Sprague Electric Co. v. Maine Unemployment Insurance Commission

544 A.2d 728, 1988 Me. LEXIS 198
Supreme Judicial Court of Maine·Decided July 5, 1988·Published·Cited by 35 cases

Opinion

SCOLNIK, Justice.

The defendant, the Maine Unemployment Insurance Commission (“the Commission”), appeals from a judgment entered in the Superior Court, York County, sustaining the appeal of the plaintiff, Sprague Electric Company (“Sprague”), brought under M.R. Civ.P. 80C. Sprague had appealed from a decision of the Commission awarding unemployment compensation to a former employee, Linda Woodward.

Sprague manufactures electrical components at its plant in Sanford. Woodward was employed by Sprague from January 19,1973 until January 17,1986. Originally hired as a reeling machine operator, a position she held for more than seven years, Woodward was then promoted to the position of mechanic in the finishing department. As a finishing mechanic working the day shift, she was responsible for servicing as many as eight reeling machines. A reeling machine measures, straightens, [729]*729and packs parts for electrical components for shipping purposes. Each reeling machine is tended by an operator.

Woodward’s job as a mechanic required her to order parts for machines as well as to repair reeling machines. Mechanics received notices of machines in need of repair by consulting a blackboard on which machine operators listed machines that had broken down and gave the time of entry. Machines were repaired by mechanics in the order that notices were entered on the board.

In addition to her duties as a mechanic, Woodward was responsible for “set-up utility” in the production room. This job involved insuring that the production room never ran out of stock for the machines. Woodward ordered supplies and stock, picked up the ordered items from the stockroom and put away the stock. Performance of her duties as utility set-up required approximately seven hours per week.

During the period of August, 1985 to January, 1986, production at Sprague declined. This decline led to lay offs in the finishing department. By January, 1986, the department staff had been reduced to the point where two operators worked on six reeling machines where previously eight operators worked on eight machines. Although no operator worked on more than one machine at a given time, Woodward was responsible for keeping all six machines in working order.

Machine operators earned a higher rate of pay depending on whether their machines were running or were “down” (off production). When machines were running, operators had an opportunity to obtain a bonus rate for increased production. When a machine was down, the machine operator received only a flat hourly rate of pay. Specifically, an operator would only receive a flat rate of $5.00 per hour if a machine was not running or only running erratically. However, if a machine was running fairly well, the same operator would receive a bonus and could earn around $9.00 per hour. Consequently, Steve Griffin, the general foreman, testified that “there’s a lot of pressure” on the mechanics to keep the machines operating. Throughout 1985, Sprague began to phase out its reeling machines while increasing the use of integrated line machines, which incorporate the function of reeling machines. Integrated line machines perform five functions — straightening, stamping, heating, drying, and sleeving, followed by reeling. A reeling machine is fairly small and compact as compared to an integrated line machine, which Woodward described to the Commission to be “as long as this [hearing] room.” The reeling machine component is built onto the end of an integrated line machine. By January, 1986, Sprague had fifteen integrated lines in operation, with five mechanics tending them.

In October of 1985, Woodward began to work four-day rather than five-day weeks. Although Woodward was senior to other mechanics, those mechanics were working full, five-day weeks because they had received formal training on integrated line machines as well as reeling machines. By the time of her separation from employment, Woodward had already worked ten four-day weeks.

Between August, 1985 and January, 1986, Woodward was encouraged by her supervisor to use her “spare time” to become trained on the integrated line machines. It is unclear from the record how often she was able to find time for such training since such opportunities arose only as her regular duties permitted. Woodward attempted to train on the integrated lines in this manner throughout the latter part of 1985.

On one occasion Woodward applied for and obtained permission to work on the integrated lines on the third shift (11:00 p.m. to 7:00 a.m.) and worked one four-hour period before her regular shift began. There was an experienced integrated line mechanic on duty in another department to train her during those four hours. This was Woodward’s only uninterrupted training time on the machinery.

In early January of 1986, Roy Heath, finishing department foreman, decided to assign Woodward to two integrated lines in addition to her other duties. Both Heath [730]*730and Griffin felt that assigning Woodward to two of the integrated lines would force her to learn to repair this machinery. However, Heath (Woodward’s immediate supervisor) was on vacation the week of January 6th when Woodward was first assigned to the integrated lines. Accordingly, she was supervised that week by Griffin, and was supposed to receive assistance and on-the-job training from the lead mechanic, Lou MacDonald.1 It was her understanding that she was still responsible for the utility set-up as well as repairs to the six reeling machines.

On Monday, January 6, Woodward began to work on two integrated lines in addition to the six reeling machines to which she was already assigned. Woodward had been promised help in tending to her utility duties, but she received no assistance during her first week on the integrated lines. Owing to her lack of experience and training on this machinery, Woodward was unable to repair the integrated lines by herself. In addition, Woodward received many complaints from the reeling machine operators whose machines were down at various times during the week of January 6-10. The operators were upset that the machines were not being repaired by Woodward since inoperability resulted in a loss of “bonus time.”

As the week progressed, more machines were down for longer periods. After Wednesday, Woodward was unable to find other integrated line mechanics to help in the repair of her two integrated lines. The other mechanics told Woodward that they felt it was not their job to train her, that it was MacDonald’s responsibility. Beyond one or two hours on Monday, however, MacDonald was unavailable to supervise, train or assist her. As a result, Woodward complained to the group leader that she wasn’t getting training and couldn’t find the lead mechanic.

On Friday, January 10, only one integrated line was working. The other line and the six reeling machines had frequent breakdowns during the morning. Woodward testified that the other mechanics were “out straight” with their own work and would not come down to assist her. On her return from a dinner break, Woodward was asked by Griffin to go to the stockroom for reeling tape, try it on the number fifteen reeler machine, and make sure it was running properly.

After completing this task, she returned to find numerous notices on the blackboard that all her machines were down. The machine operators were angry and one operator was “screaming” at her for not having fixed their machines before working on the number fifteen reeler.

Free access — add to your briefcase to read the full text and ask questions with AI

Sprague Electric Co. v. Maine Unemployment Insurance Commission, 544 A.2d 728, 1988 Me. LEXIS 198 (Me. 1988).

544 A.2d 728 (Sprague Electric Co. v. Maine Unemployment Insurance Commission) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related