Acuity v. McGhee Engineering, Inc.

297 S.W.3d 718, 2008 Tenn. App. LEXIS 799, 2008 WL 5234743
CourtCourt of Appeals of Tennessee
DecidedDecember 15, 2008
DocketM2007-02821-COA-R3-CV
StatusPublished
Cited by16 cases

This text of 297 S.W.3d 718 (Acuity v. McGhee Engineering, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Acuity v. McGhee Engineering, Inc., 297 S.W.3d 718, 2008 Tenn. App. LEXIS 799, 2008 WL 5234743 (Tenn. Ct. App. 2008).

Opinion

OPINION

ANDY D. BENNETT, J.,

delivered the opinion of the court,

in which RICHARD H. DINKINS, J., joined. PATRICIA J. COTTRELL, P.J., M.S., not participating.

*722 A surety filed suit against three engineering firms seeking to recover some of the surety’s losses on a project. The trial court granted summary judgment in favor of the engineers. We have concluded that the surety does have a right of action against the engineers based upon equitable subrogation and that the surety’s claims are not barred by res judicata or collateral estoppel. Because the consulting engineer had no contract with the project owner, the trial court did not err in granting summary judgment on contract claims against the consulting engineer. In all other respects, we reverse the trial court’s decision.

Factual Background

The dispute in this case arose out of the construction of a raw water intake and pumping station on the Cumberland River in Clarksville, Tennessee. The Logan Todd Regional Water Commission (“Logan Todd”), a special district created under Kentucky law that supplies water to three Kentucky counties, undertook the project. Logan Todd retained McGhee Engineering, Inc. (“McGhee”) as the project engineer. McGhee retained Strand Associates, Inc. d/b/a/ PEH Engineers (“Strand”) as consulting and design engineers. Logan Todd also retained E. Berkley Traughber & Associates, Inc. (“Traughber”) as the geotechnical engineer for the project. Logan Todd entered into a contract with Peters Contracting, Inc. (“Peters”) to be the general contractor on the project. In accordance with the contract between Peters and Logan Todd, Peters obtained a performance bond and a payment bond, which were issued by Acuity, A Mutual Insurance Company (“Acuity”). 1 Peters subcontracted with Tri-State Marine Construction (“Tri-State”) to perform the marine construction work. Tri-State was to install pipelines in the bed of the river. Peters entered into a subcontract with Capitol Tunneling, Inc. (“Capitol”) to bore underground tunnels and install pipelines from the pumping station to the river embankment. The underground pipelines would connect to the underwater pipelines, allowing Logan Todd to pump water from the river to a reservoir or shore well near the pumping station.

Drawing 25, prepared by Strand and issued by McGhee, showed two parallel tunnels running from the base of the shore well and extending underground about 210 feet from the shore well. During construction, Peters advised McGhee and Strand of its desire to extend the tunnels only 190 feet from the shore well. The engineers, who now argue that this decision was a “means and methods” issue left to Peters’s discretion, did not object. Peters proceeded to extend the tunnels only 190 feet from the shore well. On October 10, 2002, as Tri-State was excavating into the river embankment to connect the underwater tunnels with the underground tunnels, the river embankment began sloughing. At this point, McGhee contacted Traughber, the geotechnical engineer, to discuss appropriate action to stop the sloughing and allow the project to continue. Based upon Logan Todd’s desire to continue the work, Traughber recommended putting tarps on the embankment to give Tri-State a few more weeks to finish its work. On February 27, 2003, a large portion of the embankment collapsed into the river.

Logan Todd declared Peters to be in default under the contract for failing to perform the work in accordance with the *723 contract documents and failing to adhere to the project progress schedule. Logan Todd made a claim under the performance bond for Acuity to complete the project, and Acuity made arrangements with another contractor to complete the work. At the time of Peters’s termination, there was less than $400,000 to be paid out of the total contact amount of $3,740,000. Acuity spent over $3,000,000 to complete the contract and satisfy claims under its bonds.

Tri-State Litigation

In April 2003, Tri-State filed suit against Acuity in federal district court asserting a claim under the payment bond. 2 Acuity filed a third-party complaint against Logan Todd, Capitol, and Peters Leasing Co. In February 2005, the federal district court denied Acuity’s request to join the engineers, McGhee, Strand, and Traughber, as third-party defendants. Acuity settled with Tri-State concerning its claims in October 2005. In May 2006, Acuity and Logan Todd entered into a settlement agreement concerning claims under the performance bond.

Current Litigation

Acuity filed the instant lawsuit in March 2005 against McGhee, Strand, and Traugh-ber (collectively, “Engineers”). Its original complaint included the assertion that Acuity was equitably subrogated to the rights of Logan Todd and alleged that Engineers were hable for negligent misrepresentation. Acuity filed an amended complaint in January 2007 in which it added claims for negligent preparation and issuance of plans and specifications, breach of Engineers’ contractual obligations to Logan Todd, and breach of obligations to the surety. After answering the amended complaint, Engineers filed motions for summary judgment. In granting these motions, the chancellor found that Acuity had “no right of action under the doctrine of equitable subrogation against the defendant engineers under the facts of this case” and that Acuity’s claims were barred by res judicata and/or collateral estoppel. The court further found that Acuity’s negligent misrepresentation claim failed as a matter of law because there was no justifiable reliance by Acuity on information supplied by Engineers.

Standard op Review

Summary judgments do not enjoy a presumption of correctness on appeal. Bell-South Adver. & Publ’g Co. v. Johnson, 100 S.W.3d 202, 205 (Tenn.2003). This court must make a fresh determination that the requirements of Tenn. R. Civ. P. 56 have been satisfied. Hunter v. Brown, 955 S.W.2d 49, 50 (Tenn.1997). We consider the evidence in the light most favorable to the non-moving party and resolve all inferences in that party’s favor. Godfrey v. Ruiz, 90 S.W.3d 692, 695 (Tenn.2002). When reviewing the evidence, we must determine whether factual disputes exist. If a factual dispute exists, we must determine whether the fact is material to the claim or defense upon which the summary judgment is predicated and whether the disputed fact creates a genuine issue for trial. Byrd v. Hall, 847 S.W.2d 208, 211 (Tenn.1993); Rutherford v. Polar Tank Trailer, Inc., 978 S.W.2d 102, 104 (Tenn.Ct.App.1998). Under Tenn. R. Civ. P. 56, the moving party must negate an element of the opposing party’s claim or establish an affirmative defense. Byrd, 847 S.W.2d at 215 n. 5.

*724 Analysis

I.

Equitable subrogation

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
297 S.W.3d 718, 2008 Tenn. App. LEXIS 799, 2008 WL 5234743, Counsel Stack Legal Research, https://law.counselstack.com/opinion/acuity-v-mcghee-engineering-inc-tennctapp-2008.