Southern Systems, Inc. v. Torrid Oven Ltd.

105 F. Supp. 2d 848, 2000 U.S. Dist. LEXIS 10683, 2000 WL 1048539
CourtDistrict Court, W.D. Tennessee
DecidedJuly 25, 2000
Docket99-2089-DV
StatusPublished
Cited by12 cases

This text of 105 F. Supp. 2d 848 (Southern Systems, Inc. v. Torrid Oven Ltd.) is published on Counsel Stack Legal Research, covering District Court, W.D. Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Systems, Inc. v. Torrid Oven Ltd., 105 F. Supp. 2d 848, 2000 U.S. Dist. LEXIS 10683, 2000 WL 1048539 (W.D. Tenn. 2000).

Opinion

ORDER ON DEFENDANT’S MOTION TO STAY FOR ARBITRATION

DONALD, District Judge.

In this lawsuit plaintiff Southern Systems Incorporated (“SSI”), a subcontractor of defendant Torrid Oven Limited (“Torrid”), sued Torrid claiming that it was not paid for certain work that it performed on a conveyor system. Torrid counterclaimed asserting that SSI failed to properly perform the work on the convey- or system and that Torrid incurred substantial expense to correct the errors made by SSI. Torrid now seeks an order staying the lawsuit while the parties pursue arbitration.

This case has endured in the district court for nearly eighteen months since the *850 original complaint was filed by SSI on January 28, 1999. During this year and a half, the parties have engaged in extensive discovery and motion practice. Soon after service of the complaint, Torrid, on May 26, 1999, sought an extension of time to respond. After the district court granted that motion, Torrid filed a motion on June 16, 1999, asking the court to dismiss the lawsuit pursuant to Fed.R.Civ.P. 12(b)(2) for lack of jurisdiction over the person or, in the alternative, to dismiss the case based on the doctrine of forum non conve-niens. The motion was denied by the district court on August 2,1999.

In the interim, a number of depositions were taken by both parties. On May 18 and 19, 1999, SSI took the depositions of four Torrid employees: Jeff Muyshondt, President of Torrid; Craig Corcoran, Vice-President of Operations at Torrid; John Adamse, project manager of Torrid; and Helmut Meir, engineering manager for Torrid. Torrid then took four depositions over the course of two weeks, those of: Larry Linton, Vice-President of SSI; V.L. Patel, project engineer for SSI; Charles Van Pelt, project engineer for SSI; and Leon Linton, President of SSI.

On August 16, 1999, Torrid filed its answer to SSI’s complaint. Nowhere in the answer did Torrid assert that the dispute in this litigation was governed by an arbitration clause, nor did Torrid argue at that time that the court should stay proceedings while the parties engaged in arbitration. Torrid then served interrogatories and a request for production of documents on SSI on October 28, 1999, and answered SSI’s discovery requests on October 29, 1999, and December 13, 1999. Additional discovery continued to take place, with SSI taking the depositions of three Torrid employees on January 17-20, 2000, in Ontario, Canada, continuing a deposition of one of the employees on February 15-16, 2000, and taking the depositions of two additional Torrid employees on March 7-9, 2000. Torrid was no stranger to the deposition process, taking six more depositions between May 9, 2000, and May 18, 2000. In the meantime, Torrid filed a counterclaim against SSI on February 22, 2000, and a third party complaint against United States Fidelity & Guaranty Co., SSI’s surety, the same day. The present motion for stay of arbitration was not filed until June 16, 2000, less than one month prior to the discovery deadline of July 12, 2000, less than two months before the trial date of August 14, 2000, and nearly fifteen months after the complaint was filed.

ANALYSIS

The critical issue in this case is whether Torrid by participating in the litigation process has waived its right to arbitration.

