SPO Go Holdings, Inc. v. W & O Construction Co.

187 F. Supp. 3d 887, 2016 U.S. Dist. LEXIS 60661, 2016 WL 2607005
CourtDistrict Court, M.D. Tennessee
DecidedMay 6, 2016
DocketNo. 1-16-0010
StatusPublished
Cited by1 cases

This text of 187 F. Supp. 3d 887 (SPO Go Holdings, Inc. v. W & O Construction Co.) is published on Counsel Stack Legal Research, covering District Court, M.D. Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
SPO Go Holdings, Inc. v. W & O Construction Co., 187 F. Supp. 3d 887, 2016 U.S. Dist. LEXIS 60661, 2016 WL 2607005 (M.D. Tenn. 2016).

Opinion

MEMORANDUM

KEVIN H. SHARP, UNITED STATES DISTRICT JUDGE

Pending before the Court is Defendant W&O Construction Company, Inc.’s (“W&O’s”) Partial Motion to Dismiss (Docket No. 11), to which Plaintiff SPO Go Holdings, Inc. has responded in opposition (Docket Nosi 14 & 15). For the reasons that follow, W&O’s motion will be denied.

I.

The relevant facts, drawn from Plaintiffs Complaint and accepted as true for present purposes, are as follows:

From May 28, 2009 until June 12, 2015, Plaintiff owned the King’s Creek Golf Club (“the golf course”) in Spring Hill, Tennessee. The golf course is an Arnold Palmer Signature designed course, meaning that it was built to exacting specifications using particular materials, design principles, and product standards.

In 2014, the City of Spring Hill, Tennessee solicited bids for an ¡extension of the sewer line that runs parallel to Rutherford Creek and through the golf course. The bid was awarded to W&O and those parties entered into a Construction Contract (“the contract”). Additionally, Plaintiff and Spring Hill entered into a “Grant of Sewer Easement” agreement (“the easement”) wherein Plaintiff granted Spring Hill a 20-foot permanent gravity sewer line easement for the purpose of constructing, Operating, and maintaining the sewer line extension.

The contract provided that Phase I of the Project—the phase that affected the golf course—would be completed within 120 days. It also required that W&O restore all property affected by construction operations to its original condition, and agree to make acceptable arrangements with the owners of damaged property concerning repair or replacement. The contract also required that the golf course be restored by contractors familiar with the turf and irrigation systems. Additionally, the easement (to which B & O was not a signatory) provided that Spring Hill agreed to require its agents and contractors to restore the property to a condition similar or equal to that existing at the time construction began.

The contract was modified by an addendum providing that W&O would employ a qualified sod installer and irrigation company approved by Plaintiff and that all reworking, sod replacement, and other items of restoration would be performed at W&O’s expense. The Addendum also provided that Plaintiff would have final approval of all restoration work to be performed under the contract.

In November 2014, W&O was given the go-ahead to begin Phase I. Subsequent construction work required Plaintiff to close nine of the 18 holes on the golf course.

Without Plaintiffs consent, Spring Hill and W&O extended the deadline to complete Phase I of the project from March 2, 2015 to May 4, 2015. However, in March 2015, W&O reduced the number of daily workers on the site to three laborers and one equipment operator, with one piece of equipment. Phase I of the project was not completed by the extended deadline.

Upon completion of the project, W&O refused to use a golf course architect or Plaintiff-approved grading contractor to complete the restoration work, indicating [890]*890instead that it would perform the restoration itself. W&O also refused to use a qualified sod installer with experience in golf course restoration work.

After W&O failed to complete Phase I on time and refused to engage and pay the fees and expenses of Plaintiff-approved golf course restoration contractors, Plaintiff hired Turf Company, a business having significant experience restoring golf courses, to complete the restoration work at the golf course. Turf Company charged Plaintiff a total of $157,000, and Plaintiff demanded that amount from Spring Hill and W&O. Both refused.

Phase I was not completed until August 7, 2015. Because Phase I was not completed on time, Plaintiff suffered damages including, among other things, lost memberships and outings, numerous lost rounds of golf, and other expenses related to course maintenance.

As a result of the foregoing, Plaintiff filed a four-count Complaint, naming as Defendants both Spring Hill and W&O. With respect to the latter, Plaintiff alleges breach of contract and negligence. The negligence claim is the focus of W&O’s partial motion to dismiss.

II.

As a general rule, in considering a motion to dismiss under Federal Rule of Civil Procedure 12(b)(6), a court must take “all well-pleaded material allegations of the pleadings” as true. Fritz v. Charter Township of Comstock, 592 F.3d 718, 722 (6th Cir.2010). The factual allegations in the complaint “need to be sufficient to give notice to the defendant as to what claims are alleged, and the plaintiff must plead ‘sufficient factual matter’ to render the legal claim plausible, i.e„ more than merely possible.” Id. (quoting Ashcroft v. Iqbal, 556 U.S. 662, 129 S.Ct. 1937, 1949-50, 173 L.Ed.2d 868 (2009)).

A claim is plausible on its face if the “plaintiff pleads factual content that allows the court to draw the reasonable inference that the defendant is liable for the misconduct alleged,” and this entails showing “more than a sheer possibility that a defendant has acted unlawfully.” Ashcroft, 129 S.Ct. at 1949, Thus, “[w]hile a complaint attacked by a Rule 12(b)(6) motion to dismiss does not need detailed factual allegations, a plaintiffs obligation to provide the grounds of [its] entitlement to relief requires more than labels and conclusions, and a formulaic recitation of the elements of a cause of action will not do,” Bell Atl. Corp. v. Twombly, 550 U.S. 544, 555, 127 S.Ct. 1955, 167 L.Ed.2d 929 (2007) (internal citations and quotations omitted).

III.

W&O forwards two arguments in support of its motion to dismiss the negligence claim. First, W&O asserts that Plaintiff improperly relies upon the contract and the easement to create the alleged duty owed by W&O. Second, Plaintiffs negligence claim is barred by the economic loss doctrine. The Court is unpersuaded by either argument.

A.

“To establish negligence, one must prove; (1) a duty of care owed by defendant to plaintiff; (2) conduct falling below the applicable standard of care that amounts to a breach of that duty; (3) an injury or loss; (4) cause in fact; and (5) proximate, or legal,, cause.” McClung v. Delta Square Ltd. P’ship, 937 S.W.2d 891, 894-95 (Tenn.1996) (citing, McCall v. Wilder, 913 S.W.2d 150, 153 (Tenn.1995)). W&O argues that Plaintiff cannot meet these essential elements because it cannot establish a duty owed to it by W&O.

W&O characterizes Plaintiffs claim as “revolving around delay and/or failure to [891]*891meet a completion date,” and argues that its only “involvement on this project [was] limited to its scope of work under, the Construction Contract with Spring Hill” and there was “no duty of W&O to [Plaintiff] to complete its work by a specific deadline as the Construction Contract itself provides for extensions of time.” (Docket No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
187 F. Supp. 3d 887, 2016 U.S. Dist. LEXIS 60661, 2016 WL 2607005, Counsel Stack Legal Research, https://law.counselstack.com/opinion/spo-go-holdings-inc-v-w-o-construction-co-tnmd-2016.