Song & Song Corporation, and Jin Y. "Jim" Song, Individually v. Fine Art Construction Company, LLC

CourtCourt of Appeals of Tennessee
DecidedJune 14, 2012
DocketW2011-01708-COA-R3-CV
StatusPublished

This text of Song & Song Corporation, and Jin Y. "Jim" Song, Individually v. Fine Art Construction Company, LLC (Song & Song Corporation, and Jin Y. "Jim" Song, Individually v. Fine Art Construction Company, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Song & Song Corporation, and Jin Y. "Jim" Song, Individually v. Fine Art Construction Company, LLC, (Tenn. Ct. App. 2012).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT MEMPHIS April 18, 2012 Session

SONG & SONG CORPORATION, and JIN Y. “JIM” SONG, Individually v. FINE ART CONSTRUCTION COMPANY, LLC, ET AL.

Direct Appeal from the Chancery Court for Shelby County No. CH-07-02364, Part II Arnold Goldin, Chancellor

No. W2011-01708-COA-R3-CV - Filed June 14, 2012

Property owner hired a general contractor to perform construction work on a commercial building. The parties subsequently discovered that when the building was originally constructed, there were no fire dampers installed in the ductwork. The contractor performed the additional work necessary to install the missing fire dampers, but when the work was completed, the property owner refused to pay the amount invoiced by the contractor for the additional work. Both parties asserted that the other had breached the contract. Following a two-day bench trial, the trial court ruled in favor of the contractor and awarded her a judgment for the unpaid balance and other damages. The property owner appeals. We affirm as modified.

Tenn. R. App. P. 3; Appeal as of Right; Judgment of the Chancery Court Affirmed as Modified and Remanded

A LAN E. H IGHERS, P.J., W.S., delivered the opinion of the Court, in which H OLLY M. K IRBY, J., and J. S TEVEN S TAFFORD, J., joined.

Kevin A. Snider, Germantown, Tennessee, for the appellants, Song & Song Corporation and Jin Y. “Jim” Song, Individually

Roscoe A. Feild, Steven R. Walker, Memphis, Tennessee, for the appellees, Fine Art Construction Company, LLC, et al OPINION

I. F ACTS & P ROCEDURAL H ISTORY

Song & Song Corporation owns property located on Winchester Road in Memphis, Tennessee. The president of Song & Song Corporation is Jin Y. “Jim” Song, and he and his wife are its sole owners. In 2005, Mr. Song hired a general contractor to construct a commercial building on the property. However, the contract was only for the construction of the “shell” of the building and the completion of its top floor. The interior of the building’s first floor was to remain unfinished. The contract work was completed around February of 2007, and Mr. Song began operating an office on the second floor of the building.

In May 2007, Mr. Song obtained a quote from the original contractor of $105,000 for the completion of the unfinished first floor. Mr. Song then asked for a bid from another general contractor, Tae Young “Chris” Shin, who was an acquaintance from the Korean community and a close friend of Mr. Song’s wife. Ms. Shin had just recently obtained her general contractor’s license, in April 2007, and Mr. Song had assisted her in preparing documents for the application process. Mr. Song provided Ms. Shin with the detailed bid from the previous contractor in order to identify the scope of the work involved. Ms. Shin agreed to complete the unfinished first floor of Mr. Song’s building for $90,000, and the parties entered into a written contract to that effect on June 20, 2007.1 Ms. Shin began work shortly thereafter, and by all accounts, everything went smoothly for the next few weeks.

On August 2, 2007, a Shelby County Code Enforcement Officer issued a stop work order on the site. Shelby County Code requires that fire dampers2 be installed inside the ductwork of a multi-tenant commercial building, and two separate mechanical inspections must be performed by Code Enforcement Officers during the installation process. At Mr. Song’s building, fire dampers were required to be placed inside the ductwork that was above the first floor ceiling, between the first and second floors. The stop work order was issued because the necessary inspections of the fire dampers had not taken place, and yet the first

1 The contract was between Song & Song Corporation and Fine Art Construction, LLC, of which Ms. Shin is the sole owner and president. For ease of reference, we will refer to the parties simply as Mr. Song and Ms. Shin for much of this opinion, just as the parties have done in their briefs. 2 According to the testimony at trial, during a structure fire, a fire damper prevents the fire from spreading through the ductwork. Ductwork would normally attract smoke and fire because it moves air. A fire damper has a band similar to a heat strip, and in the event of a fire, the strip reaches a certain temperature and causes the fire damper to close. The fire damper then terminates the air flow through the ductwork and isolates the fire.

-2- floor ceiling had already been covered with sheetrock, precluding access to the ductwork above the ceiling. It was later discovered that fire dampers had never been installed in the ductwork.

