Southern Systems, Inc. v. Torrid Oven Ltd.

58 F. Supp. 2d 843, 1999 U.S. Dist. LEXIS 16913, 1999 WL 592228
CourtDistrict Court, W.D. Tennessee
DecidedAugust 2, 1999
Docket99-2089-DV
StatusPublished
Cited by3 cases

This text of 58 F. Supp. 2d 843 (Southern Systems, Inc. v. Torrid Oven Ltd.) is published on Counsel Stack Legal Research, covering District Court, W.D. Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Systems, Inc. v. Torrid Oven Ltd., 58 F. Supp. 2d 843, 1999 U.S. Dist. LEXIS 16913, 1999 WL 592228 (W.D. Tenn. 1999).

Opinion

ORDER DENYING DEFENDANT’S MOTION TO DISMISS

DONALD, District Judge.

Before this court is Defendant’s, Torrid Oven Limited, Rule 12(b)(2) motion to dismiss Plaintiffs, Southern Systems, Inc., breach of contract action for lack of personal jurisdiction. Alternatively, Defendant requests the court to dismiss Plaintiffs complaint under the doctrine of forum non conveniens. In its complaint, Plaintiff alleges that Defendant breached a contract for the design, fabrication and installation of a conveyor system and seeks compensatory damages, a sum for delay costs, interest on all past due amounts, and a declaratory judgment from this court adjudging that Plaintiff is not responsible for system operational problems allegedly caused by third party modifications to the conveyor system. Plaintiff opposes Defendant’s motion to dismiss on the grounds that Defendant has had sufficient contacts with the state of Tennessee to grant this court personal jurisdiction over it and that the doctrine of forum non conveniens is not applicable to the facts of this case. This court has subject matter jurisdiction over this case under the authority of 28 U.S.C. § 1332.

For the following reasons, the court denies Defendant’s motion to dismiss.

I. FACTS

Defendant, a Canadian corporation with its principal place of business in Ontario, Canada, entered into a contract with For-met Industries (“Formet”) to build and install a “turn-key” industrial oven at For-met’s facility in St. Thomas, Ontario in Canada. Pursuant to this contract, in March 1996, Defendant began negotiating with Plaintiff to have a conveyor system installed at the Formet facility. The conveyor system was intended to move the Formet chassis through the industrial oven. Plaintiff, an American corporation with its principal place of business in Memphis, Tennessee, submitted a proposal to Defendant during the latter part of March, 1996. On June 7, 1996, Defendant sent Plaintiff a letter of intent authorizing Plaintiff to begin designing, engineering and fabricating the conveyor system for the Formet project.

During the early months of 1997, Plaintiff began designing and fabricating the conveyor system. In late April, 1997, Plaintiff began installation of the conveyor system at Formet’s facility. Plaintiff began operating the conveyor system in November/December 1997 to allow Defendant to experiment with the system operation. In January 1998, Plaintiff began running frames for production and continued to test and adjust the conveyor system. On June 2, 1998, Defendant sent Plaintiff a letter indicating, that it was hiring another company to implement changes to the conveyor system. After Defendant began to experience operational problems with the conveyor system, it prevented Plaintiff from having access to the conveyor system. Defendant alleged that the operational problems resulted from Plaintiffs negligence and refused to pay Plaintiff the contracted amount for its services in designing, engineering and fabricating, and installing the conveyor system.

Defendant claims that Plaintiff is not entitled to payment under the contract because it failed to properly design and install the conveyor system. On the other *846 hand, Plaintiff claims that all system malfunctions resulted from the actions of the third party company that Defendant hired to implement changes to the conveyor system.

II. STANDARD

In the face of a challenge to personal jurisdiction over a defendant, the plaintiff has the burden to establish that such jurisdiction exists. American Greetings Corp. v. Cohn, 839 F.2d 1164, 1168 (6th Cir.1988). The weight of this burden depends in large part upon how the court chooses to proceed in making its determination concerning personal jurisdiction. If a district court decides to make a personal jurisdiction determination based solely upon the written material submitted by the parties, the plaintiff is “required only to make a prima facie case of jurisdiction, that is, he need only demonstrate facts which support a finding of jurisdiction in order to avoid a motion to dismiss.” Welsh v. Gibbs, 631 F.2d 436, 438 (6th Cir.1980) (internal citations and quotation marks omitted). Where the district court does not hold an evidentiary hearing on the question of personal jurisdiction, “the burden of the plaintiff is relatively slight.” American Greetings Corp. at 1169. The court should view all facts averred in the •pleadings and affidavits in a light most favorable to the plaintiff and not consider any conflicting facts offered by the defendant. Aristech Chem. Int’l Ltd. v. Acrylic Fabricators Ltd., 138 F.3d 624, 626 (6th Cir.1998).

If, on the other hand, the district court determines that the parties’ written submissions have raised issues of credibility or factual disputes requiring resolution, it may conduct a preliminary evidentiary hearing. Welsh at 439. Once this eviden-tiary hearing is held, the plaintiff must show “by a preponderance of the evidence that jurisdiction exists.” Id.

Although the parties do not raise or dispute the appropriate standard of review for a Rule 12(b)(2) motion, the court notes that there is some uncertainty in the case law as to the appropriate standard to use where some discovery has taken place, but no evidentiary hearing has been held. In Nationwide Mut. Ins. Co. v. Tryg Int’l Ins. Co., Ltd., 91 F.3d 790 (6th Cir.1996), the United States Court of Appeals for the Sixth Circuit stated that “[ajrguably, this Circuit has not expressly determined the appropriate burden of proof for cases in which the district court permits at least some discovery but does not conduct an evidentiary hearing before ruling on a 12(b)(2) motion to dismiss.” Nationwide Mut. Ins. Co. at 792. Although the Sixth Circuit found it unnecessary to decide that question in Nationwide Mut. Ins. Co. because the plaintiff was unable to satisfy the lesser burden of proof, it did provide the lower courts with some guidance when it stated “[w]ere it necessary to decide this question, we would be inclined to agree that the plaintiff need only establish a prima facie case that personal jurisdiction exists over the defendant in a case such as this.” Id. at 793.

In the case at hand, the parties have engaged in some discovery, but the court has not held an evidentiary hearing concerning the existence of personal jurisdiction over Defendant. Based upon the Sixth Circuit’s comments in Nationwide Mut. Ins. Co., the court concludes that Plaintiff is only required to satisfy the lesser burden of establishing a prima facie case of personal jurisdiction, i.e., demonstrating facts which support a finding of jurisdiction. See Third Nat’l Bank in Nashville v. WEDGE Group, Inc., 882 F.2d 1087, 1089 (6th Cir.1989).

III. DISCUSSION

A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Benton v. Cameco Corporation
375 F.3d 1070 (Tenth Circuit, 2004)
Norcold, Inc. v. GREG LUND PRODUCTS LTD.
109 F. Supp. 2d 819 (S.D. Ohio, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
58 F. Supp. 2d 843, 1999 U.S. Dist. LEXIS 16913, 1999 WL 592228, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-systems-inc-v-torrid-oven-ltd-tnwd-1999.