Torrid seeks a stay of the present proceedings pending arbitration pursuant to an arbitration clause in a written proposal from SSI to Torrid which Torrid contends constitutes part of the contract between SSI and Torrid. 1 Torrid argues that the Federal Arbitration Act (“FAA”) governs and requires a stay of underlying litigation until arbitration has been held. 2 Section 3 of the FAA provides:

*851 If any suit or proceeding be brought in any of the courts of the United States upon any issue referable to arbitration under an agreement in writing for such arbitration, the court in which such suit or proceeding is pending, upon being satisfied that the issue involved in such suit is referable to arbitration under such an agreement, shall on application of one of the parties stay the trial of the action until such arbitration has been had in accordance with the terms of the agreement, providing the applicant for the stay is not in default in proceeding with such arbitration.

9 U.S.C. § 3. Torrid insists that the language of Section 3 is mandatory and that a court must grant a stay when any party requests it. See, e.g., In re H & M Charters v. Reed, 757 F.Supp. 859, 862 (S.D.Ohio 1991) (holding that the FAA does not allow for discretion by a district court, but rather mandates that the court order arbitration upon motion of either party). In response, SSI does not dispute the existence of an arbitration clause or the application of the FAA to the dispute, 3 but contends that Torrid has waived its right to arbitration.

There is a strong federal policy in favor of arbitration. See generally National Found, for Cancer Research v. AG. Edwards & Sons, Inc., 821 F.2d 772, 774 (D.C.Cir.1987) (citing Dean Witter Reynolds, Inc. v. Byrd, 470 U.S. 213, 218-24, 105 S.Ct. 1238, 84 L.Ed.2d 158 (1985)). The strong federal policy is based upon the goal of Congress to enforce terms of a contract rather than a preference for arbitration. See Dean Witter Reynold’s, Inc., 470 U.S. 213, 219, 105 S.Ct. 1238, 84 L.Ed.2d 158 (1985). Any doubts concerning arbitration should be resolved in favor of arbitration. See AT & T Technologies, Inc., 475 U.S. at 650, 106 S.Ct. 1415; Moses H. Cone Mem. Hosp. v. Mercury Constr. Corp., 460 U.S. 1, 24-25, 103 S.Ct. 927, 74 L.Ed.2d 765 (1983). Some courts have held that an order to arbitrate should not be denied unless the contractual arbitration clause clearly does not cover the dispute at issue. See, e.g., United Steelworkers of Am. v. Warrior & Gulf Navigation Co., 363 U.S. 574, 80 S.Ct. 1347, 4 L.Ed.2d 1409 (1960); see also AT & T Technologies, Inc. v. Communications Workers of Am. et. al., 475 U.S. 643, 106 S.Ct. 1415, 89 L.Ed.2d 648 (1986); Pearce v. E.F. Hutton Group, Inc., 828 F.2d 826 *852 (D.C.Cir.1987); Cash Converters USA, Inc. v. Burns, No. 99 C 146, 1999 WL 98345, at *6 (N.D.Ill. Feb.19,1999).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jonna v. Bitcoin Latinum
E.D. Michigan, 2024
Doe v. Piraino
M.D. Tennessee, 2024
Kenneth K. Altom, Jr. v. Capital Resorts Group, LLC
Court of Appeals of Tennessee, 2020
American General Home Equity, Inc. v. Kestel
253 S.W.3d 543 (Kentucky Supreme Court, 2008)
Rich v. Walsh
590 S.E.2d 506 (Court of Appeals of South Carolina, 2003)
J.C. Bradford v. Douglas Kitchen
Court of Appeals of Tennessee, 2002
Uwaydah v. Van Wert County Hospital
246 F. Supp. 2d 808 (N.D. Ohio, 2002)
Jericho Mgmt. Inc. v. Fidelity Nat. Title Ins. Company of Tennessee
811 So. 2d 514 (Supreme Court of Alabama, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
105 F. Supp. 2d 848, 2000 U.S. Dist. LEXIS 10683, 2000 WL 1048539, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-systems-inc-v-torrid-oven-ltd-tnwd-2000.