Commercial Painting Company, Inc. v. The Weitz Company, LLC

CourtTennessee Supreme Court
DecidedSeptember 28, 2023
DocketW2019-02089-SC-R11-CV
StatusPublished

This text of Commercial Painting Company, Inc. v. The Weitz Company, LLC (Commercial Painting Company, Inc. v. The Weitz Company, LLC) is published on Counsel Stack Legal Research, covering Tennessee Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Commercial Painting Company, Inc. v. The Weitz Company, LLC, (Tenn. 2023).

Opinion

09/28/2023 IN THE SUPREME COURT OF TENNESSEE AT JACKSON November 9, 2022 Session

COMMERCIAL PAINTING COMPANY INC. v. THE WEITZ COMPANY LLC ET AL.

Appeal by Permission from the Court of Appeals Chancery Court for Shelby County No. CH-06-1573 JoeDae L. Jenkins, Chancellor ___________________________________

No. W2019-02089-SC-R11-CV ___________________________________

The economic loss doctrine generally precludes a contracting party who suffers only economic losses from recovering damages in tort. In Tennessee, the application of this doctrine is limited to products liability cases. In this appeal, we consider whether the economic loss doctrine should be expanded to apply outside the products liability context. A jury awarded compensatory and punitive damages to a drywall subcontractor in a suit against a general contractor under theories of breach of contract and tort. The Court of Appeals applied the economic loss doctrine to preclude the recovery of damages in tort in a suit between sophisticated commercial entities. The intermediate court, in part, affirmed the award of compensatory damages for breach of contract, dismissed the tort claim, and reversed the award for punitive damages. We hold the economic loss doctrine only applies in products liability cases and should not be extended to other claims.

Tenn. R. App. P. 11 Appeal by Permission; Judgment of the Court of Appeals Reversed; Judgment of the Trial Court Affirmed in Part; Remanded to the Court of Appeals

SHARON G. LEE, J., delivered the opinion of the Court, in which ROGER A. PAGE, C.J., and HOLLY KIRBY, J., joined. SARAH K. CAMPBELL, J., filed a dissenting opinion, in which JEFFREY S. BIVINS, J., joined.

Scott A. Frick, Memphis, Tennessee, for the appellant, Commercial Painting Company, Inc.

Philip E. Beck, Atlanta, Georgia, John A. Templer, Jr., Des Moines, Iowa, and Jeffrey C. Smith, Germantown, Tennessee, for the appellees, The Weitz Company, LLC, Federal Insurance Company, and St. Paul Fire & Marine Insurance Company. Gregory L. Cashion, Nashville, Tennessee, and Leah Pilconis, Arlington, Virginia, for the Amici Curiae Associated General Contractors of America and Associated General Contractors of Tennessee, Inc.

OPINION

I.

This case stems from a contract dispute between a general contractor, The Weitz Company, LLC, and its drywall subcontractor, Commercial Painting Company, Inc. Weitz was the general contractor on a multi-building retirement community in Shelby County. In December 2004, the parties entered into a contract for Commercial Painting to perform drywall work on the project.1 The contract included a schedule detailing the phases and timing of construction. Weitz agreed to pay Commercial Painting $3,222,400 for its work. Change orders later increased the amount to $3,315,189. The parties had various disputes as the project progressed.

By the end of the contract, Weitz had paid Commercial Painting twelve of its seventeen pay applications. Weitz refused to pay the remaining five applications, claiming they were submitted untimely and contained improper change order requests.

In August 2006, Commercial Painting sued Weitz2 and its sureties, Federal Insurance Company and St. Paul Fire & Marine Insurance Company, and The Village at Germantown in the Shelby County Chancery Court seeking $1,929,428.74 in damages for breach of contract, including attorney’s fees.3 Commercial Painting alleged that Weitz 1 The work included installation of exterior ceiling insulation; exterior wall metal framing; exterior wall insulation; light gauge metal partitions; gypsum board walls, ceilings, and soffits; and suspended ceilings. The contract, with an effective date of September 28, 2004, was signed by the president of Commercial Painting on November 1, 2004, and by Weitz’s representative on December 7, 2004. 2 The defendant named in the complaint’s caption was The Weitz Company, Inc., but the first paragraph of the complaint referenced the defendant as The Weitz Company-National. These entities are referred to herein collectively as “Weitz.” 3 Section 12.1 of the contract provides:

In the event it shall become necessary for either party to institute legal proceedings against the other party for recovery of any amounts due and owing under the Agreement, it is expressly agreed that the prevailing party in any such action shall be entitled to recover from the non-prevailing party all costs, including reasonable attorney’s fees, of pre-suit collection attempts, suit, and post judgment or settlement collection including those incurred on appeal.

