Gallimore, Inc. v. Home Indemnity Co.

432 F. Supp. 434, 1977 U.S. Dist. LEXIS 16065
CourtDistrict Court, W.D. Virginia
DecidedMay 3, 1977
DocketCiv. A. 74-102
StatusPublished
Cited by4 cases

This text of 432 F. Supp. 434 (Gallimore, Inc. v. Home Indemnity Co.) is published on Counsel Stack Legal Research, covering District Court, W.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gallimore, Inc. v. Home Indemnity Co., 432 F. Supp. 434, 1977 U.S. Dist. LEXIS 16065 (W.D. Va. 1977).

Opinion

OPINION AND ORDER

DALTON, District Judge.

The plaintiff, Gallimore, Inc., a Virginia corporation, brought this action against The Home Indemnity Company, a New York corporation, seeking to hold The Home Indemnity Company liable on a contractor’s bond. Jurisdiction is predicated on diversity of citizenship and more than $10,000.00 in controversy. The facts have been stipulated and the matter submitted to the court for its determination.

On April 26,1972, Gallimore, Inc., entered into a general contract with the Montgomery County School Board for the construction of an elementary school. The contract between Gallimore and the School Board required a payment bond for each subcontractor equal to 50% of the subcontract, although it did not require the procurement of performance bonds. On May 18, 1972, Gallimore subcontracted the electrical work on the school project in the amount of $104,000.00 to Martin Electric, Inc. This subcontract required a 50% payment bond, although no performance bond was required. On May 19, 1972, pursuant to the bond requirements of the subcontract, Martin Electric obtained a labor and material payment bond in the amount of $52,000.00 from The Home Indemnity Company. According to the terms of this bond, Martin Electric was designated as the principal for payment, The Home Indemnity Company as surety, and Gallimore as obligee. Although a performance bond was never issued, a notation in the lower left hand comer of the bond stated that it was “ . . . issued simultaneously with another bond in favor of the general contractor conditioned for the full and faithful performance of the contract.” (Stipulation-Exhibit A). The relevant portion of the bond setting out the terms of liability provided:

NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that if the Principal shall promptly make payment to all claimants as hereinafter defined, for all labor and material used or reasonably required for use in the performance of the subcontract, then this obligation shall be void; otherwise it shall remain in full force and effect, subject, however, to the following conditions:
(1) A claimant is defined as one having a direct contract with the Principal for labor, material, or both, used or reasonably required for use in the performance of the contract, labor and material being construed to include that part of water, gas, power, light, heat, oil, gasoline, telephone service or rental of equipment directly applicable to the subcontract.
(2) The above-named Principal and Surety hereby jointly and severally agree with the Obligee that every claimant as herein defined, who has not been paid in full before the expiration of a period of ninety (90) days after the date on which the last of such claimant’s work or labor was done or performed, or materials were furnished by such claimant, may sue on this bond for the use of such claimant, prosecute the suit to final judgment for such sum or sums as may be justly due claimant, and have execution thereon. The Obligee shall not be liable for the payment of any costs or expenses of any such suit.

For this bond, Martin Electric paid The Home Indemnity Company a premium of *436 $520.00 which was based upon the standard rate of $5.00 per thousand for a 50% labor and material payment bond. The only other bond available was a 100% performance and payment bond for which a premium of $1,026.00 would have been charged, based on a rate of $10 per thousand on the first $100,000.00 and $4.50 per thousand on the excess. (Stipulation page 3).

In October of 1972, Martin Electric accepted a quotation from Virginia Melody and Sound, Inc., for $17,230.00 for a complete sound system for the project and issued a purchase order for that amount on October 10, 1972. (Stipulation page 3). Virginia Melody delivered’ material to the project site and submitted two invoices, totalling $421.00, the last of which was dated January 16, 1973. (Stipulation page 4). However, due to Martin Electric’s financial condition, Virginia Melody refused to proceed on the project without guarantee of payment from Gallimore.

As of May 25, 1973, Martin Electric had no workers on the job and Gallimore informed Martin Electric that if they did not return to the job as of June 8, 1973, their contract would be terminated and a new subcontractor would be hired. They failed to return on the 8th and their contract was terminated, and the R & M Electric Company was contracted with for completion of the electric subcontract. Gallimore then entered into an agreement with Virginia Melody for the furnishing of all labor, material, and equipment for the installation of a complete sound system. The agreed price of this contract was $16,809.00 which equaled the balance remaining in the Martin Electric-Virginia Melody agreement. In accordance with its contract, Virginia Melody was paid the, full amount of the subcontract through four payments by Gallimore.

Previously, early in 1973, the General Electric Supply Company agreed with Martin Electric to furnish the lighting fixtures required in the electrical subcontract, but after a problem arose as to the manner of payment, refused to ship the equipment except upon a purchase order directly from Gallimore as the general contractor. Gallimore agreed, and pursuant to the change orders, the General Electric Supply Company furnished the material to them, although installation was performed by Martin Electric until its cessation of work on the project on May 25,1973. (Stipulation pages 5, 6, 8). According to its orders, Gallimore actually paid the General Electric Supply Company $43,204.37.

Prior to Martin Electric’s default, Gallimore had become concerned about Martin Electric’s financial condition and contacted the Thomas Rutherford Bonding Insurance Company, an agency for The Home Indemnity Company, and received a response that Martin Electric was “bonded”, and this was interpreted by Gallimore to mean “that Gallimore need not worry if Martin Electric failed to perform or to pay its suppliers or laborers on the project.” (Stipulation page 4). Although the “vice president of Gallimore and the principal contact for the general contractor in all dealings with the subcontractor was of the impression that the bond written by The Home contained both the payment and the performance obligation”, no inquiry was made as to whether or not a performance bond existed, and none in fact had ever been issued. (Stipulation page 3).

Martin Electric has been adjudged bankrupt, and Gallimore is seeking to recover from The Home Indemnity Company the losses it incurred through Martin Electric’s inability to perform on its contracts. Plaintiff asserts that there are two grounds for recovery. First, he argues that by virtue of its actions The Home Indemnity Company is estopped to deny coverage. Second, he claims rights to subrogation, and in furtherance of this argument, he contends that the bond that was issued contained an express obligation of performance and that the performance obligation is also implied in the bond by virtue of the provisions of Va.Code Ann. § 11-23, which provides performance coverage in certain instances.

Regarding his first argument, the plaintiff contends that the defendant is estopped to deny coverage because of the notation appearing on the face of the bond indicat *437

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gross Construction Associates, Inc. v. Nagori Corp.
282 A.D.2d 673 (Appellate Division of the Supreme Court of New York, 2001)
Washington Post Co. v. Turner
708 F. Supp. 405 (District of Columbia, 1989)
Nationwide Insurance v. Patterson
331 S.E.2d 490 (Supreme Court of Virginia, 1985)
Dukane Corp. v. Sides Construction Co.
302 N.W.2d 721 (Nebraska Supreme Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
432 F. Supp. 434, 1977 U.S. Dist. LEXIS 16065, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gallimore-inc-v-home-indemnity-co-vawd-1977.