by9 cases

This text of 234 S.W.2d 728 (Standard Accident Ins. v. Rose) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Standard Accident Ins. v. Rose, 234 S.W.2d 728, 314 Ky. 233, 1950 Ky. LEXIS 1059 (Ky. Ct. App. 1950).

Opinion

Judge Knight

Affirming in part, reversing in part.

On July 2, 1947, appellee, Green Rose, entered into a contract with E. L. Powers doing business as Powers Brothers Contraction Co., hereinafter referred to as Powers, whereby the latter agreed to construct two dwelling houses on a tract of land belonging to Rose in Jackson, Ky., at the agreed price of $11,575.00 for the two, under specifications filed with the contract. Powers was to furnish all labor and materials and was to complete the construction by December 15, 1947, and was to pay Rose $100 per month as liquidated damages for each month after that date until completed. To secure Rose, Powers was to execute bond with corporate surety in the amount of the contract. Upon signing of the contract, Rose’s attorney drew up a bond which was attached to the contract and specifications and turned over to the local agent of the Standard Accident Insurance Co. of Detroit, appellant herein. All were submitted to the appellant, which would not, or at least did not, accept the bond as drawn up by Rose’s attorney but instead executed and submitted to Rose on its regular forms used by it two bonds for $5800 each, one titled a “Performance Bond” and the other, a “Labor and Material Payment Bond.” After going over these bonds with his attorney, Rose accepted them in lieu of the bond which had been drawn up by his attorney and upon their acceptance he turned over to Powers the full amount called for in the contract, $11,575, and Powers began construction. He soon ran into financial difficulties and about October 21, 1947, ceased work on the houses and abandoned the contracts whereupon appellant was called upon as surety to make' [235]*235good on the contract. A dispute arose as to the extent of appellant’s liability and appellee filed this suit which in the final amended petition prayed judgment for $9000 necessary to complete the two houses in accordance with the specifications, $1000 for deterioration of the buildings resulting from the abandonment of the contract by Powers, and $600 for loss in rental for a period of six months from December 15, 1947, when they should have been completed. An amended petition also set out that Powers was indebted to certain named parties in various named amounts totaling $691.80 for materials used in construction of the buildings and that appellee should recover of appellant this sum for the benefit of those parties. After various motions and demurrers were filed and passed on, the issues were made up and the case was, by agreement, submitted to the judge without the intervention of a jury on the pleadings, exhibits, and the small amount of proof taken by appellee. Appellant took no proof. Whereupon a judgment was entered in favor of appellee in the sum of $10,200, being $9000 necessary to complete the buildings, $600 for their rental value until the time they could have reasonably been completed and $600 for deterioration in value of the partly constructed buildings. He was also given judgment for $691.80 for and on behalf of the material-men who had set up claims for materials furnished. Admitting its liability on the performance bond, appellant paid into court the sum of $5800 called for in that bond and subsequently paid to each of the materialmen the sums due each for materials used on the buildings and appealed from the balance of the judgment amounting to $4400 and that is the amount involved in this appeal.

_ It is appellant’s contention that the two bonds which it executed to protect appellee are completely separate; that it had done all it was required to do under the performance bond by paying the full amount of its obligation thereunder after Powers failed to live up to his contract; that it is liable on its labor and material payment bond only for labor and material used on the buildings and for which the contractor failed to pay and of which it was given proper notice under the contract; that having paid all of these it has no further liability under its bond and therefore the judgment [236]*236should be reversed to the extent of $4400 involved in this appeal.

It is the contention of the appellee that the owner intended the two bonds to protect his payment of the full contract since the total amount of the two about equalled the sum paid on the contract; that appellant knew this and intended to furnish the owner with bonds which would fully protect appellee in paying to the contractor the full amount of the contract price and therefore the two contracts should be considered together. He further contends that even separated and considered alone the labor and material payment bond should be construed as not being limited to labor and material furnished to the contractor and used on the job but for all labor and materials which the contractor was to furnish to complete the contract. He further contends that if the labor and material payment bond is not so construed, then, that it should be reformed to cover labor and materials which the contractor was to furnish to complete the contract. He further contends that appellant is estopped to deny that the two bonds fully protect the owner and give him broader coverage than the single bond submitted.

To set out the two bonds here involved in detail would unduly lengthen this opinion. It is only necessary to say that the performance bond, and denominated as such, contains the usual provisions of that character of bond, and the obligation of the bond is that “if the contractor shall promptly and faithfully perform said contract (referring to the contract between Powers and Rose), then this obligation shall be void, otherwise it shall remain in full force and effect.” We think this bond can have but one meaning and that is the natural one usually given to such bonds, that it guarantees that if the contractor defaults and fails to complete the contract, then the surety can itself complete the contract, as is authorized by the terms of the bond, or pay the full amount of its obligation thereunder of $5800, as it has done in this case. We think it is unnecessary to further consider this bond.

Since the principal dispute between the parties is the construction of the labor and material payment bond, it will be necessary to quote its more important provisions which follow:

[237]*237“Now, therefore, the condition of this obligation is such that if the Principal shall promptly make payment to all claimants as hereinafter defined, for all labor and material used or reasonably required for use in the performance of the contract, then this obligation shall be void; otherwise it shall remain in full force and effect, subject, however, to the following conditions:

“1. A claimant is defined as one having a direct contract with the Principal for labor, material or both, used or reasonably required for use in the performance of the contract, labor and material being construed to include that part of water, gas, power, light, heat, oil, gasoline, telephone service or rental of equipment directly applicable to the contract.

“2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ribeira & Lourenco v. Jackson Health Care Asso.
603 A.2d 976 (New Jersey Superior Court App Division, 1992)
Dukane Corp. v. Sides Construction Co.
302 N.W.2d 721 (Nebraska Supreme Court, 1981)
Cagle, Inc. v. Sammons
254 N.W.2d 398 (Nebraska Supreme Court, 1977)
Gallimore, Inc. v. Home Indemnity Co.
432 F. Supp. 434 (W.D. Virginia, 1977)
Modern Heating & Supply Co. v. Ohio Bank Building & Equipment Co.
451 S.W.2d 401 (Court of Appeals of Kentucky (pre-1976), 1970)
Continental Casualty Co. v. L. G. Wasson Coal Mining Corp.
407 S.W.2d 426 (Court of Appeals of Kentucky, 1966)
Standard Accident Ins. Co. of Detroit v. Rose
234 S.W.2d 728 (Court of Appeals of Kentucky (pre-1976), 1950)

Cite This Page — Counsel Stack

Bluebook (online)
234 S.W.2d 728, 314 Ky. 233, 1950 Ky. LEXIS 1059, Counsel Stack Legal Research, https://law.counselstack.com/opinion/standard-accident-ins-v-rose-kyctapp-1950.