-2- failed to properly sequence, coordinate, monitor, and inspect the work of the various subcontractors on the project, which caused Commercial Painting extra work and forced it to work in a more inefficient and costly manner. The complaint also included claims for payment under the performance bond issued by Weitz’s sureties, interest on retainage under section 66-11-144 of the Tennessee Code,4 unjust enrichment, enforcement of Commercial Painting’s mechanic’s and materialman’s lien, and interest and attorney’s fees under the Prompt Pay Act of 1991.5

Weitz answered and counterclaimed against Commercial Painting and its surety for “no event less than” $500,000 in damages for costs allegedly incurred on the project due to Commercial Painting’s delay and defective workmanship.

In a later amendment to its complaint, Commercial Painting asserted additional claims for fraud, intentional and negligent misrepresentation, rescission/reformation of the contract, and $10,000,000 in punitive damages. Commercial Painting alleged Weitz negotiated a six-month extension with the project owner before executing the contract with Commercial Painting, but the construction schedule attached to the contract did not reflect the extension. Commercial Painting also claimed Weitz signed the contract knowing the schedule was outdated by about eight months and that the actual length of the delay was eight to twelve months. Commercial Painting alleged that Weitz knew when it executed the contract that to make up for the delay, it would have to compress the construction schedule and hire extra workers to supplement the work of various subcontractors, including Commercial Painting’s drywall work. Commercial Painting also asserted that after negotiating the six-month extension with the project owner, Weitz issued an amended construction schedule that was “fraudulent and unrealistic” in order to earn an early completion bonus.6 According to Commercial Painting, Weitz continued to issue construction schedules that were unrealistic, and required the subcontractors to adhere to those schedules, never revealing the actual length of the extension until near the end of the project when it became clear that Weitz could not complete construction in time to earn the early completion bonus. Commercial Painting contended that Weitz improperly supplemented Commercial Painting’s work by falsely claiming Commercial Painting was not completing its work according to a schedule that Weitz knew contained false

4 Transferred to section 66-34-104 of the Tennessee Code by 2008 Public Acts, chapter 804, section 2, effective July 1, 2008. 5 Tenn. Code Ann. §§ 66-34-101 to -704. 6 The extension agreement negotiated by Weitz and the project owner included a bonus to Weitz of $8,597 for each day, up to forty-five days, that the project was completed early.

-3- information about the project completion date and that Weitz fraudulently charged Commercial Painting for the cost of the supplemental drywall work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dick Broadcasting Company, Inc. of Tennessee v. Oak Ridge FM, Inc.
395 S.W.3d 653 (Tennessee Supreme Court, 2013)
Lincoln General Insurance Co. v. Detroit Diesel Corp.
293 S.W.3d 487 (Tennessee Supreme Court, 2009)
Concrete Spaces, Inc. v. Sender
2 S.W.3d 901 (Tennessee Supreme Court, 1999)
McCarthy Well Co. v. St. Peter Creamery, Inc.
410 N.W.2d 312 (Supreme Court of Minnesota, 1987)
Sapp v. Ford Motor Co.
687 S.E.2d 47 (Supreme Court of South Carolina, 2009)
Quest Diagnostics, Inc v. MCI Worldcom, Inc
656 N.W.2d 858 (Michigan Court of Appeals, 2003)
Grams v. Milk Products, Inc.
2005 WI 112 (Wisconsin Supreme Court, 2005)
Shahrdar v. Global Housing, Inc.
983 S.W.2d 230 (Court of Appeals of Tennessee, 1998)
Indemnity Ins. Co. v. American Aviation
891 So. 2d 532 (Supreme Court of Florida, 2004)
Moransais v. Heathman
744 So. 2d 973 (Supreme Court of Florida, 1999)
Messer Griesheim Industries, Inc. v. Cryotech of Kingsport, Inc.
131 S.W.3d 457 (Court of Appeals of Tennessee, 2003)
Trinity Industries, Inc. v. McKinnon Bridge Co.
77 S.W.3d 159 (Court of Appeals of Tennessee, 2001)
Insurance Co. of North America v. Cease Electric Inc.
2004 WI 139 (Wisconsin Supreme Court, 2004)
Congregation of the Passion v. Touche Ross & Co.
636 N.E.2d 503 (Illinois Supreme Court, 1994)
Plourde Sand & Gravel Co. v. JGI Eastern, Inc.
917 A.2d 1250 (Supreme Court of New Hampshire, 2007)
United Textile Workers of America v. Lear Siegler Seating Corp.
825 S.W.2d 83 (Court of Appeals of Tennessee, 1990)
Lott v. SWIFT TRANSPORTATION COMPANY, INC.
694 F. Supp. 2d 923 (W.D. Tennessee, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
Commercial Painting Company, Inc. v. The Weitz Company, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/commercial-painting-company-inc-v-the-weitz-company-llc-tenn-2023.