Smith v. Dewitt and Associates, Inc.

279 S.W.3d 220, 2009 Mo. App. LEXIS 108, 2009 WL 474411
CourtMissouri Court of Appeals
DecidedFebruary 26, 2009
DocketSD 28949
StatusPublished
Cited by8 cases

This text of 279 S.W.3d 220 (Smith v. Dewitt and Associates, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Smith v. Dewitt and Associates, Inc., 279 S.W.3d 220, 2009 Mo. App. LEXIS 108, 2009 WL 474411 (Mo. Ct. App. 2009).

Opinion

DON E. BURRELL, Presiding Judge.

Barry Smith (“Plaintiff”) was injured by falling from a third-floor construction platform when a guardrail gave way. Plaintiff alleged in his petition that the guardrail failed because it had been taken down and re-installed multiple times, using the same nail holes. Plaintiff averred that this had *222 caused the guardrail to become loose and that this was not apparent to someone using the platform. Plaintiff brought his suit against the general contractor and several subcontractors, including Herrman Lumber Company — Branson, Inc. (“Herr-man”), alleging both premises liability and general negligence. Herrman filed a motion for summary judgment that was granted by the trial court and from which Plaintiff now appeals. We reverse and remand.

I.Facts and Procedural Background

Plaintiff sold and/or delivered cabinet fixtures for a construction project at The Falls Village Resort 1 (“the construction site” or “the site”). On September 7, 2006, Plaintiff was on Building 10 of the site to obtain cabinet fixture information when he came into contact with the wooden guardrail that gave way and allowed Plaintiff to fall to the ground. Plaintiff alleged that the general contractor, the siding contractor (alleged to be Herrman), and the painting contractor had all temporarily and repeatedly removed the guardrail to allow them to more easily deliver materials to the building’s upper floors. Plaintiff alleged they did so by utilizing the same nail holes, resulting in a loose attachment that created an unsafe and dangerous, hidden condition.

Herrman contended it was entitled to judgment as a matter of law because: 1) “it was not a contractor and did not deliver to the third floor of Building 10 nor work on Building 10;” and 2) “it owed Plaintiff ... no duty whatsoever.” In support of its contention that Herrman was not a contractor, Herrman attached the affidavit of Steve Maples, Herman’s manager, who denied Herrman was the siding contractor on Building 10. In support of its contentions that Herrman did not deliver to the third floor of Building 10, did not work on Budding 10, and owed no duty to Plaintiff, Herrman attached the affidavits of Maples and Wayne Greeno, a Herrman employee who had made deliveries to the construction site on August 31, 2006 — about a week prior to Plaintiffs fall. Maples’s affidavit stated in relevant part:

4. Deliveries made by [Herrman] for Buildings 10 and 11 on or about September 7, 2006 to the best of my information and belief were either to the job site trailer or the designated fenced in holding area.
5. [Herrman] made no deliveries to the third floor of Building No. 10 on or about September 7, 2006.

Greeno’s affidavit stated, in relevant part:

2. All deliveries I made were to the ground-level fenced in holding area provided at The Falls Village Resort.
3. I have never, and to the best of my knowledge, information and belief, none of our drivers made deliveries to either Building 10 or 11 while under construction on or about September 7, 2006.
4. I have never been to the third floor of Building 10.

On November 6, 2007, Plaintiff filed both a response to Herman’s motion for summary judgment and an affidavit supporting a request that the trial court grant a continuance of any ruling on Herman's motion for summary judgment so that Plaintiff could conduct additional discovery as to the other Hen-man employees who had been listed in Herman's previous discovery responses as having made deliveries to the construction site. Those previous responses indicated that Herman had two other identified delivery persons and *223 one unknown delivery person who had delivered materials to the construction site prior to the date of Plaintiffs fall.

On December 3, 2007, Plaintiff filed a supplemental response to Herrman’s statement of uncontroverted facts, attaching an interrogatory response by the general contractor listing “unknown employees of ... Herrman Lumber” 2 in response to Plaintiffs interrogatory request for “the name ... of any persons known to you ... who were present when the ‘guardrails,’ on the ‘construction property,’ described in the Petition would have been installed, adjusted, inspected, and/or removed/replaced.”

On January 14, 2008, the court denied Plaintiffs motion for additional time to conduct further discovery on the issues raised in Herrman’s motion for summary judgment by docket entry and entered the summary judgment Plaintiff now appeals.

II. Standard of Review

In determining whether a trial court has properly granted summary judgment, we review the matter de novo and give no deference to the trial court’s decision. City of Springfield v. Gee, 149 S.W.3d 609, 612 (Mo.App. S.D.2004); Murphy v. Jackson Nat’l Life Ins. Co., 83 S.W.3d 663, 665 (Mo.App. S.D.2002). We employ the same criteria the trial court should have used in deciding whether to grant the motion. Barekman v. City of Republic, 232 S.W.3d 675, 677 (Mo.App. S.D.2007) (citing Stormer v. Richfield Hosp. Serv., Inc., 60 S.W.3d 10,12 (Mo.App. E.D.2001)).

We review the record in the light most favorable to the party against whom judgment was entered and accord the non-movant the benefit of all reasonable inferences. ITT Commercial Fin. Corp. v. Midr-Am. Marine Supply Corp., 854 S.W.2d 371, 376 (Mo. banc 1993). As in this case, a “defending party” may establish a right to summary judgment by showing;

(1) facts that negate any one of the claimant’s elements facts, (2) that the non-movant, after an adequate period of discovery, has not been able to produce, and will not be able to produce, evidence sufficient to allow the trier of fact to find the existence of any one of the claimant’s elements, or (3) that there is no genuine dispute as to the existence of each of the facts necessary to support the movant’s properly-pleaded affirmative defense.

Id. at 381. “[A] ‘genuine issue’ exists where the record contains competent materials that evidence two plausible, but contradictory, accounts of the essential facts.” Id. at 382.

III. Discussion

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Joseph Zygler v. Hawkins Construction
Missouri Court of Appeals, 2020
Clyde Woodall v. Christian Hospital NE-NW
473 S.W.3d 649 (Missouri Court of Appeals, 2015)
Green v. Arizona Cardinals Football Club LLC
21 F. Supp. 3d 1020 (E.D. Missouri, 2014)
City of Kimberling City v. Leo Journagan Construction Co.
337 S.W.3d 48 (Missouri Court of Appeals, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
279 S.W.3d 220, 2009 Mo. App. LEXIS 108, 2009 WL 474411, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smith-v-dewitt-and-associates-inc-moctapp-2009.