Commercial Painting Company INC. v. The Weitz Company LLC

CourtCourt of Appeals of Tennessee
DecidedMarch 11, 2022
DocketW2019-02089-COA-R3-CV
StatusPublished

This text of Commercial Painting Company INC. v. The Weitz Company LLC (Commercial Painting Company INC. v. The Weitz Company LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Commercial Painting Company INC. v. The Weitz Company LLC, (Tenn. Ct. App. 2022).

Opinion

03/11/2022 IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON February 16, 2021 Session

COMMERCIAL PAINTING COMPANY INC. v. THE WEITZ COMPANY LLC ET AL.

Appeal from the Chancery Court for Shelby County No. CH-06-1573 JoeDae L. Jenkins, Chancellor ___________________________________

No. W2019-02089-COA-R3-CV ___________________________________

This is the third appeal arising from a commercial construction project. Most recently, the case went to trial before a jury, which awarded the plaintiff subcontractor $1,729,122.46 in compensatory damages under four separate theories and $3,900,000.00 in punitive damages. The trial court further awarded the plaintiff pre- and post-judgment interest and attorney’s fees and costs. We conclude the economic loss rule is applicable to construction contracts negotiated between sophisticated commercial entities and that fraud is not an exception under the particular circumstances of this case. Because punitive damages and interest are not authorized under the parties’ agreement, those damages are reversed. The compensatory damages of $1,729,122.46 awarded for breach of contract are affirmed. The award of attorney’s fees incurred at trial are vacated for a determination of the attorney’s fees incurred in obtaining the compensatory damages award. No attorney’s fees are awarded on appeal. We therefore reverse in part, affirm in part, and vacate in part.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Reversed in Part; Affirmed in Part; Vacated in Part and Remanded

J. STEVEN STAFFORD, P. J., W.S., delivered the opinion of the court, in which D. MICHAEL SWINEY, C.J. and CARMA DENNIS MCGEE, J., joined.

Philip E. Beck, Atlanta, Georgia; Jeffrey C. Smith, Memphis, Tennessee; John A. Templer, Jr., Des Moines, Iowa, for the appellants, Federal Insurance Company (NJ), St. Paul Fire & Marine Insurance Company, and The Weitz Company, LLC.

Scott A. Frick, Memphis, Tennessee, for the appellees, Commercial Painting Company, Inc., and Liberty Mutual Insurance Company (MA).

Gregory L. Cashion, Nashville, Tennessee, for the Amicus Curae, Associated General

1 Contractors of America and Associated General Contractors of Tennessee, Inc. In support of Defendants/Appellants

OPINION

I. BACKGROUND This is the third appeal in this case. See Com. Painting Co., Inc. v. The Weitz Co., LLC, No. W2013-01989-COA-R3-CV, 2016 WL 3519015, at *1 (Tenn. Ct. App. June 20, 2016) (“Commercial Painting II”); Com. Painting Co. v. Weitz Co., LLC, No. W2013- 01989-COA-R3-CV, 2014 WL 6453799, at *1 (Tenn. Ct. App. Nov. 18, 2014) (“Commercial Painting I”). The genesis of this lawsuit is a contract dispute between general contractor, Defendant/Appellant The Weitz Company, Inc. (“Weitz”), and its dry- wall subcontractor, Plaintiff/Appellee Commercial Painting Company, Inc. (“Commercial Painting”). Around the end of 2003, Weitz entered into a contract (“the Prime Contract”) with the owner of the project to construct a continuing care retirement community (“the Project”). In connection with the Prime Contract, Weitz and its sureties (together with Weitz, “Appellants”), issued a payment bond that obligated them to pay for labor, materials, and equipment furnished for use in the performance of the Prime Contract. The payment bond, however, became void if Weitz made prompt payment for all sums due. The payment bond was properly registered.

In October 2003, Commercial Painting bid on the drywall portion of the project. Weitz decided to award the drywall work to Commercial Painting after receiving this bid. Eventually, Mark Koch, on behalf of Commercial Painting as its President, executed a subcontract with Weitz (“the Subcontract”) on November 1, 2004, with an effective date of September 28, 2004. At that time, Mr. Koch reviewed the terms of the Subcontract, made some changes to it, and initialed every page of the 93-page document.

The Subcontract establishes a “Subcontract Sum” of $3,222,400.00 as the agreed- upon price that Commercial Painting was entitled to in exchange for full performance on the Subcontract. The Subcontract referenced various drawings and specifications from the Prime Contract to which Commercial Painting’s work was required to adhere. In some areas, Commercial Painting was required to perform a Level 3 drywall finish, while in other areas a Level 5 drywall finish was required. Whether Commercial Painting actually performed at this level would become an issue of much dispute as the project progressed.

