Southern Constructors Group, Inc. v. Dynalectric Company, Defendant-Third Party v. Allen R. Boudreaux, Third Party

2 F.3d 606, 27 Fed. R. Serv. 3d 504, 1993 U.S. App. LEXIS 24691, 1993 WL 342672
CourtCourt of Appeals for the Third Circuit
DecidedSeptember 27, 1993
Docket93-3252
StatusPublished
Cited by160 cases

This text of 2 F.3d 606 (Southern Constructors Group, Inc. v. Dynalectric Company, Defendant-Third Party v. Allen R. Boudreaux, Third Party) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Constructors Group, Inc. v. Dynalectric Company, Defendant-Third Party v. Allen R. Boudreaux, Third Party, 2 F.3d 606, 27 Fed. R. Serv. 3d 504, 1993 U.S. App. LEXIS 24691, 1993 WL 342672 (3d Cir. 1993).

Opinion

WIENER, Circuit Judge:

This ease illustrates the preclusive consequences flowing from failure to provide proper notice of a possible theory of recovery. Plaintiff-Appellant Southern Constructors Group, Inc. (“Southern”) sued Defendant-Appellee Dynalectric Company under various claims that were all predicated on the existence of a contract. The case was eventually submitted to arbitration. After receiving notice that the arbitration panel had failed to find a contract, Southern attempted to switch to a quasi-contract theory of recovery grounded in quantum meruit. The district court held that Southern had waived these claims by failing to include them within any of its original or amended complaints or even in the pretrial order. Southern appeals this conclusion. Southern also appeals the district court’s refusal to grant it leave to amend its complaint to add the quasi-contract claim. Concluding that the district court properly found waiver and did not abuse its discretion in refusing to allow amendment of the complaint to include the waived claims, we affirm.

*608 I

FACTS AND PROCEEDINGS

This case arises out of events following the-bankruptcy of MMR Holding Company, Inc. (“MMR”), a large national electrical and mechanical contractor. MMR’s bankruptcy led to default on all of its bonded work, which in turn placed responsibility for completion of this work on MMR’s surety, Aetna Casualty and Surety Company (“Aetna”). Allen R. Boudreaux, a former vice-president of MMR and owner and president of Southern, contacted Dynalectric about acquiring the contracts for completing all of MMR’s electrical work from Aetna. What transpired next is the subject matter of the present suit. Bou-dreaux claims that his expertise and connections led to the awarding of approximately $120 million of completion contracts to Dyna-lectric, and that Southern and Dynalectric entered into an agreement to split the profits of these contracts 80% to Dynalectric and 20% to Southern. Disputing that version of the facts, Dynalectric claims that it broke off negotiations with Southern before a contract was formed because it had learned that several of Boudreaux’s representations were inaccurate and that Southern was merely a shell company without any track record or employees.

Southern brought suit against Dynalectric in August of 1990. In the second amended complaint, the operative one for this litigation, Southern alleged that Dynalectric breached its contractual and fiduciary duties, and engaged in unfair trade practices and fraud. Southern’s claims included the standard prayer that it be awarded “any other just and equitable relief this Court may deem appropriate.” All of the claims were apparently predicated on proof of the existence of a contract between Southern and Dynalec-tric. 1 When extensive discovery was com-píete it became clear that the existence of the contract turned on the enforceability of a draft agreement containing an arbitration provision. Thus Southern faced the prospect of submitting to two separate proceedings — a jury trial to determine the existence of a contract; and then, only if a contract were found, an arbitration proceeding to determine whether damages were due under that contract.

Instead of incurring the costs and delays of both a trial and an arbitration proceeding, Southern and Dynalectric agreed to submit all issues in this dispute to arbitration. 2 The agreement to arbitrate provided, inter alia, that an earlier pretrial order confected by Southern and Dynalectric would control the arbitration “to the extent practicable,” and that the first stage of the arbitration would consider only whether a contract existed. If no contract were found the arbitration would be over and either party could seek to confirm or appeal the decision of the arbitration panel. Only if a contract were found to exist would the arbitration- proceed to the second stage, determining whether and to whom damages were owed under the various contractual claims.

The arbitration panel conducted four days of formal hearings at which the parties presented numerous witnesses, depositions, and exhibits. In its initial decision the majority of the arbitration panel found that no contract existed between Southern and Dynalec-tric. Only after it learned of this decision did Southern raise the issue of its entitlement to recover under a quasi-contract theory. Southern raised that issue by filing a Motion to Reconsider with the arbitration panel. The majority of the panel concluded that this motion raised issues beyond the scope of the panel’s authority and accordingly refused to reconsider the decision. 3 Dynalectric filed a *609 Motion to Confirm the Arbitration Award, which was granted by the district court.

Southern filed a timely motion with the district court to reconsider its decision confirming the arbitration award. In its motion Southern contended that the district court should hear the quasi-contract issues because the arbitration panel refused to resolve those claims. The district court reviewed the amended complaint and pretrial order, but concluded that Southern had waived the quasi-contract claims by failing to raise them in a timely manner. The district court subsequently entered judgment for Dynalectric confirming the arbitration award.

After entry of judgement Southern filed a timely motion pursuant to Fed.R.Civ.P. 59(e) to vacate the judgment and to grant leave to Southern to file a third amended complaint under Fed.R.Civ.P. 15. The third amended complaint would have added Boudreaux as a party plaintiff and would have included quasi-eontractual claims. The district court denied this motion concluding that: 1) it was correct in finding that Southern had waived the quasi-contract claims by failing to raise them until after it lost its case at arbitration; and 2) granting the motion would be unfairly prejudicial to Dynalectric in subjecting it to renewed litigation when Dynalectric had a reasonable and justifiable expectation that the arbitration had conclusively resolved its dispute with Southern. Southern timely appealed.

II

ANALYSIS

Southern advances two arguments to challenge the district court’s entry of judgment and refusal to allow Southern to amend its complaint. First, Southern argues that the district court erred when it found that the quasi-contract claims had been waived. In short, Southern argues that the claims were implicitly included (and thus not waived) within the relevant pleadings. Second, Southern contends that the district court abused its discretion in refusing to grant Southern leave to amend its complaint to add the quasi-contract claims. We analyze each of these arguments in turn.

A Waiver and Notice Pleading

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2 F.3d 606, 27 Fed. R. Serv. 3d 504, 1993 U.S. App. LEXIS 24691, 1993 WL 342672, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-constructors-group-inc-v-dynalectric-company-defendant-third-ca3-1993.