Cameron General Contractors, Inc. v. Kingston Pike, LLC

370 S.W.3d 341, 2011 WL 6740558, 2011 Tenn. App. LEXIS 683
CourtCourt of Appeals of Tennessee
DecidedDecember 21, 2011
DocketE2010-02291-COA-R3-CV
StatusPublished
Cited by3 cases

This text of 370 S.W.3d 341 (Cameron General Contractors, Inc. v. Kingston Pike, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cameron General Contractors, Inc. v. Kingston Pike, LLC, 370 S.W.3d 341, 2011 WL 6740558, 2011 Tenn. App. LEXIS 683 (Tenn. Ct. App. 2011).

Opinion

OPINION

D. MICHAEL SWINEY, J.,

delivered the opinion of the Court,

in which HERSCHEL P. FRANKS, P.J., and JOHN W. McCLARTY, J., joined.

Cameron General Contractors, Inc., a Nebraska corporation (“Cameron”), sued Kingston Pike, LLC, a Georgia limited liability company (“Kingston Pike”), for breach of a contract concerning the sale of *343 real property located in Knoxville, Tennessee. Prior to trial, Cameron elected to exercise its contractual right to terminate the contract, and the case proceeded to trial on the issue of damages. After a bench trial, the Trial Court entered its order finding and holding, inter alia, that the contract did not limit Cameron to the return of its earnest money, and granting Cameron a judgment against Kingston Pike for damages in the amount of $872,418.22, plus attorney’s fees of $137,656.56. Kingston Pike appeals to this Court. We find and hold that the contract at issue clearly and unambiguously provides that once Cameron chose to terminate the contract, Cameron’s sole remedy for Kingston Pike’s breach was a return of Cameron’s earnest money deposit. We, therefore, reverse the Trial Court’s October 28, 2010 order.

Background

In October of 2007, Cameron and Kingston Pike entered into a Real Estate Purchase Agreement (“the Contract”) for Cameron to purchase real property in Knoxville, Tennessee from Kingston Pike for development as a senior independent living facility. Under the terms of the Contract, Kingston Pike was to satisfy certain obligations prior to closing including, among other things, grading the site, creating a building pad, and constructing a common roadway.

In pertinent part, the Contract provided: 5. Contingencies. The contingencies described in Section 3, 4, 8 and 9 are for the benefit of [Cameron] and shall be satisfied (or waived) by [Cameron] in writing prior to Closing. These contingencies shall be satisfied (or waived) within ten (10) months from the Effective Date (subject to “Force Majeure Matters” as defined below), except as may be extended by written agreement between the parties, or [Cameron] shall be entitled to terminate this Agreement and receive a prompt refund of the Earnest Money from the Title Company. If and in the event the specific contingencies enumerated in the foregoing subsections are not met to [Cameron’s] reasonable satisfaction, [Cameron] may, at its option, terminate this Agreement without further obligation to [Kingston Pike] (other than with regard to obligations under this Agreement that expressly survive the termination of this Agreement) and the Title Company shall promptly return the Earnest Money to [Cameron]....
[[Image here]]
12. Seller’s Default. Subject to the terms and provisions of Section 34 of this Agreement, if the sale and purchase of the Property contemplated by this agreement is not consummated on account of [Kingston Pike’s] default or breach of any of the terms or conditions contained herein, [Cameron] may either (a) terminate this Agreement by written notice to [Kingston Pike] and to the Title Company whereupon [Cameron] shall receive a prompt refund of the Earnest Money and the parties shall have no further rights or obligations hereunder except for the obligations that expressly survive the termination of this Agreement, or (b) if [Kingston Pike] then owns the Property, [Cameron] shall have the right to file an action for specific performance.

The Contract contemplated that Kng-ston Pike would complete its site development obligations within a ten month deadline after the effective date of the Contract. After approximately twenty months had passed from the effective date of the Contract, Cameron filed this lawsuit alleging, among other things, that Kingston Pike had failed to complete its *344 site development obligations, and seeking, among other things, specific performance.

The Trial Court bifurcated the trial and first heard evidence concerning whether the delay penalty provided for in the Contract was enforceable. After the trial on this issue, the Trial Court entered its order on September 10, 2009 finding and holding, inter alia, that the delay penalty contained in the Contract constituted a penalty and was not enforceable against Kingston Pike, that Kingston Pike was in breach of the Contract, and that Cameron was entitled to specific performance.

The case proceeded to trial on the issue of damages suffered by Cameron as a result of Kingston Pike’s breach of the Contract. Prior to the start of trial, Cameron elected to exercise its contractual right to terminate the Contract. After the trial, the Trial Court entered its order on October 28, 2010 finding and holding, inter alia, that the Contract does not limit Cameron to either an award of specific performance or a return of its earnest money, and that Cameron was entitled to an award of damages in the amount of $872,418.22, plus attorney’s fees of $187,656.56. Kingston Pike appeals to this Court.

Discussion

While Kingston Pike raises multiple issues on appeal, we find three issues to be dispositive. We restate the issues as: 1) whether the Trial Court erred in finding Kingston Pike in breach of the Contract; 2) whether the Trial Court erred in awarding Cameron damages for breach of Contract; and, 3) whether the Trial Court erred in awarding Cameron attorney’s fees. Kingston Pike also requests an award of attorney’s fees on appeal. Cameron raises an issue on appeal regarding whether the Trial Court erred in holding that the delay penalty in the Contract was unenforceable, and also requests attorney’s fees on appeal.

Our review is de novo upon the record, accompanied by a presumption of correctness of the findings of fact of the trial court, unless the preponderance of the evidence is otherwise. Tenn. R.App. P. 13(d); Bogan v. Bogan, 60 S.W.3d 721, 727 (Tenn.2001). A trial court’s conclusions of law are subject to a de novo review with no presumption of correctness. S. Constructors, Inc. v. Loudon County Bd. of Educ., 58 S.W.3d 706, 710 (Tenn.2001).

As our Supreme Court has instructed:
“The cardinal rule for interpretation of contracts is to ascertain the intention of the parties and to give effect to that intention, consistent with legal principles.” Bob Pearsall Motors, Inc. v. Regal Chrysler-Plymouth, Inc., 521 S.W.2d 578, 580 (Tenn.1975); see also Christenberry [v. Tipton], 160 S.W.3d [487,] at 494 [ (Tenn.2005) ]. If the language of the contract is clear and unambiguous, the literal meaning controls the outcome of the dispute. Planters Gin Co. v. Fed. Compress & Warehouse Co., 78 S.W.3d 885, 890 (Tenn.2002).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Marina Kotova v. Thomas Kevin True
Court of Appeals of Tennessee, 2026
Shawn L. Keck v. E.G. Meek, Sr.
Court of Appeals of Tennessee, 2018

Cite This Page — Counsel Stack

Bluebook (online)
370 S.W.3d 341, 2011 WL 6740558, 2011 Tenn. App. LEXIS 683, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cameron-general-contractors-inc-v-kingston-pike-llc-tennctapp-2011.