The Subcontract also required that Commercial Painting’s work be performed according to Weitz’s project schedule and authorized Weitz to add extra work to Commercial Painting’s scope of work. In order to do so, however, the Subcontract indicated that the work would be “authorized in writing in advance” by Weitz. The Subcontract also addressed the payment process and authorized Weitz to deduct from its payments to Commercial Painting any amount necessary to protect Weitz or the owner

2 from losses related to Commercial Painting’s untimely, defective, or non-conforming work. The Subcontract further provided that the Project schedule could be updated periodically to reflect actual job progress. But the Subcontract obligated Commercial Painting to provide sufficient crews, materials, and equipment to maintain or improve Weitz’s schedule and gave Weitz the authority to reschedule or re-sequence Commercial Painting’s work. Finally, the Subcontract contained the following provisions related to damages:

5.6 Adjustments to Subcontract Time [Commercial Painting] shall be entitled to an extension of the Subcontract Time and/or reimbursement for delay damages only to the extent that the [Weitz] actually receives an extension of time and/or reimbursement for delay damages under the Prime Contract for events pertaining to the [Commercial Painting’s] Work. Except to the extent of the foregoing passthrough rights, [Commercial Painting] hereby waives and releases [Weitz] from any and all Claims for such delay damages including without limitation Claims attributable to breach of contract or tort and whether caused by [Weitz], Owner or other persons for any reason or cause whatsoever, and regardless of whether any such delay or other conduct on the part of [Weitz], Owner or other person may be deemed unreasonable or was not contemplated by the parties. * * * 11.6 Contract Terms Control In no event shall [Weitz] be obligated to pay [Commercial Painting] any anticipatory profit or indirect, special, or consequential damages, however caused, and [Commercial Painting] hereby waives all such Claims. Without limiting the generality of the foregoing, [Commercial Painting] specifically agrees that it shall not be entitled to assert, and it hereby waives, any Claims in quantum meruit, interest on late payments, or any other measure of damages other than as specifically provided in items 11.4 and 11.5 above.

Item 11.4 governed termination of the relationship by Weitz for cause; this section generally entitled Commercial Painting to the unpaid balance on the Subcontract Sum minus Weitz’s expenses in completing the project.1 If these expenses exceeded the unpaid

1 Specifically, item 11.4 provides as follows:

11.4 Consequences of Termination for Cause

Upon termination of [Commercial Painting’s] continuing performance under the Agreement for cause, [Weitz] may without limitation of any other available remedies, proceed as follows: (i) direct [Commercial Painting] to immediately leave the site, but to give possession of all materials and supplies at the site and stored off-site, to [Weitz] for use in completing [Commercial Painting’s] work; in the event of such a directive to leave 3 balance, then Commercial Painting’s surety was obligated to pay the difference.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hensley v. Eckerhart
461 U.S. 424 (Supreme Court, 1983)
Tina Marie Hodge v. Chadwick Craig
382 S.W.3d 325 (Tennessee Supreme Court, 2012)
Betty Saint Rogers v. Louisville Land Company
367 S.W.3d 196 (Tennessee Supreme Court, 2012)
Baugh v. Novak
340 S.W.3d 372 (Tennessee Supreme Court, 2011)
Cameron General Contractors, Inc. v. Kingston Pike, LLC
370 S.W.3d 341 (Court of Appeals of Tennessee, 2011)
Baptist Memorial Hospital v. Argo Construction Corp.
308 S.W.3d 337 (Court of Appeals of Tennessee, 2009)
Rolen v. Wood Presbyterian Home, Inc.
174 S.W.3d 158 (Court of Appeals of Tennessee, 2005)
Sanford v. Waugh & Co., Inc.
328 S.W.3d 836 (Tennessee Supreme Court, 2010)
Sneed v. Board of Professional Responsibility
301 S.W.3d 603 (Tennessee Supreme Court, 2010)
Lincoln General Insurance Co. v. Detroit Diesel Corp.
293 S.W.3d 487 (Tennessee Supreme Court, 2009)
Jeremy Flax v. Daimler-Chrysler Corporation
272 S.W.3d 521 (Tennessee Supreme Court, 2008)
Concrete Spaces, Inc. v. Sender
2 S.W.3d 901 (Tennessee Supreme Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
Commercial Painting Company INC. v. The Weitz Company LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/commercial-painting-company-inc-v-the-weitz-company-llc-tennctapp-2022.