Ms. Shin informed Mr. Song about the stop work order and the lack of fire dampers. She claimed that the fire dampers should have been installed by the previous contractor who began the process of installing the ductwork. Ms. Shin, and her subcontractor, ultimately installed the necessary fire dampers and obtained the necessary approval of them from the Code Enforcement Officer on September 21.

Mr. Song paid the $90,000 contract price prior to the completion of the work, and he also paid a total of $8,904.90 toward invoices he received for the additional work. On September 25, Mr. Song gave Ms. Shin a written “Incentive Agreement,” which stated that Song & Song Corporation promised to pay her $5,000 if she obtained a temporary use and occupancy permit for the first floor by October 15, so that Mr. Song’s tenants could begin to move in. Ms. Shin completed her work and passed the mechanical, electrical, and plumbing inspections by October 10. However, Mr. Song fired Ms. Shin on October 11, before she could obtain the final inspection necessary to obtain the aforementioned permit. Mr. Song obtained the permit himself on October 16. Ms. Shin submitted a final invoice to Mr. Song after she was terminated, which stated that he still owed an additional $16,927.28 for materials and additional work that was completed prior to her termination.

Mr. Song, individually, along with Song & Song Corporation, filed this lawsuit against Ms. Shin and Fine Art Construction, LLC on December 4, 2007. He alleged that he had experienced “numerous and continuing problems with the work that Defendants performed as well as with the time line of the work being completed.” The complaint mentioned the fact that the work had failed to clear a mechanical inspection, requiring the removal of sheetrock and the installation of fire dampers. The complaint alleged that the resulting delay had caused him to lose a commercial tenant and incur substantial damages. The complaint alleged breach of contract/warranty, fraud/misrepresentation, violation of the Tennessee Consumer Protection Act, “money had and received,” unjust enrichment, and negligent/reckless acts or omissions. It sought $100,000 in compensatory damages, treble damages, $300,000 in punitive damages, and attorney’s fees, among other things.

Ms. Shin and her construction company filed an answer and a countercomplaint, alleging that she had completed the contract work and the additional work, for which Mr. Song had allegedly promised to pay. Ms. Shin alleged that Mr. Song had improperly terminated her after she completed her work, rendering it impossible for her to obtain the final inspection within the incentive payment period. Thus, Ms. Shin claimed that she was entitled to damages for the outstanding invoice balance, the incentive bonus, and attorney’s

-3- fees.

A two-day bench trial was held in May 2011. The written contract entered into by the parties listed various items to be completed, and, relevant to this appeal, it stated, “The heating and air will be completed by the installation of a five ton condenser, duct-work, and restroom exhaust fan.” However, it did not mention fire dampers.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hughes v. Metropolitan Government of Nashville & Davidson County
340 S.W.3d 352 (Tennessee Supreme Court, 2011)
Varnadoe v. McGhee
149 S.W.3d 644 (Court of Appeals of Tennessee, 2004)
Keyt v. Keyt
244 S.W.3d 321 (Tennessee Supreme Court, 2007)
Ali v. Fisher
145 S.W.3d 557 (Tennessee Supreme Court, 2004)
Bogan v. Bogan
60 S.W.3d 721 (Tennessee Supreme Court, 2001)
Walker v. Sidney Gilreath & Associates
40 S.W.3d 66 (Court of Appeals of Tennessee, 2000)
Realty Shop, Inc. v. RR Westminster Holding, Inc.
7 S.W.3d 581 (Court of Appeals of Tennessee, 1999)
State v. Thompson
197 S.W.3d 685 (Tennessee Supreme Court, 2006)
Security Fire Protection Co. v. Huddleston
138 S.W.3d 829 (Court of Appeals of Tennessee, 2003)
Larsen-Ball v. Ball
301 S.W.3d 228 (Tennessee Supreme Court, 2010)
Union Carbide Corp. v. Huddleston
854 S.W.2d 87 (Tennessee Supreme Court, 1993)
Watson v. Watson
196 S.W.3d 695 (Court of Appeals of Tennessee, 2005)
Galbreath v. Harris
811 S.W.2d 88 (Court of Appeals of Tennessee, 1990)
Wells v. Tennessee Board of Regents
9 S.W.3d 779 (Tennessee Supreme Court, 1999)
Estate of Adkins v. White Consolidated Industries, Inc.
788 S.W.2d 815 (Court of Appeals of Tennessee, 1990)
Co-Operative Stores Co. v. United States Fidelity Guaranty Co.
137 Tenn. 609 (Tennessee Supreme Court, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
Song & Song Corporation, and Jin Y. "Jim" Song, Individually v. Fine Art Construction Company, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/song-song-corporation-and-jin-y-jim-song-individua-tennctapp-2012.